This is Amendment 0002 to solicitation 69056725Q000008 issued by the Federal Highway Administration Western Federal Lands Division for the Snug Harbor Road Gulley Remediation and Erosion Control project in Alaska. The amendment extends the offer due date from 02/11/2025 1400 PT to 02/16/2025 1400 PT.
The amendment revises multiple areas of the Statement of Work (pages D-4 through D-15), including clarifications on turf establishment procedures, timing requirements, and material specifications. Key changes include requiring contractors to complete all work under Tasks 1-7 (except additional watering) by 6/20/2025, with final turf establishment inspection on 7/18/2025. The amendment also corrects the state jurisdiction from Wyoming to Alaska regarding insurance requirements, and provides additional details about material installation procedures, including specifications for erosion control blankets, fiber rolls, and turf establishment methods. Work hours are restricted to 7am-7pm Monday-Friday and 8am-7pm Saturday-Sunday due to adjacent residential housing, with traffic delays limited to 15 minutes per passage.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
69056725Q000008 x
X copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
690567
Vancouver WA 98661
610 E FIFTH STREET
FHWA WESTERN FED LANDS DIVISION
Federal Highway Administration
01/31/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.
Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers X is extended,
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
01/16/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
AK PFH 59(3), Snug Harbor Road Gulley Remediation and Erosion Control
See page 2.
15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
NA
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ONE (1)
douglas.g.taylor Highlight
Amendment No. A0002, dated 1-31-3025 AK PFH 59(3) Solicitation No. 69056725Q000008 Snug Harbor Road Gulley Remediation Page 2 and Erosion Control
REVISIONS ARE AS FOLLOWS:
SF 1449, SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(Pen & Ink change)
Page A-1, Block 8. Revises "OFFER DUE DATE/LOCAL TIME" from 02/11/2025 1400 PT to 02/16/2025 1400 PT.
STATEMENT OF WORK
Pages D-4 through D-15. Revises multiple areas of the Statement of Work (SOW) as indicated by red and blue and/or lined through text. Attached pages replace the original pages in their entirety.
ENCLOSURES
Pages:
D-4 through D-15
D-4
AK PFH 59(3)
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002 between two degradable, synthetic or natural fiber nettings. Do not use monofilament netting or similar material. Conform to the following:
i. The short-term double-net erosion control blanket shall be designed for:
a. Typical functional longevity of 12 months
b. Maximum “C” factor per ASTM D6459: 0.10
c. Maximum gradient slope: 1V:2H
d. Minimum shear stress per ASTM 6460: 1.75 lb/ft2
e. Minimum MD material tensile strength per ASTM 6818: 75 lb/ft
f. Minimum TD material tensile strength per ASTM 6818: 40 lb/ft
g. Material thickness per ASTM D6525: >0.25 to <0.50 inch
h. Ground coverage per ASTM D6567: >50% to <90%
i. Material mass per ASTM D6475: >8.0 oz/yd2
E. Item 0005 – Turf Establishment. Furnish and apply seed, fertilizer, tackifier, biotic soil amendment, and bonded fiber mulch on areas as outlined in the Project Tasks.
4. STATEMENT OF WORK TASKS
A. Task 1 – Lane Closure Permit and Traffic Control. Contractor must apply for a temporary Lane Closure Permit from Alaska DOT&PF ROW Property Management Section a minimum of 45 calendar days before beginning work. Traffic control to be placed as per the TEMPORARY TRAFFIC CONTROL SINGLE LANE CLOSURE LAYOUT (WITH FLAGGERS) Standard Plan No. 635-6 (Sheet No. 8 in Attachment 0003 – Project Plans) while also incorporating any additional requirements by Alaska DOT&PF (if any).
The Contractor is responsible for installing and removing all traffic control devices daily and for performing all flagging duties.
Due to adjacent residential housing, work activity is restricted to the hours between 7 a.m.
and 7 p.m. Monday thru Friday and between 8 a.m. and 7 p.m. on Saturday and Sunday.
Delays to public traffic are limited to 15 minutes per passage thru the project.
Metal tracked equipment will not be allowed to have direct contact with the pavement.
