This document appears to be a set of design drawings for the installation of new steel poles and catenary wires as part of the Lowell National Historical Park Trolley System project. The drawings provide detailed specifications and installation instructions for the new steel poles, including pole foundations, grounding/lightning protection, crossarm connections, and catenary wire anchoring. Key details include:

The project is for the Department of Transportation Volpe Transportation Systems Center under Contract No. 6913G621P800012. The drawings are issued for construction and identify specific pole locations and types of work required at each pole, such as removing and replacing existing wooden poles, installing new steel poles, and modifying crossarms and catenary wires. The drawings also include several installation details and notes providing requirements for the new steel pole design, foundation, grounding, and catenary wire connections.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHEET TITLE

SHEET 1 OF 4

CO

NS

UL

TA

NT

S

DE

SC

RI

PT

IO

N

PROJECT NO: 20035-00-00020

MODEL FILE: COVERSHEET.dwg

DRAWN BY:

CHK'D BY:

COPYRIGHT WATERMARK 2019

MA

RK

DA

TE

CAM

JS

PR

EP

AR

ED

F

OR

DO

T

- V

OL

PE

C

EN

TE

R

LO

W

EL

L, MA

LO

W

EL

L N

AT

IO

NA

L H

IS

TO

RI

CA

L P

AR

K

TR

OL

LE

Y

SY

ST

EM

GE

OT

EC

H

IN

VE

ST

IG

AT

IO

N

AN

D

NE

W S

TE

EL

P

OL

E

DE

SI

GN

IS

SU

ED

F

OR

C

ON

ST

UC

TI

ON

5-

-2

LOWELL, MA

LOWELL NATIONAL HISTORICAL PARK

TROLLEY SYSTEM

PROJECT LOCATION

MARKET ST

MIDDLE ST

MERRIMACK ST

SH

AT

TU

CK

ST

DU

MMER

ST

LU

CY

LA

RC

OM

PA

RK

AR

CA

ND

D

R

FATHER MORISSETTE BLVD

DU

TT

ON

ST

KIR

K S

T

BR

OAD

WAY

ST

LEW

IS ST

MARKET ST

GEOTECHNICAL INVESTIGATION AND NEW STEEL POLE DESIGN

DRAWING LIST

SHEET NO. TITLE

G-1 COVER SHEET

C-1 SITE PLAN

C-2 DETAIL SHEET

C-3 CATENARY POLE SCHEDULE AND DETAILS

DEPARTMENT OF TRANSPORTATION (DOT) VOLPE TRANSPORTATION SYSTEMS CENTER

CONTRACT NO. 6913G621P800012

DR

AW

IN

G

NO

PM

IS

/P

KG

N O.

SH

EE

T 1 O

F

Mike.Buonopane Inserted Text

DUTTON STREET

MERRIMACK CANAL

011010009008007006

BUMPING POST

"SWAMP LOCKS"

TROLLEY STATION STOP

"DUTTON ST. SPUR

AT SWAMP LOCKS"

BROADW

AY STREET

MARKET STREET

GRADE CROSSING GRADE CROSSING

0 1 2 3 4 5 6 7 8 9 10

11 12

13 14

EP 2+58

N001B N001A

N003

N005 N006 N007 N008 N009 N0010 R002 R004

R011A (RENUMBER

AS POLE 011)

R012 R013 R014 R015 R016 R017 R018 R019 R020

046A

043A

045A

045B

047A

032D 032C

032B032A

027026

DUTTON STREET

NATIONAL STREETCAR MUSEUM

"MACK PLAZA"

TROLLEY STATION STOP

MOODY STREET FEEDER

GATEHOUSE STATION

MERRIMACK STREET

AR

CA

ND

D

RI

VE

GRADE CROSSING

PEDESTRIAN CROSSING (CONC.)

MERRIMACK CANAL

"MOODY STREET FEEDER

GATEHOUSE SPUR"

END OF USABLE TRACK

LUCY LARCOM PARK

LOWELL HIGH SCHOOL

LOWELL HIGH SCHOOL

GRADE CROSSING

GRADE CROSSING

15 16 17 18 19 20

EP 1+23

21 22 23 24 25 26 27 28

14EP 2+20

"SUFFOLK MILLS TO WYE" TRACK

EP

+6

GRADE CROSSING

FATHER

MORISSETTE BLVD.

