This file is a Vendor Questions and Answers document for Solicitation No. 69056726Q000034, concerning Post-Construction Environmental Compliance Monitoring Services for the OR FLAP GRANT 24(2), Granite Hill Road Reconstruction, Phase II project. The document addresses six technical questions submitted by potential vendors, with responses provided by the contracting office dated August 25, 2026.
The key issues raised by vendors pertain to pricing uncertainties and scope clarifications across multiple tasks. Question 1 addresses the unpredictability of maintenance effort under Task 1 due to weather and site conditions, with the vendor requesting conversion to an "Each" bid item; the response indicates assumptions will be addressed in an upcoming amendment. Question 2 seeks confirmation that major repairs, replacement, reconstruction, significant sediment removal, and specialized equipment costs are excluded from the base bid; the response references Task 5 language excluding such work. Question 3 concerns the pricing challenge of Task 3's turbidity monitoring and corrective action requirements, proposing either separate bid items or notification-only procedures; again, the response defers to an upcoming amendment. Question 4 requests estimated sediment removal quantities for Task 4; the response states quantities cannot be provided, noting maintenance and corrective action will be completed during day inspections using hand tools only. Question 5 requests confirmation that work exceeding Task 5 limitations will require separate authorization and contract modifications; the response confirms that work exceeding one day or requiring more than hand tools requires TPOC decision and potential modification. Question 6 clarifies that Task 8's "complete ESCP of record" requirement includes only post-construction phase documentation and records of inspections and maintenance performed under this contract, not original construction phase documentation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VENDOR QUESTIONS AND ANSWERS
Solicitation No.: 69056726Q000034 Project Name:
# General Technical Question Answer Date
1 X
The maintenance required under Task 1 presents a significant pricing challenge because the level of effort will depend on unpredictable weather and site conditions. If additional work is required, will that work be addressed under Task 5?
Because the quantity and severity of potential deficiencies cannot reasonably be determined before award, this requirement could involve substantial and unpredictable work, including replacing failed measures, repairing erosion damage, removing accumulated sediment, installing additional controls, or correcting pre-existing noncompliant conditions. These costs cannot reliably be included in a competitively bid lump-sum price.
Would WFLHD consider revising this work to an “Each” bid item so the Contractor can bill for each event as it occurs? The anticipated number and extent of these events cannot reasonably be predicted.
The assumptions for maintenance under Task 1 are the same as those for Task 5. Will be addressed in an upcoming amendment.
25-Aug-2026
2 X
Please confirm that the Contractor is not required to include costs in its base bid for major repairs;
replacement or reconstruction of controls; significant sediment removal; extensive erosion repair; or work requiring machinery or specialized equipment.
Task 5 specifically states "This statement of work does not cover more extensive repairs or use of specialized equipment." See also the response to Question #1
25-Aug-2026
Post-Construction Environmental Compliance Monitoring Services for the OR FLAP GRANT 24(2), Granite Hill Road Reconstruction, Phase II project
VENDOR QUESTIONS AND ANSWERS
3 X
Task 3 states “If turbidity exceeds 10 percent of background, notify TPOC immediately. Take immediate action to address cause of exceedance. Continue to monitor until the stormwater discharge is measured at less than 10 percent of background NTU.”
This requirement cannot reasonably be priced as a lump-sum item because the number, duration, and severity of potential turbidity exceedance events are unknown.
Would WFLHD consider establishing a separate bid item with an estimated quantity for each turbidity-monitoring or corrective-action event
Alternatively, could the requirement be revised to state:
“Notify the TPOC, and a contract modification will be issued if corrective action is required”?
Use the same assumptions as the maintenance and corrective actions under Tasks 1 and 5. Will be addressed in an upcoming amendment.
25-Aug-2026
4 X
Task 4 – Sediment Removal: Please provide an estimated quantity of sediment or soil to be removed under Task 4 so the Contractor can determine and price the anticipated level of effort. As currently written, the quantity of material, removal effort, and disposal requirements are undefined, making the task difficult to price competitively.
This is not possible to provide. Based on the assumption of maintenance and corrective action being completed during the day of the site inspection with hand tools only, then this uncertainty can be addressed.
Disposal of sediment should be outside of riparian areas and surface waters, but can be redistributed in the project area.
25-Aug-2026
5 X
Task 5 – Work Exceeding the Stated Limitation: Please confirm that corrective work exceeding the Task 5 limitation will require separate written authorization and will be compensated through a contract modification/change order. Clearly defining the level of effort included in the base task, with additional work handled by modification, will allow bidders to price the base requirement consistently.
The SOW specifically states that anything requiring more than a day or is more extensive than can be addressed using hand tools will go to the TPOC to decide about a modification. It does not state that we will modify.
25-Aug-2026
6 X
Task 8 – Complete ESCP: Does the “complete ESCP of record” required under Task 8 include documentation from both the original construction phase and the post-construction stabilization phase, or only the post-construction stabilization work performed under this contract?
This task is to provide any records that are done as part of the post-construction phase and documenting inspections and maintenance done as part of this contract.