6923G525Q0667 QA.pdf

PDF 77 KB Posted

Attached to
Cleaning of Asbestos - Contaminated Crawl Spaces (Eisenhower Lock Tunnel)
Solicitation number
6923G525Q0667
Issued by

About this file

This document is a Questions and Answers (Q&A) file for solicitation 6923G525Q0667. The Q&A addresses two key inquiries: first, confirmation of an available asbestos survey report (which is attached), and second, clarification on wage determination and project details. The contract is subject to the Service Contract Act Wage Determination #2015-4169, with work anticipated to start on or about October 1st, 2025. GLS will supply water and power for the project, and offerors have discretion in determining their technical approach and labor categories.

View the file

Other files

File Type Posted
cementitios pipe_Redacted.pdf PDF
6923G525Q0667A00001.pdf PDF
Attachment B_Pricing Sheet.xlsx XLSX spreadsheet
RFQ 6923G525Q0667.pdf PDF
Attachment D_Reference Drawings.pdf PDF
Attachment C_Service Contract Act WD 2015-4169.pdf PDF
Attachment A_PWS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6923G525Q0667

QuesƟons and Answers

# QuesƟon Answer

1 Could you kindly confirm if an asbestos survey or report is available, and if so, share it with us?

Report is aƩached.

2 What wages are we using, so we're all on the same page? When will this work start? To confirm, you will supply water and power.

This contract is subject to the Service Contract Act Wage DeterminaƟon # 2015-4169, provided as AƩachment C. The determinaƟon of technical approach and labor categories are at the discreƟon of each offeror.

Work is anƟcipated to start on or about October 1st, 2025.

GLS will supply water and power.