This is a Questions and Answers (Q&A) amendment to a federal solicitation addressing clarifications on project requirements and specifications.

Solicitation No. 6913G626Q300051 / Amendment 00002 addresses four key questions from potential contractors. The project is subject to prevailing wage requirements, with the Wage Determination document for Delaware provided in the solicitation package. Contractors should base pricing estimates on 20 feet for borings and wells, as this estimate is appropriate based on previous investigations at adjacent operable units. Regarding materials, five drums for soil cuttings and development water has been deemed acceptable for the initial contract; however, the U.S. DOT Volpe Center will acquire additional drums through a separate purchase if needed. Well covers must be stick-up style as specified in Section 3.4 of the Statement of Work, not flush mount. All other terms and conditions of the original solicitation remain unchanged.

View the file

Other files for this federal contract opportunity

Other files attached to Drilling and Related Services, newest first.
File Type Posted
V3262202 Evaluation Criteria_REV 1.pdf PDF
V3212060 TAR Clauses_.pdf PDF
FAR Clauses_Terms and Conditions.pdf PDF
SOW_Attachment1_FieldSamplingPlan.pdf PDF
FAR 52.212-4.pdf PDF
V3262202 Evaluation Criteria.pdf PDF
FortDuPont_Drilling_SOW_7-15-26 Rev1 (1).pdf PDF
WAGE Determination_Delaware.pdf PDF
TAR Payment Clause.pdf PDF
SOW_Attachment2_VolpeSOPs.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. 6913G626Q300051 / Amendment 00002 – Adress Questions

All other terms and conditions remain the same

1. Is this prevailing wage project? The Wage Determination document for

Delaware has been provided in the solicitation.

2. Should we base our pricing off 20 feet for borings and wells? Based on information obtained from previous investigations at adjacent operable units, this estimate is appropriate.

3. 5 drums seem light for soil cuttings and development water. The U.S. DOT Volpe Center will acquire additional drums through a separate purchase if needed.

4. (Well Covers) is this a stick up or flush mount? A stick up well cover shall be used as specified in Section 3.4 of the Statement of Work.