This document is a Questions and Answers (Q&A) file for the Riverside Road Improvements B project (Project No.: ID BOUNDARY 5806(3)B), involving Western Federal Lands Highway Division. The document contains five questions from potential contractors, primarily addressing project solicitation and technical specifications. Key details include that the project is being solicited exclusively to pre-selected Idaho, Montana, and Surrounding Areas Multiple Award Task Order Contract (MATOC) contractors, with all opportunities posted on SAM.gov. Technical questions addressed include specifications for steel sign panels, geotextile materials, and a request for testing equipment information. The questions were submitted by contractors such as J7 Contracting, Poteet Construction, Granite, and ACF West Inc., with response dates ranging from 11/24/25 to 12/4/25. The agency consistently directs contractors to follow specific solicitation documents, plans, and specifications for project details.

View the file

Other files

File Type Posted
BidTab_ID BOUNDARY 5806(3).pdf PDF
Proposal Summary_ID BOUNDARY 5806 (3)B.pdf PDF
Amendment A002.pdf PDF
Lab Trailer Blank Check In Form.docx DOCX document
WFLHD Lab Trailers - Appendix B.docx DOCX document
QA_12-01-2025.pdf PDF
QA_11-24-2025.pdf PDF
A001_Physical Data Files.zip ZIP file
Amendment A001.pdf PDF
Physical Data.zip ZIP file
id-a2158063_plans.pdf PDF
RFP_ID BOUNDARY 5806(3)B_69056725R000018.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.: ID BOUNDARY 5806(3)B Project: Riverside Road Improvements B

# General Technical Question Answer Date Firm Address Phone email

1 X We have seen the notice for this project. How do we get prequalified to bid as a Prime Contractor?

This project is being solicited to our Idaho, Montana, and Surrounding Areas Multiple Award Task Order Contract (MATOC) contractors. The contractors that can bid as a Prime Contractor have already been determined:

https://highways.dot.gov/federal-lands/business/construction-contracting/idaho-montana-and-surrounding-areas-idiq-matoc. Please look for future MATOC contract opportunities on SAM.gov.

11/24/25 J7 Contracting, Inc. 208-267-6000 admin@j7contracting.com

2 X This is the first notice we have seen about this project, why is it not posted on the local plan centers requesting prime contractors?

Per FAR 2.101, The Governmentwide point of entry (GPE) is located at https://www.sam.gov; this is where Western Federal Lands Highway Division posts all contract opportunities.

11/24/25 J7 Contracting, Inc. 208-267-6000 admin@j7contracting.com

3 X

Line Item No. A0134 SIGN, STEEL PANEL, TYPE 3 SHEETING calls for the sign panels to be made from steel per bid item and spec. No.

718.03. Sign panels are usually made from

aluminum.

Please review and advise if this is really what is required or can aluminum panels be used.

Please bid according to the plans and solicitation documents.

12/1/25 Poteet Construction 3460 Grant Creek Rd Missoula, MT 59808

406-728-9370 geichert@poteetconstruct ion.com

4 X

Can you please provide a list of testing equipment that WFL could provide as stated in Section 154 – Contractor Sampling and Testing for the Riverside Rd project in Boundary County, ID

This will be added via Amendment 12/1/25 Granite 7131 N Railroad Ave Pasco, WA 99301

425-615-9240 steve.liikala@gcinc.com

5 X

We have some confusion on a project you engineered drawing for and wanted to see if could get some clarification. The geo report calls out RS580I /rs380I or equal. If you follow the spec, we have other High-performance geotextiles that will pass the spec but they are not equal to rs580I. Looks like 45000SY of Woven geotextile and there is a big price difference in rs580i/rs380i and other High performance wovens.

Follow the specifications, See FP section 207 & 714 and SCR section 714

12/4/25 ACF West Inc. Libery Lake WA 509-252-0019 cory.lenz@acfwest.com