WY NP GRTE 13(1), Repair North Park Road at Milepost 15. 8
Solicitation number
69056726R000006
Issued by

About this file

This document is a Questions and Answers (Q&A) file for a federal construction contract opportunity (Project No. WY NP GRTE 13(1)) regarding repair work on North Park Road at Milepost 15.8 in Grand Teton National Park.

The Q&A addresses five technical questions posed by potential bidders, with responses dated between April 7, 2026 and April 15, 2026. Key clarifications include: site access is available via US 26 despite seasonal closures on US 89 between Yellowstone and Grand Tetons; work will be scheduled to limit impacts during peak travel hours, with details to be provided in Amendment A001; temporary steel traffic barriers are a subsidiary contractor obligation with no separate pay item; flaggers may be used to supplement lump-sum temporary traffic signals as bid; and the National Park Service has reserved three campground sites at Flagg Ranch for contractor use, also to be addressed in Amendment A001. The responses reference relevant specification sections (156.07, 635.12, 635) and federal procurement standards (FP-24 109.05(b)), indicating this project involves traffic control management and temporary construction accommodations in a national park setting.

View the file

Other files

File Type Posted
QA_05-01-2026.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
QA_04-07-2026.pdf PDF
Wyo_FenceGuide.pdf PDF
WY NP GRTE Multi(1) Field Report from 2023-09-23.pdf PDF
grte13-1_plans.pdf PDF
RFP_69056726R000006_WY NP GRTE 13(1).pdf PDF
Trip Report 2024-07-30 WY NP GRTE 13(1) North Park Rd.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: WY NP GRTE 13(1), Project: Repair North Park Road at Milepost 15.8

# General Technical Question Answer Date

1 X Are roads currently open to access this site?

You can access the site - the road is open.

The only closure is between Yellowstone and Grand Tetons on US 89- that section is closed (typical seasonal closure). But you can access it from other directions i.e. via

US 26.

For road information, check out:

https://www.nps.gov/grte/planyourvisit/ro ads.htm#:~:text=The%20Teton%20Park%20

Road%20is,until%20it%20is%20snow%20co vered and https://map.wyoroad.info/.

4/7/26

2 X

Section 156.07, Public Traffic: Is all work expected to be conducted at night or will some daytime activities be permitted beyond basic maintenance?

Yes. Intent is to limit impacts to travelling public during peak travel hours. This will be addressed by Amendment A001.

4/15/26

3 X

635.12, Portable traffic Barriers: This section mentions that temporary steel barrier may be used. There is no pay item for barrier that I can find. Is this an oversight?

No. See FP-24 109.05(b). Barriers are a subsidiary obligation of the Contractor.

4/15/26

4 X

Section 635, Temp Traffic Control quantities:

There is a lump sum item for Temporary Traffic

Signals as well as a bid item for 700 hours of flagging. Are flaggers expected to be used on the project in addition to the Traffic Signals?

Flaggers may be used to augment

Temporary Traffic Signals. Bid as advertised.

4/15/26

5 X

I can find no mention of a designated campground site for Contractors. Will there be accommodations available for Contractors working on this project?

The NPS has reserved 3 sites at Flagg Ranch campground for contractor use. This will be addressed by Amendment A001.

4/15/26