Industry standards must be applied to protect the asphalt which can be rubber pads for metal tracks, rubber tracked equipment, or other protective measures. If the contractor chooses to position heavy equipment along the edge of the roadway or encroaching over the ditch area, the contractor is to take the proper measures to protect the edge of the asphalt and ditch.
Any damage to the road and/or ditch will be the responsibility of the contractor to repair and clean-up. If the work activity causes soil to be deposited or eroded into the ditch, it is the responsibility of the contractor to remove the material from the ditch.
B. Task 2 – Removal of Erosion Control & Trim Grass Within Gulley Repair Area.
Contractor to, where needed for gulley repair, remove existing fiber rolls and Rolled Erosion Control Product (RECP) while ensuring the existing RECP that is to remain in place is properly re-fastened along the edges as per Detail W629-1 ROLLED EROSION CONTROL PRODUCT ON SLOPES (Sheet No. 7 in Attachment 0003 – Project Plans).
D-5
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
If areas requiring new rolled erosion control product have existing grass, the grass is to be trimmed low to the ground and the cut material is to be removed from the area prior to placing additional topsoil or installing new rolled erosion control product.
Locations with contiguous gullies (like those near Sta 308+10, Sta 309+10, and Sta 309+30) or gullies in very close proximity (like those near Sta 309+90 and Sta 310+10) shall be treated as one gulley with the fiber rolls and rolled erosion control product spanning both sites.
C. Task 3 – Place Topsoil. Contractor to fill all gulleys with topsoil as reflected on the Erosion Survey sheets (Sheets No. 2 thru 5 in Attachment 0003 – Project Plans) depicting the limits of the gullies. If further erosion has occurred since the survey was completed, adjustment to those limits may be directed by the COR. If the contractor’s work effort results in additional erosion due to foot traffic, those areas must also be filled and repaired as needed.
Topsoil shall be placed in 6-inch lifts with each lift being hand tamped before placing the next lift. If the topsoil is overly dry, it should be lightly moistened prior to hand tamping but still be dry enough to not stick to the tamper. The final lift should be mounded up an inch or more per the direction of the COR to allow for additional settlement. However, care must be taken to ensure that surface inconsistencies are not created that would cause the RECP to bridge over an area (i.e., topsoil surface must be consistently smooth to install the RECP in direct contact with the soil surface at all locations).
The existing slopes cannot be further destabilized by equipment. Therefore, heavy equipment will not be allowed on the slope to perform this work.
The contractor is to take care in performing the work to not allow new material deposit (or erosion) in the ditch. Removal of new material deposit in the ditch caused by project efforts will be the responsibility of the contractor to clean out.
If material is stockpiled in nearby turnouts along Snug Harbor Road, surround with sediment wattles and cover with plastic sheeting. Plastic sheeting will need to be reasonably secured with sand bags or by other securing methods.
D. Task 4 – Install Straw Fiber Rolls. Install 9-inch (min.) diameter straw fiber rolls being sure to imbed them 3-inches in the ground and place the removed soil on the uphill side of the fiber roll and tamp the material down as per the FIBER ROLL detail (Sheet No. 6 in Attachment 0003 – Project Plans). The slope is known to be comprised of rocky or compacted soils so installation methods should account for that in driving the stakes to secure the fiber rolls to the slope.
Fiber rolls are to be placed at a 10-foot spacing although adjustment will be required depending on where the gulley’s upper and lower limits are in relation to the existing fiber rolls. Every other fiber roll is to line up with the existing fiber rolls that are placed at a 20-foot spacing.
D-6
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
The new fiber rolls are to extend 5 feet past the limits of the gulley on each side. The limits of the gulley are defined as the area depicted on the Erosion Survey plan sheets unless the COR provides other direction. The new fiber rolls that line up with the existing fiber rolls will overlap the existing fiber rolls as per the FIBER ROLL detail. Where this occurs, the 12-inch minimum overlap (and the taper) is to be in addition to the 5-foot requirement.
Locations with contiguous gullies, or gullies in very close proximity, shall be treated as one gulley with the fiber rolls spanning both sites in a single run.
