QA_10-20-2026.pdf

PDF 180 KB Posted

Attached to
WY NP YELL 10(24), Grand Loop Road Norris to Golden Gate, Phase 3
Solicitation number
69056726R000020
Issued by

About this file

This is a Questions and Answers document for Project No. WY NP YELL 10(24), Grand Loop Road Norris to Golden Gate, Phase 3. The document does not address specific required products or services, but rather provides clarifications on project scope and scheduling matters.

Key details from the Q&A include: Slope scaling quantities will be quantified by hours needed to perform the work under an anticipated offer schedule for the Task Order solicitation, rather than as a lump sum amount under bid item 651-Rockfall Protection. Rock bolts and dowels are anticipated to be installed at slope scaling locations. Project specifications will be published during the winter 2026/2027 solicitation period, with a Notice to Proceed date planned for May 2027. Quantities for temporary traffic control items, including potential Portable Temporary Traffic Signal System (PTTS) components, will be provided in the project solicitation rather than as a standalone bid item. All answers were provided between October 5 and October 20, 2026.

View the file

Other files

File Type Posted
QA_10-05-2026.pdf PDF
Prelim Letter_WY NP YELL 10(24).pdf PDF
PROJECT DESCRIPTION_WY NP YELL 10(24).pdf PDF
yell10-24_Preliminary Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. WY NP YELL 10(24)

Project Grand Loop Road Norris to Golden Gate, Phase 3

# General Technical Question Answer Date

1 X

Are the scaling quantities for the areas to be scaled that are called out in the plans to be factored into the lump sum amount under 651-

Rockfall Protection?

An offer schedule will be developed for the

Task Order solicitation. Slope Scaling is anticipated to be quantified by Hours needed to perform the work.

10/5/26

2 X Are the rock bolts and dowels to be installed at the scaling locations?

Yes, Rock Bolts and Dowels are anticipated at the slope scaling locations.

10/5/26

3 X When will project specifications be published?

The Task Order is planned for solicitation during the winter 2026/2027.

10/5/26

4 X What is the anticipated NTP date for this project?

A Notice to Proceed date is being planned for May 2027.

10/5/26

5 X

Will a bid item be added to the solicitation for a

Portable Temporary Traffic Signal System

(PTTS)?

Quantities for temporary traffic control items will be provided in the project solicitation.

10/20/26

Check General or Technical

File details come from the government source that posted it. Updated .