Tabulation of Bids_MT BIGHORN 46(1)pdf.pdf
PDF 320 KB Posted
- Attached to
- MT BIGHORN 46(1) WARMAN LOOP ROAD Federal contract opportunity
- Solicitation number
- 69056724B000008
About this file
This document is a tabulation of bids report for the MT BIGHORN 46(1) WARMAN LOOP ROAD project. The project involves full depth reclamation over 47,500 square yards, 3,500 square yards of placed riprap, 185 cubic yards of roadway aggregate, and asphalt concrete pavement. The solicitation was issued by the Department of Transportation Federal Highway Administration as solicitation number 69056724B000008. The bids were opened on February 6, 2024 in Vancouver, WA. Riverside Contracting, Inc. provided the lowest bid at $2,622,675 while the engineer's estimate was $4,104,789.50. FM Construction LLC bid $4,204,224.72. The anticipated award date is not provided. The document lists the line items, quantities, units, unit prices, and amounts for each bidder and the engineer's estimate.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidSum_MT BIGHORN 46(1).pdf | ||
| QA_02-05-2024.pdf | ||
| QA_01-31-2024.pdf | ||
| QA_01-29-2024.pdf | ||
| Amendment A001.pdf | ||
| QA_01-24-2024.pdf | ||
| QA_01-23-2024.pdf | ||
| MDT Structure Inspection Report v1.2_02247_01-31-2022_RFS.pdf | ||
| mt-a0300461_control-points.xlsx | XLSX spreadsheet | |
| mt-a0300461_Geotechnical Pavement Recon Report.pdf | ||
| mt-a0300461_plans.pdf | ||
| mt-a0300461_WarmanLoopRoad_HydraulicsReport.pdf | ||
| mt-a0300461_WarmanLoopRoad_RevisedFinalGeotechnicalReport.pdf | ||
| Physical Data MT BIGHORN 46(1).zip | ZIP file | |
| FLH Bridge oversized or overload vehicle permit request form Oct 2018.pdf | ||
| mt-a0300461_proposedalignment.pdf | ||
| IFB 69056724B000008.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 02/07/24
1 out of 7 Project No: MT BIGHORN 46(1)
Project Name: Warman Loop Road
Solcitation No: 69056724B000008
Division: Western Federal Lands
State: MT County: BIGHORN
Schedule: A
Schedule Type: Base
Federal Land: Opened at: Vancouver, WA
Opened by: Marino Chea
Date: 02/06/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed:
Title:
Date:
Contract Awarded to:
Contractor
RIVERSIDE CONTRACTING, INC.
5571 Alloy South Missoula, MT 59808
FM Construction LLC 157 High Eagle Ave Crow Agency, MT 59022
Engineer's Estimate
Award Date:
Comment Bid Amount
$4,104,789.50
$4,204,224.72
$2,622,675.00
Responsive
Project No: MT BIGHORN 46(1)
Project Name: Wannan Loop Road
Line Item
Number
A0020
A0040
A0060
A0080
A0l00
Pay Item No.
15101-0000
15201-0000
15301-0010
15401-0000
15501-0000
Description Quantity
MOBILIZATION
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
CONSTRUCTION SURVEY AND STAKING
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
CONTRACTOR QUALITY CONTROL AND ASSURANCE
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
CONTRACTOR TESTING
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
CONSTRUCTION SCHEDULE
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
Report Date: 02/07/24 2 out of?
Schedule: A
Schedule Type: Base
Unit Unit Price
Lump Sum Lump Sum
LPSM Lump Sum
Lump Sum Lump Sum
LPSM Lump Sum
Lump Sum Lump Sum
LPSM Lump Sum
Lump Sum Lump Sum
LPSM Lump Sum
Lump Sum Lump Sum
LPSM Lump Sum
Amount
$1,040,000.00 $458,303.00 $250,000.00
$145,000.00 $77,140.91 $80,000.00
$110,000.00 $197,881.92
$70,000.00
$70,000.00 $87,501.03 $70,000.00
$15,000.00 $11,220.11 $5,000.00
A0120 15702-6000 SOIL EROSION CONTROL, TEMPORARY STREAM DIVERSION (WAR MAN CREEK)
RIVERSIDE CONTRACTING, INC. Lump Sum $55,000.00 FM Construction LLC Lump Sum $34,394.80 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
A0140 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
RIVERSIDE CONTRACTING, INC. $5.25 $32,812.50
FM Construction LLC $6.13 $38,312.50 Engineer's Estimate 6,250 LNFT $7.00 $43,750.00
Project Name: Wannan Loop Road
Line Item
Number
A0160
A0180
A0200
A0220
A0240
A0260
A0280
Pay Item No.
