WY NPS YELL 10(26), Gardner River High Bridge
Solicitation number
69056726R000002
Issued by

About this file

This document is a Questions and Answers (Q&A) file for the WY NPS YELL 10(26) Gardner River High Bridge project. The Q&A covers 15 technical questions from potential contractors, addressing various aspects of the bridge repair and restoration project. Key topics include project cost clarification (the estimated budget is $20-$30 million), expansion joint replacements, structural steel repairs, concrete repairs, catwalk system repairs, and temporary access limitations. The responses indicate that additional clarifications will be provided through forthcoming amendments, and contractors are advised to bid as shown in the current documentation. Specific areas of work include removing and replacing damaged bridge railing components, repairing pedestals, addressing erosion control, and handling potential overload/permit load requests for temporary support structures. The government will not provide contractor housing sites for this project.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WY NPS YELL 10(26),

Gardner River High Bridge

# General Technical Question Answer Date

1 X

I have one quick question in the RFP the project estimated magnitude is stated between $5,000,000 to $10,000,000. In the project description that was posted in September it was listed to be between $20,000,000 to $30,000,000. Did the scope of the project change a bunch?

. This is an error on our part, there is no change to the scope. The project estimated price range is $20 - $30 Million. This will be corrected in an amendment.

12/31/25

2 X

Plan Sheet N.2, N.7 & N.8 shows long tapers of concrete barrier rail from off the bridge ends to the start of the truss sections. My question is why the concrete barrier rail is not extended across the bridge to protect the workers in the work zone areas. The barrels as shown will not stop an out of control vehicle.

Per Note 6 on Plan Sheets N.7 and N.8, all traffic control devices are for informational purposes only and pertain to the provided traffic control plans. It is the responsibility of the contractor to provide effective traffic control that meets the requirements of FP- 24, the MUTCD, and all special contract requirements.

Please also note the requirements listed in SCR 156.06(d) for placement of temporary barriers, crash cushions, or crash attenuators, and SCR 563.04A for restriction on gross weight (vehicles, equipment, supplies, traffic control devices and all other loads on top of the deck).

1/8/26

Check General or Technical

3 X

On plan sheet S19 & S20 it states to expose full collar depth for epoxy injection using hand methods. This excavation could be up to 6’ of excavation on the uphill sides of the towers.

Would FHWA reconsider expanding the construction limits to the middle towers so this excavation can be performed with equipment?

Pleas bis as shown 1/8/26

4 X

It will be very difficult to construct containments for paint removal and repainting on the middle towers without having the construction limits expanded to the towers. Would FHWA consider expanding the construction limits to the middle two towers?

Pleas bis as shown 1/8/26

5 X

For the approach spans on plan sheet S4 it states to keep all existing transverse reinforcement. It is our understanding that one approach span was repaired in the past with UHPC. It will be very difficult not to damage the transverse bars during removal of the UHPC and other concrete. Would FHWA consider allowing mechanical splices or overlapping of new reinforcing to existing rebar near the barrier wall/curb?

Please bid as shown 1/8/26

6 X

Bid schedule contains Line Item No 0600 – Crack Repair by Epoxy Injection. Bid item is listed as LS. Based on the contract information provided, there is no way to determine a LF quantity for this item. Request that this item be changed to LF with an estimated qty, or at the least that an estimated qty be provided for the LS item so all bidders can be on the same page bidding this item.

This will be addressed via a forthcoming amendment.

7 X

Plan sheet S.10 shows details for Expansion Joint repairs on the project. Details for Existing Expansion Joint at Approach 1/Approach 2 have note stating “Remove expansion joint device and anchor bolts and replace according to proposed section”. It is unclear what is meant by this statement. Is this work just remove and reinstall the existing joints or are we to replace with new? Is the contractor to determine the “proposed section”?

Approach expansion joint to be replaced.

