OR FS DSHUT601 60(1), Road 60 Improvements, MP 0 - 1. 0
Solicitation number
69056725B000011
Issued by

About this file

This document is a Questions and Answers (Q&A) file for Project No. OR FS DSHUT601 60(1), a Road 60 Improvements project covering mile posts 0 to 1.0. The document contains four technical questions from potential bidders, all of which were responded to identically with a directive to wait for the forthcoming solicitation documents.

The questions cover specific technical details such as surveyor responsibilities, as-built and topographical requirements, erosion control substitutions, seed source acceptability for turf establishment, and mobile/portable traffic signal usage. The respondent consistently advised that all such details will be included in the future Invitation for Bids, which will contain Special Contract Requirements (SCRs), plans, and physical project data. The response date for all questions is consistently noted as 12/12/25, indicating a future procurement process.

View the file

Other files

File Type Posted
QA_12-12-2025_2.pdf PDF
Prelim Letter_OR FS DSHUT601 60(1).pdf PDF
prelim_orf-dshut60-1_plan.pdf PDF
PROJECT DESCRIPTION_OR FS DSHUT601 60(1).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. OR FS DSHUT601 60(1) Project Road 60 Improvements, MP 0 to 1.0

# General Technical Question Answer Date

1 X

Please advise what the requirements will be for the surveyor as to responsibilities?

Will the surveyor be required to provide as builts and topo for this project?

Please wait for the solicitation documents (Invitation for Bids that includes the Special Contract Requirements [SCRs], plans, and physical data) that will be posted when this project goes on advertisement.

12/12/25

2 X Please advise what substitutions will be allowed for erosion control.

Please wait for the solicitation documents (Invitation for Bids that includes the Special Contract Requirements [SCRs], plans, and physical data) that will be posted when this project goes on advertisement.

12/12/25

3 X Please advise if seed from McPheeters Turf will suffice for “Turf Establishment”.

Please wait for the solicitation documents (Invitation for Bids that includes the Special Contract Requirements [SCRs], plans, and physical data) that will be posted when this project goes on advertisement.

12/12/25

4 X Please advise if Mobile/Portable traffic signals will suffice for traffic control?

Please wait for the solicitation documents (Invitation for Bids that includes the Special Contract Requirements [SCRs], plans, and physical data) that will be posted when this project goes on advertisement.

12/12/25