15802-0000
20301-2400
20405-3000
25101-0400
30202-2000
30205-0500
30402-5600
Description Quantity
WATERING FOR DUST CONTROL
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate ALL
REMOVAL OF SIGN
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 21
SUBEXCAVATION, 18-INCHDEPTH
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 3,500
PLACED RIPRAP, METHOD A, CLASS 4
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 185
ROADWAY AGGREGATE, METHOD 2
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 175
ROADWAY AGGREGATE, SHOULDER FINISHING
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 3.990
FULL DEPTH RECLAMATION, METHOD 2, 9-INCH DEPTH
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 47,500
Report Date: 02/07/24 3 out of?
Schedule: A
Schedule Type: Base
Unit Unit Price Amount
Lump Sum $15,000.00 Lump Sum $56,581.77
LPSM Lump Sum $10,000.00
$250.00 $5,250.00 $322.74 $6,777.54
EACH $250.00 $5,250.00
$130.00 $455,000.00 $83.71 $292,985.00
SQYD $50.00 $175,000.00
$285.00 $52,725.00 $215.35 $39,839.75
CUYD $200.00 $37,000.00
$125.00 $21,875.00 $69.79 $12,213.25
TON $60.00 $10,500.00
$45,000.00 $179,550.00 $4,214.89 $16,817.41
MILE $12,000.00 $47,880.00
$2.50 $118,750.00 $1.69 $80,275.00
SQYD $4.00 $190,000.00
Project Name: Wannan Loop Road
Line Item
Number Pay Item No. Description
Tabulation of Bids
Quantity
Schedule: A
Schedule Type: Base
Unit Unit Price
Report Date: 02/07/24 4 out of?
Amount
A0300 40101-5500 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH OR 3/4-INCH NOMINAL MAXIMUM SIZE
AGGREGATE, <0.3 MILLION ESAL (TYPE III ROUGHNESS)
RIVERSIDE CONTRACTING, INC. $155.00 $1,201,250.00
FM Construction LLC $262.41 $2,033,677.50 Engineer's Estimate 7,750 TON $160.00 $1,240,000.00
A0340 40105-3000 ANTISTRIP ADDITIVE, TYPE 3
RIVERSIDE CONTRACTING, INC. $245.00 $19,110.00
FM Construction LLC $466.67 $36,400.26 Engineer's Estimate 78 TON $350.00 $27,300.00
A0380 41102-1000 PRIME COAT, METHOD 1
RIVERSIDE CONTRACTING, INC. $0.55 $26,125.00
FM Construction LLC $1.17 $55,575.00 Engineer's Estimate 47,500 SQYD $1.50 $71,250.00
A0400 57501-0000 MINOR BRIDGE WORK
RIVERSIDE CONTRACTING, INC. Lump Sum $20,000.00 FM Construction LLC Lump Sum $11,990.20 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
A0420 60201-0400 12-INCH PIPE CUL VERT
RIVERSIDE CONTRACTING, INC. $225.00 $7,650.00
FM Construction LLC $214.04 $7,277.36 Engineer's Estimate 34 LNFT $70.00 $2,380.00
A0440 60201-0800 24-INCH PIPE CULVERT
RIVERSIDE CONTRACTING, INC. $255.00 $21,420.00
FM Construction LLC $222.88 $18,721.92 Engineer's Estimate 84 LNFT $150.00 $12,600.00
A0460 60220-2400 9 FEET SPAN, 5 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT
RIVERSIDE CONTRACTING, INC. $4,250.00 $225,250.00
FM Construction LLC $7,512.79 $398,177.87 Engineer's Estimate 53 LNFT $1,600.00 $84,800.00
Project Name: Wannan Loop Road
Line Item
Number
A0480
A0500
Pay Item No.
60704-0000
62201-0300
Description Quantity
CLEANING CUL VERT IN PLACE
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 7
DUMP TRUCK, 12 CUBIC YARD MINIMUM CAPACITY
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 10
Schedule: A
Schedule Type: Base
Report Date: 02/07/24 5 out of?