E. Task 5 – Install Short-Term Double-Net Erosion Control Blankets, Type 2.D.
Following application of turf establishment mixture, iInstall short-term double-net erosion control blankets (RECP) according to manufacturer recommendations and to the following minimum guidelines. Complete turf establishment work before installing RECP.
Unroll the RECP parallel to the primary direction of flow and place it in direct contact with the soil surface. Do not stretch or allow RECP to bridge over surface inconsistencies.
Overlap edges of adjacent RECP by 4 inches minimum. Use fasteners according to the plans and use enough fasteners to prevent seam separation. Drive fasteners (using fasteners recommended for rocky or compacted soils) flush with the soil surface. Note that longer fasteners may be necessary in sandy, loose, or wet soils.
RECP needs to be spliced in the middle of a slope. Ensure the RECP is “shingled” with the upslope RECP overlapping the downslope RECP. There should be six inches of overlap in a splice. Use a staple check slot to secure the overlap. A check slot is made by placing a row of fasteners four inches on center and then placing a second row of fasteners four inches on center, staggered from the first row.
Place and secure RECP over the exposed soil extending past the limits of the gulley area and overlapping the existing RECP as depicted on the ROLLED EROSION CONTROL PRODUCT ON SLOPES Standard Detail W629-1 (Sheet No. 7 in Attachment 0003 – Project Plans).
As per the FIBER ROLL detail (Sheet No. 6 in Attachment 0003 – Project Plans) , the RECP is to go over the top of the fiber roll. Install fasteners directly adjacent to both sides of the fiber roll with a spacing tight enough to ensure that the RECP is completely flush to the topsoil along the entire length of the fiber roll. At a minimum, it is expected that the fasteners should be placed along both sides of the fiber roll at the same spacing as the stakes used to secure the fiber roll. Ensure that the fasteners selected can hold the RECP flush to the topsoil along the entire length of the fiber roll.
Securely fasten RECP to the soil by installing fasteners at a minimum rate of 1.5 per square yard.
Locations with contiguous gullies, or gullies in very close proximity, shall be treated as one gulley with the rolled erosion control product spanning both sites in a
D-7
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002 contiguous/overlapping mat.
F. Task 6 – Install Turf Establishment, Hydraulic Method. This work consists of soil preparation, watering, fertilizing, seeding, and mulching.
i. Material includes:
a. Fertilizer
b. Biotic soil amendment
c. Seed
d. Tackifier
e. Bonded Fiber Mulch
f. Water
ii. General. Within 7 days after completion and approval of gulley and slope repairTasks 1 through 4, apply turf establishment. After the fiber rolls have been installed (but before the RECP is installed), the contractor is to proceed with turf establishment as directed below and in accordance withper industry standards.
ii.iii. Do not apply turf establishment during windy weather or when the ground is excessively wet, frozen, snow covered, extremely dry, cloddy, hard pan, or not friable.
iii.iv. Preparing Seedbed. Remove weeds, sticks, stones 2 inches in diameter and larger, and other debris detrimental to application, growth, or maintenance of the turf.
Cultivate the seeding area to a minimum depth of 4 inches and prepare a firm, but friable seedbed before seeding.
iv.i. After the fiber rolls have been installed (but before the RECP is installed), the contractor is to proceed with turf establishment as per industry standards.
v. Watering. Moisten seeding areas before seeding. However, if seed, fertilizer, and biotic soil amendment are to be mixed, follow manufacturer’s recommendations.
Maintain the moisture until turf is established and or until final acceptance is received.
vi. Fertilizing. Apply fertilizer by hydraulic method at a mix rate of 300 pounds/acre.
Add fertilizer to the slurry and mix before adding seed. Apply the seed and fertilizer in one application.
vii. Biotic Soil Amendment. Apply biotic soil amendment at a mix rate of 3500 pounds per acre. If recommended by the manufacturers, the biotic soil amendment can be mixed with the seed, fertilizer and tackifier in the hydro-seeder tank.
viii. Seeding. Apply seed by hydraulic method at a mix rate of 50 pounds of pure live seed per acre. Use hydraulic-type equipment t ha t can p rov i de a uniform application using water as the carrying agent. Add a tracer material consisting of either wood or grass cellulose fiber mulch to the water. Apply the tracer material at a rate of 400
D-8
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002 pounds per acre to provide visible evidence of uniform application. Add the seed to the water slurry no more than 30 minutes before application. Seed by hand in areas inaccessible to hydraulic seeding equipment.
ix. Bonded Fiber Mulching. Hydraulic method. Apply mulch in a separate application from the seed using hydraulic-type equipment.
