QandA 08-26-2025.pdf
PDF 121 KB Posted
- Attached to
- Cooling Tower Wet‐Deck Media Replacement and Cleaning Federal contract opportunity
- Solicitation number
- 69056725Q000041
About this file
This Vendor Questions and Answers document is for a Cooling Tower Wet-Deck Media Replacement and Cleaning project (Solicitation No. 69056725Q000041). The document addresses 16 vendor questions covering project details such as performance requirements, site conditions, and technical specifications. Key clarifications include: the period of performance is 30-60 calendar days after order receipt, no bid bond is required, the due date is Tuesday 09/02/2025 at 2:00 pm PT, and government personnel will assist with turning off power and water.
Notable technical details include on-site water supply and drain availability, acceptance criteria based on manufacturer specifications, and performance testing to be conducted by the Technical Point of Contact (TPOC). An important update in Amendment 0001 removed the epoxy basin coating from the scope due to the existing stainless steel basin. Vendors are advised that the project requires demonstrating relevant experience for similar cooling tower replacement projects, with flexibility in documenting past work performance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 0003_25Q000041.pdf | ||
| QandA 08-28-2025.pdf | ||
| Amendment 0002_25Q000041.pdf | ||
| Site Visit Log.pdf | ||
| QandA 08-21-2025.pdf | ||
| Attachment 0006_Site Visit.pdf | ||
| QandA 08-19-2025.pdf | ||
| Amendment 0001_25Q000041.pdf | ||
| 69056725Q000041_RFQ.pdf | ||
| Attachment 0003_Scope Task Details and General Requirement.pdf | ||
| Attachment 0001_Offeror Work Experience.pdf | ||
| Attachment 0002_Past Perf Questionnaire.docx | DOCX document | |
| Attachment 0005_Facility Site Image.pdf | ||
| Attachment 0004_Wage Determination No.2015-5563 .pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VENDOR QUESTIONS AND ANSWERS
Solicitation No.:
Project No.:
Project Name: Cooling Tower Wet‐Deck Media Replacement and Cleaning
# General Technical Question Answer Date
1 X
We’d like to ask that the expectation to provide details on every applicable job for the past 5 years be changed to “applicable job for the past 5 years OR the past 5 jobs AND a list of work performed over the past 5 years” as to limit the amount of administrative work that would need to be done
The requirement is to demonstrate relevant experience for at least five years out of the last seven in this discipline and should focus on experience relevant to the requirement, particularly projects of similar size and scope. There is no requirement to provide evidence of every single job/service for that period.
19-Aug-2025
2 X I'd like to schedule a site visit to look at the tower and start putting together a bid for this project. This will be addressed in Amendment 0001 19-Aug-2025
3 X I want to make sure that a Bid Bond is Not Required for FBO Cooling Tower Wet-Deck Media Replacement job. Correct, Bid Bond is not required. 21-Aug-2025
4 X Can you please tell us where Amendment 0001 is located? Looking through items listed on Sam.gov and it seems to all be original
The amendment can be found in the attachments section of the SAM.gov posting, titled Amendment 0001_25Q000041.pdf
26-Aug-2025
5 X
Reading through the scope and we noted that there is a 30 day completion. To clarify, is this from the date it is awarded? Or is this from the day that materials arrive on site?
The period of performance for the work listed in this order will be extended from thirty (30) days to sixty (60) calendar days after receipt of the order.
26-Aug-2025
6 X Did the due date change from what is on Sam.gov? The due date is Tuesday 09/02/2025 at 2:00 pm PT, see amendment 0001. 26-Aug-2025
7 X Can you confirm the make, model, and dimensions of the cooling tower cell(s) and wet-deck media panels? This will be addressed in Amendment 0002. 26-Aug-2025
8 X Are as-built drawings or manufacturer cut sheets of the existing tower available? This will be addressed in Amendment 0002. 26-Aug-2025
9 X Are there any known structural issues (corrosion, frame damage, leaks) beyond what is described in the scope? Normal corrosion of the metallic fasteners, some scale. 26-Aug-2025
10 X Can you provide pictures of the cooling tower nameplate and/or the type of media used? Contractor can research that one. 26-Aug-2025
69056725Q000041
VENDOR QUESTIONS AND ANSWERS
11 X Who is responsible for de-energizing electrical panels and isolating incoming process water? Will Government personnel assist?
We will assist turning off power and water. 26-Aug-2025
12 X What is the valve layout for isolating process water, and are the valves in working condition?
Layout is simple, unknown if they hold when closed but assumed so. 26-Aug-2025
13 X Is there an on-site water supply and drain available for cleaning and flushing? Yes. 26-Aug-2025
14 X What are the acceptance criteria for performance testing (temperature approach, drift rate, flow distribution)?
Meeting manufacturers specifications for installation, effective flow, and function. With one year warranty since the chiller wont come back on till next summer.
26-Aug-2025
15 X Does the Government require third-party testing/certification, or will COR inspection suffice? The TPOC will incpect. 26-Aug-2025
16 X Is the epoxy basin coating product specified by brand, or may contractors propose an equivalent system?
Epoxy was removed from scope as unnecessary due to Stainless basin. See Amendment 0001. 26-Aug-2025