Please see “REPLACEMENT OF APPROACH

EXPANSION JOINT SECTION”,

“REPLACEMENT OF APPROACH EXPANSION

JOINT DETAIL”, and “REPLACEMENT OF

APPROACH EXPANSION JOINT PLAN”

directly below referenced existing sections on S.10 for replacement details.

1/8/26

8 X

Plan sheet S.14 shows details for Bridge Railing on Project. Work item 2 note references “Remove and replace damaged steel bridge railing system components (5 locations). There is no way to adequately price this work without more details. What are the components? Are they posts, are they rail sections, are they a combination of both? If railing, how many rail sections, how long? Please clarify details of work or make this a Contingent Sum item so work can be completed without shifting all the risk of unquantified/unclear work requirements onto the contractor.

Existing known damage to bridge railing documented in “1570-023P Special Study Inspection Report 2024.pdf”, see Photo #46, Photo #53, and Photo #54. Extent of each repair location is defined by a single post and the two adjacent spans of railing.

Additional clarification will be provided via a forthcoming amendment.

9 X

Plan sheet S.17 shows details for Misc Structural Steel Repairs. Note 5 states “Install high strength bolts in place of missing and misshapen/mis-installed rivets. Missing rivets at isolated locations…”. Where does this work measure and pay? It is not referenced in Line Item 0460 Misc Repair of Structural Steel and Bridge Rail item. Is the work to be done under a Contingent Sum or Change order? There is no way for a contractor to adequately quantify or price this work as shown. In numerous past projects requiring this type of work, a unit price bid item for Replacing Rivets with High Strength Bolts bid item has been provided in the bid schedule. Please either create a unit price bid item for this work, or at least provide an estimated qty for contractors to include in their bid.

Rivet work included in 55501-0000 Structural Steel (Misc. Repair of Structural Steel & Bridge Rail). Additional clarification will be provided via a forthcoming amendment.

1/8/26

10 X

Plan sheet S.22 shows details for Portal Breastwall Concrete Repair. Is this full depth repair? (IE, removing the entire breast wall to the limits shown). What class of concrete is to be used for this work? Section 572 Concrete Repair has multiple classes/types of concrete.

Please clarify.

Repair categorized as 572.04(b) Deep Repairs, and unsound concrete is anticipated for the full depth of the removal limits shown. The three classes of concrete shown in 572.03(a) Hydraulic Cement Concrete are all acceptable for use on repair area.

11 X

Plan sheet S.24 shows Catwalk Repair Details.

Line item A0480 in bid schedule references Catwalk Repair as a LS item. Work item 2 states “Replace missing or damaged/defective hardware, and correct improperly installed existing hardware. Replace damaged hardware as directed by CO.” Work item 5 states “Reset/correct any non-functional cable railing”.

Again, there are not enough details or quantities for a contractor to adequately price this work.

Please either clarify quantities of work required, or consider making this a Contingent Sum item sow work can be completed without shifting all the risk of unquantified/unclear work requirements onto the contractor.

See “1570-023P Special Study Inspection Report 2024.pdf” for documented defects of catwalk system. Additional clarification will be provided via a forthcoming amendment.

1/8/26

12 X

Plan sheets E.1 and E.2 show temporary access limits for the North and South Approaches.

What are the temporary access limits for Towers 1, 2 and 3? CFRP work at the pedestal bases, as well as ground anchoring of painting access/containment scaffold will be required here. Please clarify.

No temporary equipment access is provided. Additional clarification will be provided via a forthcoming amendment.

1/8/26

13 X Plan sheet F.3 shows pedestal repair erosion control plan. Is no erosion control required for Tower 3 pedestal repair?

Bid as shown 1/8/26

14 X

SCR Section 562.03 Temp Access Design references that contract is to evaluate all overload and permit load requests received for temporary support structure. Can owner provide any clarification on how many overload/permit load requests a contractor would expect to get for this section of highway for the duration of project?

Typical expectation of approximately 5 unique truck configurations per month for this structure.

15 X Are there any contactor camp sites available for this project?

There are no contractor housing sites being provided by the government as part of this project.

1/16/26