Apply bonded fiber matrix hydraulic mulch at a minimum mix rate of 1900 pounds per acre (including tracer as per manufacturer’s recommendations) or as specified by the manufacturer. Apply so no hole in the matrix is greater than 0.04 inches. Apply so that no gaps exist between the matrix and the soil. Mulch by hand in areas inaccessible to mulching equipment.
x. Turf Establishment. Use hydro-type equipment capable of providing a uniform application using water as the carrying agent. Do not use hydro-type equipment with gear driven pumps, which can damage the seed. Equipment must be capable of reaching cut slopes a minimum of 100 feet high. Mix and apply the mixture in accordance with manufacturer’s recommendations. Establish turf by hand in areas inaccessible to mechanical equipment.
a. Turf establishment mixture. Provide the turf establishment mixture with the components as specified and recommended by manufacturers. Do not blend biotic soil amendments before placing in the hydro-type equipment. Mix in biotic soil amendment after all other components have been placed in the mixing tank.
b. Application. Apply the mixture within 30 minutes of adding the seed to the slurry mixture. Moisten the area before applying the mixture. Apply from opposite directions, to ensure the highest level of coverage, effectiveness, and performance.
Apply the mixture in two applications, placing no more than 50% of the mixture at a time. Adjust the mixture application rate according to manufacturer’s recommendations to avoid sloughing or washing away the mixture on steep slope.
xi. Turf Establishment Specifications:
a. Fertilizer – Provide fertilizer meeting applicable Federal and state rules and regulations and required minimum percentages of available nutrients. Provide the fertilizer in new, clean, sealed, and properly labeled containers with name, mass, and guaranteed analysis of contents clearly marked.
Furnish fertilizer for turf establishment with the following minimum percentages of available nutrients: 20N:20P:10K
(1) Each ingredient is acceptable up to 5 percent over the minimum requirements.
(2) Potassium need not be present but will be allowed.
(3) Formulate the 20:20:10 fertilizer from urea-formaldehyde compounds. The maximum activity index is 50.
b. Seed – Conform to the Federal Seed Act, the Federal Noxious Weed Act, and applicable state and local seed and noxious weed laws. Do not use wet, moldy, or otherwise contaminated or damaged seed. Furnish each seed type in separate sealed container. Clearly label each container with the following:
(1) Name and type of seed;
D-9
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
(2) Lot number;
(3) Net mass;
(4) Percent of purity, germination and hard seed;
(5) Percent of maximum weed seed content;
(6) Seed origin;
(7) Noxious weeds present;
(8) Other crop seed;
(9) Inert matter;
(10) Name and address of seed distributor; and
(11) Mixture percent of each component
Furnish a mixture consisting of the following kinds of seed with the corresponding percentages by weight of “live seed”:
(1) Alyeska Polargrass (Arctagnosis latifolia) 20%
(2) Actrared Red Fescue (Festuca rubra) 30%
(3) Norcoast Bering Harigrass (Deschampia beringensis) 30%
(4) Fireweed (Epilotium latifolium) 5%
(5) Nookta Lupine (Lupinus nootkatensis) 15%
Determine the amount of “live seed” in a container by the following formula: Net weight of seed in container multiplied by the purity percentage multiplied by the germination percentage. (If seed is 85 percent pure and tests 90 percent germination, then a 100 pound (45.4 kilogram) container would contain 76.5 pounds (34.7 kilograms) of “live seed”.)
c. Bonded fiber matrix hydromulch – Furnish a mixture of fibers and bonding agent which, when hydraulically applied and dried, produce a matrix conforming to the following:
(1) Does not dissolve or disperse when wetted;
(2) Holds at least 10 ounces (1000 grams) of water per ounce of dry matrix;
(3) Has no germination or growth inhibiting factors;
(4) Forms no water insensitive crust;
(5) Contains material that is 100 percent biodegradable; and
(6) Is colored with a green dye noninjurious to plant growth.