N029 (MOVE

OFF SIDEWALK)

R043R041R040R039R038R037R036R035R034R033 R031R030

N029R028 R022

N003

R004

SHEET TITLE

SHEET 2 OF 4

CO

NS

UL

TA

NT

S

DE

SC

RI

PT

IO

N

PROJECT NO: 20035-00-00020

MODEL FILE: C-1.dwg

DRAWN BY:

CHK'D BY:

COPYRIGHT WATERMARK 2021

MA

RK

DA

TE

SCALE: 1" = 60'

GEOTECH INVESTIGATION AND NEW STEEL POLE DESIGN (POLES 001 TO 020)

PR

EP

AR

ED

F

OR

DO

T

- V

OL

PE

C

EN

TE

R

LO

W

EL

L, MA

LO

W

EL

L N

AT

IO

NA

L H

IS

TO

RI

CA

L P

AR

K

TR

OL

LE

Y

SY

ST

EM

GE

OT

EC

H

IN

VE

ST

IG

AT

IO

N

AN

D

NE

W S

TE

EL

P

OL

E

DE

SI

GN

CAM

JS

SCALE: 1" =60'

GEOTECH INVESTIGATION AND NEW STEEL POLE DESIGN (POLES 021 TO 043)

KEY

NOTES:

IS

SU

ED

F

OR

C

ON

ST

UC

TI

ON

5-

-2

DR

AW

IN

G

NO

PM

IS

/P

KG

N O.

SH

EE

T 2 O

F

AutoCAD SHX Text SEE DETAIL 9 DRAWING C-3 FOR POLES N001A AND N001B INSTALLATION DETAILS FOR ANCHORING CATENARY WIRE.

AutoCAD SHX Text

POLE 001 IS AN EXAMPLE OF DESIRED NEW STEEL POLE DESIGN.

AutoCAD SHX Text CATENARY POLE TYPE D: INSTALL NEW LONGER 2 " DIA. (SCH. 40 GALVANIZED) 12" DIA. (SCH. 40 GALVANIZED) CROSSARM 20'-6" IN LENGTH AT REPLACEMENT POLE R004 TO CARRY NEW CATENARY WIRE FOR DUTTON STREET SPUR. (SEE NOTE 11)

AutoCAD SHX Text CATENARY POLE TYPE C (POLE N003) TO INCLUDE TWO NEW CROSSARMS LOCATED AT 90° TO EACH RAIL SPUR TOPICK UP CATENARY WIRE FOR BOTH SPURS (SEE NOTE 11)

AutoCAD SHX Text GROUNDING AND LIGHTNING PROTECTION IS REQUIRED AT POLE N001A. SEE DETAIL 3 DRAWING C-2.

AutoCAD SHX Text

WYE

AutoCAD SHX Text REMOVE POLES 032A, 032B, 032C, 032D AND CATENARY WIRE TO ABANDONED MOODY ST. FEEDER SPUR

AutoCAD SHX Text MOVE TELECOMMUNICATIONS CABLE FROM POLE 032A TO POLE 033. COIL EXCESS CABLE NEATLY ON POLE 033.

AutoCAD SHX Text

EXISTING POLE LOCATION AND NUMBER

AutoCAD SHX Text

NEW POLE IN NEW LOCATION AND NUMBER

AutoCAD SHX Text

EXISTING CATENARY WIRE

AutoCAD SHX Text

NEW CATENARY WIRE

AutoCAD SHX Text

REPLACE POLE IN SAME LOCATION AND NUMBER

AutoCAD SHX Text

AutoCAD SHX Text 60'

AutoCAD SHX Text 120'

AutoCAD SHX Text Scale: 1" = 60'-0"