Unit Unit Price Amount
$7,000.00 $49,000.00 $4,594.98 $32,164.86
EACH $2,000.00 $14,000.00
$180.00 $1,800.00 $199.30 $1,993.00
HOUR $150.00 $1,500.00
A0520 62201-0550 BACKHOE LOADER, 6 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 24-INCH WIDTH
RIVERSIDE CONTRACTING, INC. $220.00 $2,200.00
FM Construction LLC $270.06 $2,700.60 Engineer's Estimate 10 HOUR $150.00 $1,500.00
A0540 62201-2850 MOTOR GRADER, 12 FOOT MINIMUM BLADE
RIVERSIDE CONTRACTING, INC. $270.00 $2,700.00
FM Construction LLC $234.65 $2,346.50 Engineer's Estimate 10 HOUR $200.00 $2,000.00
A0560 62301-0000 GENERAL LABOR
RIVERSIDE CONTRACTING, INC. $70.00 $1,400.00
FM Construction LLC $85.89 $1,717.80 Engineer's Estimate 20 HOUR $90.00 $1,800.00
A0580 62405-0300 PLACING CONSERVED TOPSOIL, 4-INCH DEPTH
RIVERSIDE CONTRACTING, INC. $55.00 $11,550.00
FM Construction LLC $7.00 $1,470.00 Engineer's Estimate 210 SQYD $5.00 $1,050.00
A0600 62502-0000 TURF ESTABLISHMENT (DRY METHOD)
RIVERSIDE CONTRACTING, INC. $20.00 $4,200.00
FM Construction LLC $13.89 $2,916.90 Engineer's Estimate 210 SQYD $5.00 $1,050.00
Project Name: Wannan Loop Road
Line Item
Number
A0620
A0640
A0660
A0680
A0700
A0720
Pay Item No.
63302-0000
63309-0000
63401-0700
63401-0700
63401-0800
63502-0600
Description Quantity
SIGN SYSTEM
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 112
DELINEATOR (DESIGN F)
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 30
PAVEMENT MARKINGS, TYPED, SOLID (YELLOW)
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 2,350
PAVEMENT MARKINGS, TYPED, SOLID (WHITE)
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 50
PAVEMENT MARKINGS, TYPED, BROKEN (YELLOW)
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 20,800
TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 2
Schedule: A
Schedule Type: Base
Report Date: 02/07/24 6 out of?
Unit Unit Price Amount
$145.00 $16,240.00 $168.59 $18,882.08
SQFT $175.00 $19,600.00
$86.00 $2,580.00 $99.17 $2,975.10
EACH $50.00 $1,500.00
$1.05 $2,467.50 $1.17 $2,749.50
LNFT $0.75 $1,762.50
$1.05 $52.50 $1.17 $58.50
LNFT $0.75 $37.50
$0.25 $5,200.00 $0.29 $6,032.00
LNFT $0.25 $5,200.00
$430.00 $860.00 $495.84 $991.68
EACH $325.00 $650.00
A0740 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH
RIVERSIDE CONTRACTING, INC. $34.00 $3,400.00
FM Construction LLC $57.84 $5,784.00 Engineer's Estimate 100 EACH $40.00 $4,000.00
Project Name: Warman Loop Road
Line Item
Number
A0760
A0780
A0800
Pay Item No.
63504-1000
63506-0500
63506-0600
Description Quantity
TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 247
TEMPORARY TRAFFIC CONTROL, FLAGGER
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 1,360
TEMPORARY TRAFFIC CONTROL, PILOT CAR
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate 200
Total Schedule - All Items
RIVERSIDE CONTRACTING, INC.
FM Construction LLC Engineer's Estimate
Schedule: A
Schedule Type: Base
Report Date: 02/07/24 7 out of 7
Unit Unit Price Amount
$76.00 $18,772.00 $87.50 $21,612.50
SQFT $45.00 $11,115.00
$90.00 $122,400.00 $77.36 $105,209.60
HOUR $70.00 $95,200.00
$116.00 $23,200.00 $112.78 $22,556.00
HOUR $90.00 $18,000.00
$4,104,789.50 $4,204,224.72 $2,622,675.00
| 2024-02-07T07:03:01-0800 | |
| MARINO CHEA |