(7) Contains material composed of 100 percent recycled thermally refined virgin wood fiber, crimped interlocking with mineral activators and wetting agents including high- viscosity colloidal polysaccharides, cross-linked biopolymers, and water absorbents.
(8) Is phytosanitary and free from plastic netting, and when cured forms an intimate bond with the soil surface to create a continuous, porous, absorbent, and flexible erosion resistant blanket that allows for rapid germination and accelerated plant growth.
d. Polymer stabilized fiber matrix tackifier – Furnish a commercially available product containing no solvents or other diluting agents toxic to plant life that is without growth or germination inhibiting factors, nonflammable, nontoxic to aquatic organisms, and functional for at least 180 days.
D-10
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
Furnish the following:
(1) A liquid formulation with polyacrylamide as the primary active ingredient with the following requirements:
(a) Linear, anionic copolymer of acrylamide and sodium acrylate; and
(b) Anionic with a residual monomer content that is at most 0.05 percent by mass.
(2) Formulated and labeled as one of the following:
(a) Water-in-oil emulsion. A product containing at least 2.6 pounds per gallon pure polyacrylamide that is at least 30 percent active; or
(b) Liquid dispersed polyacrylamide. A product containing at least 4.4 pounds per gallon pure polyacrylamide that is at least 35 percent active.
e. Biotic Soil Amendment - Furnish biotic soil amendment composed of at least 90 percent organic matter and other material designed to enhance seed germination, vegetation establishments and soil health and the following:
(1) Composed of mycorrhizal fungi and a minimum of three of the following ingredients:
(a) Biochar;
(b) Humus/Humic Acid;
(c) Porous Ceramics or Water-holding Organic Polymers;
(d) Seaweed Extract;
(e) Beneficial Bacteria; and
(f) Micronutrients.
(2) Soil amendment content
Biotic Soil Amendment Property Test Method Specifications
Physical Organic matter ASTM D586 90% minimum pH ASTM D1293 5.0 – 8.5 C:N ration ASTM E1508 10:1 min.
Water-holding Capacity(1) ASTM D7367 400% min.
Moisture content ASTM 2974 10% min. 50% max.
Environment Acute toxicity EPA method 2021.0 Non-toxic
EPA metal limits SW846-6020 04.06 Pass
Performance Growth enhancement ASTM D7322 500% min.
D-11
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
NOTE: (1) Water holding capacity of the prepackaged material without the addition of ancillary amendments.
(3) Provide test results dated within 3 years prior to the date of application from an independent, accredited laboratory that has been recognized by an accrediting organization to test and evaluate products to product safety standards demonstrating that the product meets the requirements of Table 2.
xii. Protecting and Caring for Seeded Areas. Protect and care for seeded areas including watering when needed. For quotation purposes, anticipate watering four additional times after the initial watering. Repair or apply supplemental applications of seed, bonded fiber mulch, fertilizer, biotic soil amendment, tackifier, and water as many times as needed until turf is established or and final acceptance is received. Plan on watering four additional times to establish the turf.
G. Task 7 – Clean-Up & Replacement of Existing Erosion Control Products. Contractor is to perform clean-up and replacement of existing erosion control products (from prior Phase 2 contract) as directed by the COR to ensure that it is functioning properly and not inhibiting slope revegetation. This work may include removal of existing non-functioning erosion control measures and replacing them with new, properly installed Fiber Rolls and Rolled Erosion Control Product. This may also require additional Turf Establishment work.
An example of an area requiring this effort is reflected in the last photo (taken in the upper part of the slope near Station 306+50) included in Attachment 0004 – Existing Conditions Photos.
All tasks associated with this SOW will fall under the general guidance of the Contracting Officer’s Representative (COR).