AutoCAD SHX Text

1. POWER TO THE CATENARY WIRE WILL BE TURNED OFF BY THE LOWELL NATIONAL HISTORICAL POWER TO THE CATENARY WIRE WILL BE TURNED OFF BY THE LOWELL NATIONAL HISTORICAL PARK FOR THE DURATION OF THE PROJECT. THE CONTRACTOR SHALL HAVE A LICENSED ELECTRICIAN CONFIRM THAT THE POWER IS OFF PRIOR TO WORK AT EACH LOCATION. 2. COMMUNICATION CABLING MUST BE PROTECTED DURING THE REMOVAL AND REPLACEMENT COMMUNICATION CABLING MUST BE PROTECTED DURING THE REMOVAL AND REPLACEMENT PROCESS. ALL COMMUNICATION CABLES WILL REMAIN OPERATIONAL FOR THE DURATION OF THE PROJECT. THE CONTRACTOR IS RESPONSIBLE TO ENSURE THAT NO DISRUPTION OF SERVICE OCCURS. 3. DURING REMOVAL OF EXISTING WOODEN POLES AND INSTALLATION OF NEW STEEL POLES, SUPPORT DURING REMOVAL OF EXISTING WOODEN POLES AND INSTALLATION OF NEW STEEL POLES, SUPPORT THE EXISTING CATENARY AND TELECOMMUNICATIONS CABLE AND CROSSARMS AS NECESSARY SO THAT EXISTING WIRING AND CROSSARMS TO BE REINSTALLED ON THE NEW STEEL POLES ARE NOT DAMAGED. 4. GUY WIRES ON EXISTING WOODEN POLES AND IN OTHER LOCATIONS AS NOTED ARE TO BE GUY WIRES ON EXISTING WOODEN POLES AND IN OTHER LOCATIONS AS NOTED ARE TO BE REMOVED AND DISPOSED. GUY WIRE ANCHORS ARE TO BE CUT 2 INCHES BELOW GRADE AND REMOVED AND DISPOSED. 5. NEW STEEL POLE HEIGHTS TO MATCH EXISTING, UNLESS OTHERWISE NOTED. THE CONTACTOR NEW STEEL POLE HEIGHTS TO MATCH EXISTING, UNLESS OTHERWISE NOTED. THE CONTACTOR SHALL FIELD MEASURE EACH POLE LOCATION TO CONFIRM EXISTING POLE CROSSARM HEIGHTS SUCH THAT NEW STEEL POLES WILL ACCEPT EXISTING CROSSARMS AT THE PROPER HEIGHT. 6. SEE CATENARY POLE SCHEDULE (SHEET C-3) FOR WORK REQUIRED AT EACH POLE LOCATION. SEE CATENARY POLE SCHEDULE (SHEET C-3) FOR WORK REQUIRED AT EACH POLE LOCATION. 7. CATERNARY WIRING TO BE RE-TENSIONED AND TESTED FOLLOWING COMPLETION OF NEW STEEL CATERNARY WIRING TO BE RE-TENSIONED AND TESTED FOLLOWING COMPLETION OF NEW STEEL POLE INSTALLATIONS. 8. WHERE TREE TRIMMING IS REQUIRED, ALL LIMBS WITHIN 3 FEET OF CATENARY AND WHERE TREE TRIMMING IS REQUIRED, ALL LIMBS WITHIN 3 FEET OF CATENARY AND TELECOMMUNICATIONS CABLE ARE TO BE REMOVED AND DISPOSED OF PROPERLY. 9. EXISTING WOODEN POLES SCHEDULED FOR REPLACEMENT ARE TO BE REMOVED AND DISPOSED OF EXISTING WOODEN POLES SCHEDULED FOR REPLACEMENT ARE TO BE REMOVED AND DISPOSED OF PROPERLY. WHERE NEW LOCATIONS ARE IDENTIFIED POLES MAY BE CUT 2 INCHES BELOW GRADE. BACKFILL TO MATCH ADJACENT SURFACE. 10. NEW STEEL POLE ALIGNMENT MUST BE SET SO THAT RE-INSTALLED CROSSARM IS LEVEL AND AT NEW STEEL POLE ALIGNMENT MUST BE SET SO THAT RE-INSTALLED CROSSARM IS LEVEL AND AT 90° TO THE CATENARY WIRE. MAINTAIN EXISTING CROSSARM HEIGHTS AT ALL REPLACEMENTS.11. CATENARY WIRE FITTINGS AND INSULATORS ETC. REQUIRED TO CONSTRUCT NEW CROSSARMS AT CATENARY WIRE FITTINGS AND INSULATORS ETC. REQUIRED TO CONSTRUCT NEW CROSSARMS AT POLES N003 AND R004 MAY BE SALVAGED FROM OTHER POLES/CROSSARMS THAT ARE TO BE REMOVED.

