This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the Federal Highway Administration's Vancouver, Washington office on January 27, 2026, for the WY NPS YELL 10(26), Gardner River High Bridge project.

Amendment A002 revises language in Subsections 109.06 (Pricing of Adjustments) and 109.08 (Progress Payments) on pages E-31 through E-33a of the Special Contract Requirements. Key modifications include: (1) limiting profit on contract modifications to 10 percent of total cost, with provisions for lower profit following FAR 15.404-9 profit analysis; (2) clarifying that the Government's receiving report will be developed using measurements and quantities from pay notes received by the Contracting Officer in Masterworks and determined acceptable; (3) establishing a 15 percent variance threshold for equitable adjustment of unit-priced items with estimated quantities; (4) specifying invoice submission deadlines with different timelines for September-July work (7th day after closing) and August work (5th day after closing), along with consequences for late submissions; (5) detailing procedures for processing proper and defective invoices with specific notification and correction timelines; (6) defining partial payment limitations for material and preparatory work not exceeding 80 percent of contract bid price or 100 percent of supported invoice amounts; and (7) adding Table 109-1 establishing decimal accuracy requirements for payment calculations based on awarded unit price ranges.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

N/A

PAGE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)

A002 01/27/2026 N/A See Blk 14

6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A

Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.

X

69056726R000002

9B. DATED (SEE ITEM 11)

12/31/2025

10A. MODIFICATION OF CONTRACT/ORDER NO.

N/A

10B. DATED (SEE ITEM 13)

CODE: N/A FACILITY CODE: N/A

N/A

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

(__ ) is extended, ( x ) is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

N/A

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN

ITEM 10A.

N/A

B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D OTHER (Specify type of modification and authority)

N/A

E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

WY NPS YELL 10(26), Gardner River High Bridge

SPECIAL CONTRACT REQUIREMENTS

Pages E-31 through E-33a, Subsections 109.06 Pricing of Adjustments and 109.08 Progress Payments. Revises language for Masterworks.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

N/A

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

PREVIOUS EDITION NOT USABLE

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

E-31 DIVISION 100

Special Contract Requirements Revised by Amendment A001 and A002 Project: WY NPS YELL 10(26), Gardner River High Bridge

109.06 Pricing of Adjustments. Delete subjection (c)(3) and substitute the following:

(3) Profit. Include a reasonable profit, except when precluded by the FAR. Limit profit to

10 percent of the total cost. Due to the limited risk in post-work pricing, a lower project profit may be determined by a profit analysis according to FAR 15.404-9 Profit.

Delete the first paragraph of Subsection (d) and substitute the following:

(d) Cost or pricing data. When the contract modification exceeds the amount indicated in

FAR Clause 52214-27 Price Reduction for Defective Cost or Pricing Data – Modifications –

Sealed Bidding, FAR Clause 52.215-10 Price Reduction for Defective Certified Cost or Pricing

Data, or FAR Clause 52.215-11 Price Reduction for Defective Cost or Pricing Data –

Modifications, and the CO has determined that an exception does not apply, submit cost or pricing data according to Subsection 109.06(b) or (c) as applicable and as defined in FAR

Subpart 2.1 Definitions, for the Contractor and each major subcontractor. See FAR Subpart

15.4 Contract Pricing and FAR Table 15-1 Instructions for Submitting Cost/Price Proposals

When Certified Cost or Pricing Data Are Required for guidance.

Add the following: Delete Subsection (c) and substitute the following:

(c) Government’s receiving report. The Government’s receiving report will be developed using the measurements and quantities from pay notes received by the CO in Masterworks and determined acceptable.

(e) Variation in Estimated Quantity. If the quantity of a unit-priced item is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price will be made upon demand of either party. The equitable adjustment will be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity

109.08 Progress Payments. Delete Subsection (c) and substitute the following:

(c) Government’s receiving report. The Government’s receiving report will be developed using the measurements and quantities from pay notes received by the CO in Masterworks and determined acceptable.

Delete Subsection (d) and substitute the following:

(d) Closing date and invoice submittal date. The closing date for progress payments will be designated by the CO. Include work performed after the closing date in the following month's invoice. For work performed between September and July of any year, submit invoices to the designated billing office by the 7th day after the closing date. Invoices received by the designated billing office after the 16th day following the closing date, for work included in the

September through July invoices, will not be accepted for payment processing that month. For work included in the August invoice, submit the invoice to the designated billing office by the

5th day after the closing date. Invoices received by the designated billing office after the 5th day following the closing date, for work included in the August invoice, will not be accepted for

E-32 DIVISION 100

Project: WY NPS YELL 10(26), Gardner River High Bridge payment processing that month. Include late, unprocessed invoice submittals in the following month’s invoice.

Delete Subsection (e) and substitute the following:

(e) Processing progress payment requests. No payment will be made for work unless field note documentation for the work was provided by the closing date.

(1) Work performed between September and July.

(a) Invoices received by the 7th day following the closing date.

(1) Proper invoices. If the invoice meets the requirements of Subsection 109.08(b), and the quantities and unit prices shown on the Contractors' invoice agree with the corresponding quantities and unit prices shown on the Governments' receiving report, the invoice will be paid.

