Results of Bid Opening - Project VA ST NASA 1(8).pdf
PDF 109 KB Posted
- Solicitation number
- 693C73-20-B-000015
About this file
This document summarizes the results of a bid opening for the rehabilitation of the Wallops Island Causeway Bridge project VA ST NASA 1(8). The project consists of repairing concrete beams, resealing expansion joints, repairing concrete beams using glass fiber reinforced polymer, and other miscellaneous work. The project will be split into multiple work schedules and contract options with a total expected cost between $1,000,000 to $5,000,000. Four contractors submitted bids ranging from $3,606,356 to $5,473,025.44. The engineer's estimate was $4,417,810. Curtis Contracting, Inc. provided the lowest bid of $4,486,174. The performance period to complete all contract work is 440 calendar days.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
NASA Wallops Island Causeway Bridge
PROJECT: VA ST NASA 1(8)
SOLICITATION NO. 693C73-20-B-000015
June 2, 2020 at 2:00 p.m.
Sterling, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-20-B-000015 Project: VA ST NASA 1(8) June 2, 2020, 2:00 p.m. local time
BIDDER’S BID TOTALS TOTAL PRICE
Curtis Contracting, Inc. SCHEDULE A
$3,466,003.00
OPTION 1
$300,590.00
OPTION 2
$197,484.00
OPTION 3
$522,097.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3
$4,486,174.00
Kovilic Construction Company SCHEDULE A
$3,445,600.00
OPTION 1
$360,890.00
OPTION 2
$497,945.00
OPTION 3
$531,145.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3
$4,835,580.00
If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all contract work will be 440 calendar days
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-20-B-000015 Project: VA ST NASA 1(8) June 2, 2020, 2:00 p.m. local time
BIDDER’S BID TOTALS TOTAL PRICE
Titan Industrial Services, Inc SCHEDULE A
$3,414,849.50
OPTION 1
$650,015.00
OPTION 2
$211,195.00
OPTION 3
$1,196,965.94
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3
$5,473,025.44
Freyssinet, Inc. SCHEDULE A
$2,419,262.00
OPTION 1
$574,890.00
OPTION 2
$297,705.00
OPTION 3
$314,499.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3
$3,606,356.00
Engineer’s Estimate SCHEDULE A $2,500,000,00
OPTION 1
$796,640.00
OPTION 2
$537,820.00
OPTION 3
$583,350.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3
$4,417,810.00
If the Government awards the contract as Schedules A + B + C + D, the performance period to complete all contract work will be 440 calendar days
| Slide Number 1 |
| FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-20-B-000015 Project: VA ST NASA 1(8)�June 2, 2020, 2:00 p.m. local time � |
| FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-20-B-000015 Project: VA ST NASA 1(8)�June 2, 2020, 2:00 p.m. local time � |
File details come from the government source that posted it. Updated .