SHEET 3 OF 4

CO

NS

UL

TA

NT

S

DE

SC

RI

PT

IO

N

PROJECT NO: 20035-00-00020

MODEL FILE: C-2.dwg

DRAWN BY:

CHK'D BY:

COPYRIGHT WATERMARK 2021

MA

RK

DA

TE

PR

EP

AR

ED

F

OR

DO

T

- V

OL

PE

C

EN

TE

R

LO

W

EL

L, MA

LO

W

EL

L N

AT

IO

NA

L H

IS

TO

RI

CA

L P

AR

K

TR

OL

LE

Y

SY

ST

EM

GE

OT

EC

H

IN

VE

ST

IG

AT

IO

N

AN

D

NE

W S

TE

EL

P

OL

E

DE

SI

GN

CAM

JS

SCALE: N.T.S.

DETAIL 4 - TYPICAL CATENARY

POLE - TYPE A

SCALE: N.T.S.

DETAIL 6 - TYPICAL CATENARY POLE -

CROSS ARM CONNECTION

SCALE: N.T.S.

DETAIL 5 - TYPICAL CATENARY

POLE - TYPE B

SCALE: N.T.S.

DETAIL 2 - NEW STEEL POLE

FOUNDATION

SCALE: N.T.S.

DETAIL 1 - TYPICAL NEW STEEL

CATENARY POLE

SCALE: N.T.S.

DETAIL 3 - NEW STEEL POLE GROUNDING

AND LIGHTNING PROTECTION

IS

SU

ED

F

OR

C

ON

ST

UC

TI

ON

5-

-2

DR

AW

IN

G

NO

PM

IS

/P

KG

N O.

SH

EE

T 3 O

F

AutoCAD SHX Text

SEE TYPICAL CATENARY POLE - TYPE A FOR WORK ON CATENARY GUY WIRES AND CROSSARM.

AutoCAD SHX Text FABRICATE NEW UPPER CROSSARM. DETACH AND RE-ATTACH EXIST POWER LINES AND COMMUNICATIONS CABLES.

AutoCAD SHX Text EXISTING INSULATORS, CROSSARM SUPPORTS AND CONNECTION TO CATENARY WIRE TO REMAIN.

AutoCAD SHX Text

REMOVE AND REPLACE UPPER GUY WIRE

AutoCAD SHX Text

ATTACH NEW GUY WIRES TO NEW STEEL POLE

AutoCAD SHX Text REMOVE EXISTING CROSSARM CONNECTION AND RE-ATTACH EXISTING CROSSARM TO NEW STEEL POLE

AutoCAD SHX Text

2'-0" DIAMETER

AutoCAD SHX Text

SONOTUBE

AutoCAD SHX Text

6'-0" DEPTH

AutoCAD SHX Text

POLE CAP

30'-0"

