Attachment 002 Table of Borings.pdf
PDF 46 KB Posted
- Attached to
- Geotechnical Drilling Services for Project OR FLAP DOUGLAS 251(2), Winchester Bridge Replacement
- Solicitation number
- 69056727Q000006
About this file
This document is a Table of Borings specification for a geotechnical investigation supporting the Winchester Creek Bridge Replacement project in Oregon (FLAP Douglas 251(2)) scheduled for 2026. The investigation requires two bridge foundation borings (BH26-01 and BH26-02) at specified GPS coordinates near Winchester Creek. BH26-01 requires 30 feet of auger drilling and 80 feet of HQ core drilling to a maximum depth of 130 feet, with 30 Standard Penetration Tests (SPTs) and 2 Shelby samples, while performing suspension logging for seismic design. BH26-02 requires 30 feet of auger drilling and 20 feet of HQ core drilling to a maximum depth of 50 feet, with 14 SPTs and 2 Shelby samples. Both borings require truck-mounted rigs with traffic control and rolling closures, pavement patching, and utility avoidance measures.
The combined project totals 60 feet of auger drilling, 100 feet of HQ core drilling, 44 SPTs, and 4 Shelby samples across both locations. Critical specifications include HQ3 coring for all rock intervals, SPT sampling at 2.5-foot intervals (2.5, 5, 7.5, and 10 feet), and field verification of GPS coordinates due to their approximate nature. The document notes that all boring locations are subject to change based on proposed alignment alterations, with permitted relocations up to 50 feet from current positions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Borings - OR FLAP DOUGLAS 251(2) Winchester Creek Bridge Replacement - 2026 Geotechnical Investigation
Boring ID Purpose of Boring Latitude
Longitude 1 Estimated
Feet of Auger
Estimated Feet of Core (HQ)
Possible Maximum
Depth (ft)
Maximum
No. of SPTs
Subgrade
Samples
Possible
Shelby
Samples
Comments: Drill Type, Access, Instruments, etc.
BH26-01 Bridge Foundation 43.67511 -124.17883 30 80 130 30 0 2
Truck-mounted rig, traffic control/rolling closure, patch pavement. Underground utilities at approximate boring location shall be avoided. Perform suspension logging for seismic design.
BH26-02 Bridge Foundation 43.67497 -124.17833 30 20 50 14 0 2
Truck-mounted rig, traffic control/rolling closure, patch pavement. Underground utilities at approximate boring location shall be avoided.
60 100 180 44 0 4
NOTES: 1 GPS coordinates are approximate. Field locating is required.
2 SPT samples are on 2.5-ft intervals: 2.5, 5, 7.5, 10
3 HQ3 for all rock coring.
4 All boring locations are subject to change based on alterations to the proposed alignment. Borings may be moved up to 50 ft. from their current locations
TOTALS