RFQ6933A225Q000003 JRRF PF204 Patrol Boat DryDocking QA1.pdf
PDF 118 KB Posted
- Attached to
- PF204 Patrol Boat Dry Docking
- Solicitation number
- 6933A225Q000003
About this file
This is a Questions & Answers document for RFQ6933A225Q000003, regarding the dry docking of MARAD PF204 Patrol Boat. The document addresses four key inquiries about the project specifications and timeline.
The Q&A clarifies that while the Period of Performance (POP) is 45 days, it can be extended up to 60 days total with a 15-day extension. The document specifies aluminum plating requirements: 3/16" from gunwale to chine, 1/4" for the bottom from bow to frame 11, and 5/16" from engine-room bulkhead to stern. Vessel plans are available through a provided defense.gov link. The quote submission deadline has been extended from February 21, 2025, to February 28, 2025, with an anticipated award date of March 28, 2025.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers #1
RFQ6933A225Q000003 MARAD PF204 Patrol Boat Dry Docking
Question 1: Is there flexibility in the stated 45-day period of performance?
Answer: Yes, we can be flexible, sixty (60) days wouldn’t be unusual. If so, how should that be indicated in the bid submission beyond the supporting documentation required, which indicates the start and finish dates for the performance of work items? POP is 45 days with a possible extension of 15 days, at no time will the POP exceed 60 total days.
Question 2: What are the full specs for the 3/16 aluminum to be used for the hull plating repairs?
Answer: 3/16th aluminum from the gunwale to the chine, ¼” bottom of the boat from the bow to frame 11 (aft of the engine-room bulkhead), and 5/16” aluminum from the engine-room bulkhead to the stern.
Question 3: Please confirm how we would be able to obtain a set of plans for the vessel.
Answer: Plans can be found at the following link:
https://media.defense.gov/2019/Nov/14/2002210729/-1/-1/0/41_FOOT_UTB_MODEL-
PLANS.PDF
Question 4: Based on the quote submission deadline of February 21, 2025, what is the anticipated award date?
Answer: The quote submission deadline is extended to February 28, 2025. The anticipated award date is March 28, 2025 https://media.defense.gov/2019/Nov/14/2002210729/-1/-1/0/41_FOOT_UTB_MODEL-PLANS.PDF https://media.defense.gov/2019/Nov/14/2002210729/-1/-1/0/41_FOOT_UTB_MODEL-PLANS.PDF
File details come from the government source that posted it. Updated .