(2) Defective invoices. If the invoice does not meet the requirements of

Subsection 109.08(b), or if any of the quantities or unit prices shown on the

Contractors' invoice exceed the corresponding quantities and unit prices shown on the Governments' receiving report, the invoice will be deemed defective and the

Contractor so notified according to FAR Clause 52.232-27(a)(2). Defective invoices will not be corrected by the Government and will be returned to the

Contractor within 7 days after the Government’s designated billing office receives the invoice.

Revise and resubmit returned invoices by the 18th day following the closing date.

The CO will evaluate the revised invoice. If the invoice still does not meet the requirements of Subsection 109.08(b), the Contractor will be so notified according to FAR Clause 52.232-27(a)(2), and no progress payment will be made that month.

Correct the deficiencies and resubmit the invoice the following month.

If the revised invoice meets the requirements of Subsection 109.08(b), but still has quantities or unit prices exceeding the corresponding quantities and unit prices shown on the Governments’ receiving report, the Government’s data for that item of work will be used. The Contractors’ invoice, as revised by the Governments’ receiving report, will be forwarded for processing by the 23rd day following the closing date. The Contractor will be notified by the 23rd day following the closing date of the reasons for any changes to the invoice.

(b) Invoices received between the 8th and 16th day following the closing date.

(1) Proper invoices. If the invoice meets the requirements of Subsection 109.08(b), and the quantities and unit prices shown on the Contractors' invoice agree with the corresponding quantities and unit prices shown on the COs' receiving report, the invoice will be deemed proper and forwarded for processing within 7 days of receipt.

(2) Defective invoices. If the invoice does not meet the requirements of

Subsection 109.08(b), the invoice will be deemed defective, the Contractor so notified according to FAR Clause 52.232 27(a)(2), and no progress payment will

E-33 DIVISION 100

Project: WY NPS YELL 10(26), Gardner River High Bridge be made that month. Correct the deficiencies and resubmit the invoice the following month.

If the invoice meets the requirements of Subsection 109.08(b), but has quantities or unit prices exceeding the corresponding quantities and unit prices shown on the

Governments' receiving report, the Government’s data for that item of work will be used. The Contractors’ invoice, as revised by the Governments’ receiving report, will be forwarded for processing within 7 days after receiving the invoice. The

Contractor will be notified, within 7 days of the Government’s receipt of the invoice, of the reasons for any changes to the invoice.

(2) Work performed during August.

(a) Proper invoices. If the invoice meets the requirements of Subsection 109.08(b), and the quantities and unit prices shown on the Contractor's invoice agree with the corresponding quantities and unit prices shown on the CO's receiving report, the invoice will be deemed proper and forwarded for processing within 7 days of receipt.

(b) Defective invoices. If the invoice does not meet the requirements of

Subsection 109.08(c), the invoice will be deemed defective, the Contractor so notified according to FAR Clause 52.232 27(a)(2), and no progress payment will be made that month. Correct the deficiencies and resubmit the invoice the following month.

If the invoice meets the requirements of Subsection 109.08(b), but has quantities or unit prices exceeding the corresponding quantities and unit prices shown on the

Governments' receiving report, the Government’s data for that item of work will be used. The Contractors’ invoice, as revised by the Governments’ receiving report, will be forwarded for processing within 7 days after receiving the invoice. The Contractor will be notified, within 7 days of the Government’s receipt of the invoice, of the reasons for any changes to the invoice.

Delete Subsection (f) and substitute the following:

(f) Partial payments. Invoices may include the following:

(1) Progress payments may include partial payment for material to be incorporated in the work, provided the material is delivered on or near the project, or stored in an approved storage location.

Provide test results and material certifications for material when partial payment is requested.

Do not request partial payment for materials that do not meet the contract specifications according to Subsections 106.03 and 106.04 or when the pay factor is less than 0.9 as calculated under Subsection 106.05. Partial payments will not be made for living or perishable material.

(2) Partial payment for preparatory work.

E-33a

Project: WY NPS YELL 10(26), Gardner River High Bridge

Individual and cumulative partial payments for preparatory work and material will not exceed the lesser of

• 80 percent of the contract bid price for the item; or

• 100 percent of amount supported by copies of invoices submitted.

The quantity paid will not exceed the corresponding quantity estimated in the contract. Partial payment for preparatory work and material does not constitute acceptance of work.

Submit pay notes according to Subsection 109.01. Provide a cost breakdown of the bid item components and submit invoices or other documents supporting the partial payment.

The CO may adjust partial payments for protection of the Government.

109.09 Final Payment. Add the following after the first paragraph:

Payment for individual pay items will be based on the awarded unit price for each pay item according to the following table.

Table 109-1

Decimal Accuracy of Quantities for Payment

Awarded unit price Decimal Accuracy of

Quantities for Payment

< $1.00 0 decimals

≥ $1.00 to < $100.00 1 decimals

≥ $100.00 to < $1000.00 2 decimals

≥ $1000.00 3 decimals