5. DELIVERABLES
Ref Deliverable Submittal Format
Submittal to FHWA Electronic Hard
Copy
2.B.iii Topsoil Submittal X At least 7 days prior to topsoil installation
2.B.iii Straw Fiber Roll Submittal X At least 7 days prior to fiber roll installation
2.B.iii Short-Term Double-Net Erosion Control Blanket, Type 2D Submittal X
At least 7 days prior to erosion control blanket installation
2.B.iii Fertilizer Submittal X At least 7 days prior to installation
2.B.iii Biotic Soil Amendment Submittal X At least 7 days prior to installation
2.B.iii Seed Submittal X At least 7 days prior to installation
D-12
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
2.B.iii Tackifier Submittal X At least 7 days prior to installation
2.B.iii Bonded Fiber Mulch Submittal X At least 7 days prior to installation
2.B.iv Submit Hazardous Spill Plan X At least 2 days before beginning work
4.A Approved Temporary Lane Closure Permit (including approved TCP) from Alaska DOT&PF (Copy)
X Prior to mobilizing on site
8. Certificate of Insurance X Before work begins
6. MEASUREMENT
All costs associated with temporary traffic control (including the lane closure permit) shall be paid via lump sum.
Measure topsoil placement by cubic yards. All costs associated with furnishing and installing topsoil shall be accounted for in the unit price.
Measure installed straw fiber rolls by the linear foot. Costs associated with removal of old fiber rolls shall be considered incidental to the cost of installing new fiber rolls.
Measure installed rolled erosion control product (RECP) by the square yard. Costs associated with removal of the old RECP shall be considered incidental to the cost of installing new rolled erosion control product. Also, costs associated with the trimming/disposal of existing grass where required prior to placement of topsoil and new RECP shall be considered incidental to the cost of installing the new rolled erosion control product.
Measure Turf turf Establishment establishment application by the square yard. Watering is required as needed to maintain moisture until turf is established and . Watering is incidental to the cost of turf establishment. Plan on watering four additional times after the initial watering.
Removal and replacement of previously installed poorly performing erosion control products as directed by the COR shall be covered as per the unit pricing of furnishing and installing pertinent replacement contract items (fiber rolls, rolled erosion control product, and turf establishment).
7. PERIOD OF PERFORMANCE SCHEDULE
Provide the COR a minimum of two weeks’ notice prior to commencement of work.
NO workWork shall NOT begin prior to 6/09/2025. All work under Tasks 1 through 7, except for additional watering to achieve turf establishment, must be completed and must be complete no later than 7/18/20246/20/2025.
Final inspection to verify turf establishment will be conducted on 7/18/2025.
D-13
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
8. INSURANCE REQUIREMENTS
The successful offeror will be required to procure and maintain until final acceptance of the contract, liability insurance of the types and limits specified below. The successful offeror shall obtain insurance from companies authorized to do business in Wyoming Alaska and shall cover all operations under the contract whether performed by the Contractor or by subcontractors.
Before work begins, furnish "certificates of insurance" certifying that the policies will not be changed or canceled until thirty (30) days written notice has been given to the Government.
Insurance coverage in the minimum amounts set forth below shall not relieve the Contractor of liability more than the coverage.
A. Carry insurance meeting the following minimums:
i. Worker's compensation insurance. Minimum required by law.
ii. Comprehensive or commercial general liability insurance.
iii. Personal injury and property damage coverage.
iv. Contractual liability coverage.
v. Completed operations liability coverage.
a. $1,000,000 combined single limit for each occurrence; and
b. $2,000,000 general aggregate limit.
vi. Automobile liability insurance. $1,000,000 combined single limit for each occurrence.
9. INSPECTION AND ACCEPTANCE
All supplies and/or work hereunder shall be subject to review by the government. The COR is responsible for inspection and acceptance of all incoming shipments, documents, and services.
Acceptance of the final deliverables shall be made in writing by the COR.
Material and installation acceptance shall be based on:
A. Certification. For material manufactured off-site, use a manufacturer with an ISO 9000 certification or an effective testing and inspection system. Require the manufacturer to clearly mark the material or packaging with a unique product identification or specification standard to which it is produced.
