Amendment A001.pdf
PDF 310 KB Posted
- Attached to
- OR FLAP UMATILL 582(1), Mill Creek Road
- Solicitation number
- 69056724B000019
About this file
This document is an Amendment A001 to Solicitation 69056724B000019 for the OR FLAP UMATILL 582(1), Mill Creek Road construction project. The amendment revises several subsections of the Special Contract Requirements, including changes to the requirements for aggregate course preparation, mixing, spreading, compacting, and surface tolerance. It also modifies the requirements for aggregate surface reconditioning, such as excavating potholes and repairing soft and unstable areas. The solicitation is being offered by the Department of Transportation Federal Highway Administration as full and open competition with a Price Evaluation Factor for HUBZone Small Businesses.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 11/7/2024 N/A See Box 14
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056724B000019
9B. DATED (SEE ITEM 11)
10/10/2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF
N/A
D OTHER (Specify type of modification and authority) N/A
R
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
OR FLAP UMATILL 582(1), Mill Creek Road
See page 2.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A001, dated 11-07-2024 OR FLAP UMATILL 582(1) Solicitation No. 69056724B000019 Mill Creek Road
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Page F-4 through F-5, Subsection 301.03, General. Revises Subsection.
Page F-9, Subsection 303.06, Aggregate Reconditioning. Revises Subsection.
ENCLOSURES
Pages:
F-4 through F-5 / F-9
F-4
Special Contract Requirements Project: OR FLAP UMATILL 582(1), Mill Creek Road
DIVISION 300
AGGREGATE AND BASE COURSES
Section 301. — UNTREATED AGGREGATE COURSES
04/02/21– FP-14
Construction Requirements
301.03 General. Delete the text of this Subsection and substitute the following:
Prepare surfaces receiving aggregate courses according to Section 204 or 303 as applicable.
After a representative quantity of aggregate is produced, submit proposed target values for the appropriate sieve sizes along with a representative 400-pound sample at least 14 days before incorporating the aggregate into the work. Submit target values to the CO. Submit aggregate samples to the Vancouver Laboratory.
Set target values for base aggregate within the gradation ranges shown in Table 703-2 for the specified grading designation. List the percent passing for all sieve sizes shown in Table 703-2.
Target values for non-specification sieves are necessary for performing The Humphres Method of Granular Soils.
Remove and dispose of aggregate base grading D (temporary) when temporary widening is no longer needed. After removal, restore ditch lines and grades in areas of temporary widening as shown on the plans.
After placing the final 4-inch lift of new aggregate base, traffic should not be permitted before the chip seal construction is complete.
301.04 Mixing and Spreading. Delete the text of this Subsection and substitute the following:
Use the optimum moisture content from the Government-performed Humphres Test. Mix aggregate and water to obtain a uniform mixture with a moisture content within 1 percent of the optimum moisture content. Spread and shape uniform layers of mixtures on prepared surfaces.
Do not place mixtures in compacted layers thicker than 6 inches (150 millimeters). Compact each layer according to Subsection 301.05 before placing the next layer. Route hauling equipment uniformly over the full surface width to minimize rutting and uneven compaction.
If the calculated mean value for a tested sieve differs from the target value by more than the allowable deviation for that sieve, terminate placement and submit new target values with another aggregate sample to the Vancouver Laboratory for a new Humphres Test.
Revised by Amendment A001
F-5 DIVISION 300
Project: OR FLAP UMATILL 582(1), Mill Creek Road
301.05 Compacting. Delete the text of the first paragraph and substitute the following:
The Government will determine the maximum density and optimum moisture according to the test procedures described on pages 92 to 98 of Highway Research Board Bulletin No. 319, dated 1962, The Humphres Method of Granular Soils. Use the data provided to determine the maximum density based on the gradation of field compaction samples.
301.06 Surface Tolerance. Delete the text of this Subsection and substitute the following:
When grade finishing stakes are required according to Subsection 152.05(f), finish surfaces to within ±0.05 feet from the staked line and grade elevation (or from the design line and grade elevation if Automated Machine Guidance (AMG) methods are used).
When grade finishing stakes are not required according to Subsection 152.05(f), shape surfaces to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations exceeding ½ inch in 10 feet between two contacts of the straightedge with the surface.
Correct defective areas by loosening, adding, or removing material; reshaping; and compacting.
301.08 Acceptance. Amend as follows:
Delete the first sentence of the second paragraph and substitute the following:
Aggregate gradation, SEP, and fractured faces will be evaluated under Subsection 106.05.
Delete paragraph (b) and substitute the following:
(b) SE/P200 (SE/P75) Index (SEP). The lower specification limit for the SEP is 1.000.
Add the following:
(c) Fractured faces. The lower specification limit is 50 percent.
Measurement
301.09 Add the following:
Do not measure aggregate base courses placed at the Optional Contractor Staging Areas shown on the plans.
F-9
Project: OR FLAP UMATILL 582(1), Mill Creek Road
Section 303. — ROAD RECONDITIONING
Construction Requirements
303.06 Aggregate Surface Reconditioning. Amend as follows:
Delete the text of this Subsection and substitute the following:
Excavate 6-inch-deep pothole every 1000 feet along centerline of Mill Creek Road within the Project limits to verify existing aggregate depths. Backfill excavated potholes according to Subsection 204.10. Compact the backfill material according to Subsection 204.11.
Repair soft and unstable areas to the full aggregate surface depth and according to Subsection 204.07. Scarify the thickness of aggregate surfacing material to 6 inches. Remove irregularities and shape to a uniform surface. Finish and compact the surface according to Subsection 302.05.
Add the following:
See ora-umatill582-1_Pavement Evaluation.pdf listed under FAR Clause 52.236-4 Physical Data (Apr 1984), and comply with the recommendations of 6.2.1.
| AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT |
| A001 |
File details come from the government source that posted it. Updated .