AutoCAD SHX Text

GROUND SLEEVE

AutoCAD SHX Text

GROUND LINE

GENERAL NOTES: : 1. POLES TO CONFORM TO MBTA SPECIFICATION P-22-H. THEY SHALL POLES TO CONFORM TO MBTA SPECIFICATION P-22-H. THEY SHALL HAVE A FINISH COAT OF EPOXY PAINT COMPATIBLE WITH THE PRIMER COAT AND APPLIED AT THE FACTORY. COLOR TO CONFORM TO FEDERAL COLOR STANDARD 595A, COLOR 24036, GREEN. 2. POLE HOLES TO BE AUGERED OR HAND EXCAVATED. UNSTABLE SOIL POLE HOLES TO BE AUGERED OR HAND EXCAVATED. UNSTABLE SOIL TO HAVE STEEL CAISSON INSERTED INTO SOIL AS EXCAVATION PROCEEDS TO KEEP HOLE FROM COLLAPSING. 3. POLE TO BE DIRECTLY EMBEDDED INTO POLE HOLE AND REST POLE TO BE DIRECTLY EMBEDDED INTO POLE HOLE AND REST AGAINST BARE SOIL. POLE TO BE PROPERLY RAKED AND SUPPORTED THEN CONCRETE TO BE POURED INTO HOLE. CONCRETE TO BE 4,000 PSI-3/8" AGGREGATE. 4. THE BOTTOM SURFACE OF THE BUTT PIPE SECTION THAT BARES THE BOTTOM SURFACE OF THE BUTT PIPE SECTION THAT BARES AGAINST SOIL SHALL BE CLEANED TO BARE METAL TO INSURE A GOOD ELECTRICAL EARTH GROUND. 5. LENGTH OF BUTT SECTION BELOW GROUND LINE SHALL CORRESPOND LENGTH OF BUTT SECTION BELOW GROUND LINE SHALL CORRESPOND TO THE DEPTH OF THE FOUNDATION SHOWN IN DETAIL 2.

AutoCAD SHX Text

SEE FOUNDATION DETAIL SHEET C-2

AutoCAD SHX Text

(DIA = 10.75")

AutoCAD SHX Text

(DIA = 8.625")

AutoCAD SHX Text NOTE: FOR BOTH CATENARY POLE TYPES A & B, PROVIDE A SHOP DRAWING/FABRICATION DRAWING DETAILING THE NEW CROSSARMS, COMMUNICATION CABLE CONNECTIONS, AND GUY WIRE AND CROSSARM CONNECTIONS TO NEW STEEL POLE, FOR REVIEW AND APPROVAL.

AutoCAD SHX Text NOTES: 1. CATENARY POLE TYPE C (POLE N003) - PROVIDE TWO NEW CROSSARMS CATENARY POLE TYPE C (POLE N003) - PROVIDE TWO NEW CROSSARMS AT 90° TO EACH RAIL SPUR, INCLUDING CATENARY WIRE INSULATORS,CONNECTORS AND GUY WIRES TO PICK UP CATENARY WIRE FOR BOTH THE SWAMP LOCKS AND DUTTON ST. SPURS . 2. PROVIDE A 4 INCH STEEL CHANNEL CONNECTING POLES N001A AND N001B PROVIDE A 4 INCH STEEL CHANNEL CONNECTING POLES N001A AND N001B AT THE HEIGHT OF THE CATENARY WIRE. PROVIDE BOLTED EYE CONNECTION TO TERMINATE THE DUTTON ST. SPUR CATENARY WIRE AT THE CENTER OF THE CHANNEL BETWEEN THE TWO NEW POLES. (SEE DETAIL 9, SHEET C-3)

AutoCAD SHX Text

#4 AWG COPPER WIRE (INSULATED)

AutoCAD SHX Text 1" FRE CONDUIT CLAMP TO POLE WITH CONDUIT CLAMPS (x3)

AutoCAD SHX Text 6'-0"

AutoCAD SHX Text 6"

AutoCAD SHX Text

ARRESTOR BLOCK

AutoCAD SHX Text LIGHTNING ARRESTOR (EATON COOPER POWER SERIES DISTRIBUTION ARRESTOR, OR APPROVED EQUAL)

AutoCAD SHX Text

TROLLEY WIRE OR FEED TAP

AutoCAD SHX Text

4/O CABLE

AutoCAD SHX Text

POLE

AutoCAD SHX Text

ROD (TYP)

AutoCAD SHX Text 12"

AutoCAD SHX Text NOTES: 1. GROUND ROD TO BE "x6'-0" (MIN.) GROUND ROD TO BE "x6'-0" (MIN.) 58"x6'-0" (MIN.) COPPERWELD. 2. CABLE CONNECTIONS TO GROUND ROD CABLE CONNECTIONS TO GROUND ROD AND POLE BY EXOTHERMIC WELDING

