This document is a federal contracting compliance report on the Western Federal Lands Highway Division (WFLHD) construction contract administration procedures and performance data regarding equitable adjustments for change orders.
WFLHD reports that it currently has no agency-specific additional policies and procedures beyond FAR requirements for definitizing equitable adjustments on construction contracts. The document provides historical performance data covering fiscal years 2021 through 2023 on the time required to definitize change order proposals after receipt of adequate definitization proposals. The data shows variability in processing times across the three-year period. In FY 2021, 9 total change orders were definitized, with 5 requiring 91-180 days and 2 requiring 366 or more days. In FY 2022, 2 total change orders were definitized, with both processed within 91-180 days. In FY 2023, 16 total change orders were definitized, with the majority processed in the 31-90 day range (6 proposals), followed by 91-180 days (4 proposals) and 181-365 days (3 proposals). No change orders were definitized after contract completion in any fiscal year. The data demonstrates an overall trend toward faster definitization in recent years, with fewer instances of extended processing times beyond 180 days.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WFLHD Construction Contract Administration
FAR 36.211 requires a description of the Federal Highway Administration’s (FHWA) procedures that apply to definitization of equitable adjustments for change orders under construction contracts. It also requires that FWHA furnish data on the agency’s past performance, for the prior 3 fiscal years, regarding the time required to definitize equitable adjustments for change orders under construction contracts.
Change orders as defined in FAR 2.101 are changes to the contract work pursuant to FAR 52.243-4, Changes.
There are no agency-specific additional policies and procedures that exist at this time.
The table below contains data regarding the definitization of equitable adjustments for change orders under construction contracts by fiscal year (FY).
Time to definitize after receipt of an adequate change order definitization proposal under construction contracts
Number of change order proposals definitized under construction contracts
FY 2021 FY 2022 FY 2023
0 to 30 days 1 1 0 31 to 60 days 1 0 3 61 to 90 days 0 0 3 91 to 180 days 5 1 4 181 to 365 days 0 0 3 366 or more days 2 0 0 After completion of contract performance via a contract modification addressing all undefinitized equitable adjustments received during contract performance
0 0 0 https://www.acquisition.gov/far/part-52#FAR_52_243_4