B. Visual Inspection. Acceptance is based on visual inspection of the work for compliance with the contract and prevailing industry standards. Payment Acceptance for turf establishment will be authorized once the turf is deemed to be have successfully established as per industry standards.
D-14
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
10. AUTHORITY TO OBLIGATE THE GOVERNMENT
The Contracting Officer is the only individual who can legally commit or obligate the Government to the expenditure of public funds. No cost chargeable to the proposed task order can be incurred before receipt of a fully executed task order or specific authorization from the Contracting Officer.
11. PAYMENT FOR UNAUTHORIZED WORK
No payments will be made for any unauthorized supplies and/or services or for any unauthorized changes to the work specified herein. This includes any services performed by the Contractor of their own volition or at the request of an individual other than a duly appointed Contracting Officer.
Only a duly appointed Contracting Officer is authorized to change the specifications, terms, and conditions under this effort.
12. NON-PERSONAL SERVICES
This order is a non-personal service as defined in FAR subpart 37.101. It is understood and agreed that the Contractor and/or Contractor’s employees and subcontractors:
• Shall perform the services specified herein as independent contractors, not as employees of the government;
• Shall be responsible for their own management and administration of the work required and bear sole responsibility for complying with any and all technical, schedule, or financial requirements or constraints attendant to the performance of this contract;
• Shall be free from supervision or control by any government employee with respect to the manner or method of performance of the services specified; but
• Shall, pursuant to the government’s right and obligation to inspect, accept or reject the work, comply with such general direction of the Contracting Officer, or the duly authorized representative of the Contracting Officer, as is necessary to ensure the accomplishment of the contract objectives.
13. CONTRACTOR’S FAILURE TO PERFORM REQUIRED SERVICES
The rights of the Government and remedies described in this section are in addition to all other rights and remedies set forth in the contract. Specifically, the Government reserves its rights under the appropriate Inspection of Services and Termination Clauses. Any reductions in the Contractor’s invoice shall reflect the contract’s reduced value resulting from the Contractor’s failure to perform required services. The Contractor shall not be relieved of the full performance of the services hereunder and may be terminated for default based upon the inadequate performance of services, even if a reduction was previously taken for any inadequate performance.
14. MISCELLANEOUS
D-15
Snug Harbor Road Gulley Remediation and Erosion Control AMENDMENT 0002
A. Anti-Deficiency. Unless otherwise authorized by Public Law or Federal Regulation, nothing contained herein shall be construed as binding the Government to expend, in any one fiscal year, any sum in excess of the appropriation made by Congress for that fiscal year in furtherance of the matter of the contract or to involve the Government in an obligation for the future expenditure of monies before an appropriation Is made (Anti-Deficiency Act, 31 U.S.C. 1341.A.1).
B. Indemnification. Indemnify and hold harmless the Government, its employees, and its consultants from suits; actions; or claims brought for injuries or damage received or sustained by a person, persons, or property resulting from the work performance or arising out of the negligent performance of the contract.
Any indemnification language contained in standard form agreements executed between the Government and the Contractor shall be binding upon the Government only to the extent authorized by law, opinions of the Government Accountability Office and the Federal Tort Claims Act (28 U.S.C. §§ 2671-2680).
15. CLOSEOUT OF CONTRACT FILES
The Government will initiate the administrative closeout of the Delivery Order after receiving evidence that all technical requirements have been completed. The Contractor shall furnish all required documents in support of the closeout of this contract.
The Government anticipates the timeframe to complete administrative close out of this contract will not exceed thirty (30) days. The costs incurred in the administrative closeout of task orders and contract files are unallowable direct costs under the contract and, therefore, cannot be charged as direct costs to the Government. Contractors are to handle such costs in accordance with their disclosure statements/cost accounting systems.
16. LIST OF ATTACHMENTS
Attachment 0001 – Quoter Work Experience (1 page) Attachment 0002 – Past Performance Reference Questionnaire (5 pages) Attachment 0003 – Project Plans (9 pages) Attachment 0004 – Existing Conditions Photos (4 pages) Attachment 0005 – Prior Project Plans (12 pages) Attachment 0006 – Service Contract Labor Standards Wage Determinations (11 pages)