AutoCAD SHX Text

REMOVE AND REPLACE LOWER GUY WIRE FROM INSULATOR TO NEW STEEL POLE

AutoCAD SHX Text

INSTALL NEW GALVANIZED STEEL TURNBUCKLES WITH LOCKS ON UPPER AND LOWER GUY WIRES

AutoCAD SHX Text

GUY WIRE CONNECTION (SEE DETAIL 7, SHEET C-3)

AutoCAD SHX Text FINAL LENGTH OF CROSSARM MUST MAINTAIN CATENARY WIRE AT CENTER OF TRACK. CUT EXISTING CROSSARMS, OR ADD LENGTH WITH COUPLINGS, AS NECESSARY TO MAINTAIN REQUIRED DIMENSION

GALVANIZED STEEL SERVICE SADDLE WITH SET BOLT TO ACCEPT EXISTING CROSSARM (SEE INSET PHOTO) AND (SEE DETAIL 10, SHEET C-3)

SHEET 4 OF 4

CO

NS

UL

TA

NT

S

DE

SC

RI

PT

IO

N

PROJECT NO: 20035-00-00020

MODEL FILE: C-3.dwg

DRAWN BY:

CHK'D BY:

COPYRIGHT WATERMARK 2019

MA

RK

DA

TE

CAM

JS

PR

EP

AR

ED

F

OR

DO

T

- V

OL

PE

C

EN

TE

R

LO

W

EL

L, MA

LO

W

EL

L N

AT

IO

NA

L H

IS

TO

RI

CA

L P

AR

K

TR

OL

LE

Y

SY

ST

EM

GE

OT

EC

H

IN

VE

ST

IG

AT

IO

N

AN

D

NE

W S

TE

EL

P

OL

E

DE

SI

GN

SCALE: N.T.S.

DETAIL 10 - STEEL POLE

CROSSARM ATTACHMENT

SCALE: N.T.S.

DETAIL 11 - BELL CAP FOR STEEL POLES

SCALE: N.T.S.

DETAIL 7 - TYPICAL GUY WIRE

CONNECTION TO NEW STEEL POLES

SCALE: N.T.S.

DETAIL 8 - TYPICAL HIGH VOLTAGE FEED LINE

AND COMMUNICATION CABLES CROSSARM

DETAIL CATENARY POLE TYPE "B"

IS

SU

ED

F

OR

C

ON

ST

UC

TI

ON

5-

-2

DR

AW

IN

G

NO

PM

IS

/P

KG

N O.

SH

EE

T 4 O

F

SCALE: N.T.S.

DETAIL 9 - POLE N001A AND N001B

TERMINAL CHANNEL

AutoCAD SHX Text

NOTE:

AutoCAD SHX Text A PHYSICAL SAMPLE OF POLE CAP WILL BE PROVIDED UPON AWARD AS AN EXAMPLE OF DESIRED DESIGN

AutoCAD SHX Text

GALVANIZED STEEL DOUBLE BOLT PIPE CLAMP W/SPACERS

AutoCAD SHX Text

GALVANIZED STEEL SHACKLE W/LOCKING PIN

AutoCAD SHX Text

GUY WIRE

AutoCAD SHX Text

2-GALVANIZED U-BOLTS

AutoCAD SHX Text

HIGH VOLTAGE FEED LINES W/INSULATORS

AutoCAD SHX Text

4-INCH PAINTED STEEL CHANNEL (SAME PAINT SYSTEM AS POLE)

AutoCAD SHX Text

1 FT. MIN.

AutoCAD SHX Text

GALVANIZED SERVICE SADDLE

AutoCAD SHX Text

EXISTING 2" CROSSARM CUT TO PROPER LENGTH INSERTED INTO POLE PLATE

AutoCAD SHX Text

COMMUNICATION CABLE HUNG FROM BELOW CHANNEL

AutoCAD SHX Text

4" STEEL CHANNEL (SAME PAINT SYSTEM AS POLES)

AutoCAD SHX Text

2-GALVANIZED STEEL U-BOLTS (TYP)

AutoCAD SHX Text

3" GALVANIZED STEEL EYE BOLT TO ANCHOR CATENARY WIRE AT CENTER OF RAIL SPUR

AutoCAD SHX Text

POLE N001B