This document is a Questions and Answers (Q&A) file for a federal construction project at the Oregon Dunes National Recreation Area. The project, identified as OR FLAP DOUGLAS 251(1), involves Umpqua Dunes Access Improvements and is being solicited by the Department of Transportation Federal Highway Administration. The Q&A document contains 24 technical questions from potential bidders covering various project aspects, including guardrail specifications, terminal details, traffic control, staging areas, project phasing, and construction requirements.
Key details include the government's responses directing bidders to specific sections of the solicitation documents for clarification, references to upcoming amendments (A001 and A002), and guidance on technical specifics like guardrail installation, post spacing, and terminal placement. The document indicates a hard copy submission is required, with the government firm on not extending the bid opening date. Bidders are advised to consult the plans and solicitation documents on SAM.gov for complete project details, with the bid date set for 6/18/25.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tabulation_OR FLAP DOUGLAS 251(1).pdf | ||
| Bid Summary_OR FLAP DOUGLAS 251(1).pdf | ||
| Amendment A002.pdf | ||
| QA_6-18-2025.pdf | ||
| Amendment A001.pdf | ||
| QA_6-16-2025.pdf | ||
| or-a1902511_superelevation_report_SHD.xlsx | XLSX spreadsheet | |
| or-a1902511_plans.pdf | ||
| Physical Data.zip | ZIP file | |
| IFB 69056724B000025_OR FLAP DOUGLAS 251(1).pdf | ||
| or-a1902511_control-points.xlsx | XLSX spreadsheet | |
| or-a1902511_earthwork.pdf | ||
| WFLHD Construction Contract Administration_FY 23 V2.pdf | ||
| or-a1902511_Alignments.pdf | ||
| or-a1902511_escp.pdf | ||
| or-a1902511_XS.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. OR FLAP DOUGLAS 251(1)
Project Oregon Dunes National Recreation Area ‐
Umpqua Dunes Access Improvements
# General Technical Question Answer Date
1 X
The Plans are very vague on what exactly you are looking to use for the guardrail on this project. It's calling for double sided rail but doesn't show a drawing on what style of double-sided rail that needs to be used. Are block outs going to be used on both sides etc. There is a weak post drawing, but I'm not seeing that needed in any of the plan sheets.
See section 710.06(a) for Metal Beam Rail and see Amendment A001 for updated details.
6/16/25
2 X
What are your plans on covering the exposed ends of the rail on the backside of the double-sided rail that doesn't get a Terminal? From what I can see it will just be a blunt end of rail exposed.
Terminal Sections are for motor vehicles. 6/16/25
3 X
What drawings are actually needed on this project? I see a lot of drawings that don't pertain to any of the rail that's being asked to be installed. For example, are there any areas that are going to be requiring the spanning of rail?
Guardrail drawings needed will be based on field conditions.
6/16/25
4 X
What style of Terminals are you wanting to use, Non- Flared terminals? Will the Non- flared terminals encroach on the access road that is being built for OHV travel, because the Non-
Flared Terminals do flare one foot?
See sheet H.6 for terminal details and
617.03.
6/16/25
5 X Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
See Section 153 for QCM requirements. 6/18/25
6 X
Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
See Section 108. 6/18/25
7 X Please provide bidding quantities for the deteriorated base course.
No additional quantities are available. 6/18/25
8 X Please provide the site visit registration information.
Per FAR Provision 52.236-27 Site Visit
Construction (page B-18 of the Invitation for
Bids [IFB]), there will be no government arranged site visits.
6/18/25
9 X
Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity?
There are no government provided water sources. See page A-2a of the Notice to
Bidders. See Subsection 105.02(c).
6/18/25
Check General or Technical
10 X Does this project require phasing?
Bid according to the plans and solicitation documents.
6/18/25
11 X Field office location? Is power available nearby?
See Subsection 105.04 for approved staging and storage locations.
6/18/25
12 X Please provide lay down/staging area for construction.
See Subsection 105.04 for approved staging and storage locations.
6/18/25
13 X Can we shut down roadway access or do we need to maintain one lane for travel?
See Section 156 for traffic control requirements.
6/18/25
14 X What are the limitations for construction intervals (for proposed road work)?
See Sections 108 and 156. 6/18/25
15 X
Is there an anticipated start date?
See FAR Clause 52.211-10 Commencement, Prosecution, and Completion of Work on page C-23 of the IFB.
6/18/25
16 X Please provide details for the fence we are to remove and reset.
Remove and reset fence according to
Section 619.
6/18/25
17 X What is the size or sizes of the drain to be plugged?
This will be addressed under Amendment
A002.
6/18/25
18 X What are the new requirements for manholes to be adjusted Adjust manholes according to Section 604. 6/18/25
19 X
You changed the name of the drawing from
Type 2 weak posts Guardrail to MGS Type 2
Double-Sided rail. This drawing shows cold formed channel posts, base plated posts, S3"x5.7" posts, so what is it? No blocks are shown, are you wanting to use blocks? The post drilling for attaching rail doesn't show holes on both sides of the posts. Are blocks used on both sides?
This will be addressed under Amendment
A002.
6/18/25
20 X This drawing shows posts on 12'6" centers, is that correct?
Bid according to the plans and solicitation documents.
6/18/25
21 X
Regarding the use of a Non-Flared Terminal. We all agree that the Terminals are for vehicle traffic, but the issue here is that when you install them the head needs to be flared off the road a minimum of one foot. By doing this on a median it places the head of the Terminal into the Off-road vehicle's road. You also have a blunt end of Guardrail in the median on the off-road vehicle side where the Terminal meets the median rail.
Bid according to the plans and solicitation documents.
6/18/25
22 X
I am trying to put together a bid Would I be able to get access to your bid quantities for the earthwork, aggregate, HMAC, or concrete so that I can provide them an accurate estimate of testing that will need performed for this contract? If there are no bid quantities, could I get a link to the plans and specials to try to estimate based on that?
Please see the plans and solicitation documents on SAM.gov:
https://sam.gov/opp/11e11bc0b7e44b108
4585806fe3afa96/view
23 X
After looking at your second Addendum, it shows weak post Guardrail to be installed. Is that correct instead of MGS Guardrail? The drawing you provided shows the posts placed on the joints, MGS Guardrail the posts fall 3' 1
1/2" from the joint. I have looked up some federal drawings, wouldn't 31" W-beam median
Guardrail be the best solution?
Bid according to the plans and solicitation documents.
6/18/25
24 X Would you consider an extension as this is a hard copy submission?
The Government does not intend to extend the bid opening date.