QA_08-19-2024.pdf
PDF 106 KB Posted
- Attached to
- MT FLAP DOT 236(2), Winifred North Federal contract opportunity
- Solicitation number
- 69056724B000007
About this file
This document contains questions and answers regarding a federal contract opportunity for the MT FLAP DOT 236(2), Winifred North project. The key details are:
The federal contract opportunity is Solicitation Number 69056724B000007, issued by the Department of Transportation Federal Highway Administration. The project involves roadway work, and the agency has posted preliminary documents on SAM.gov to aid prospective bidders. Bidders are instructed to monitor SAM.gov for the actual solicitation release date and advertisement period, and to submit questions during the advertisement period. The contract requires the contractor to commence work within 10 calendar days of receiving the notice to proceed, and complete the work by 10/31/2025. The questions cover topics such as cattle guard specifications, color requirements, drawings, and excavation/borrow material. The agency provides responses indicating bidders should refer to the solicitation documents for the requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| BidTab MT FLAP DOT 236(2).pdf | ||
| BidSum_MT FLAP DOT 236(2).pdf | ||
| QA_08-13-2024.pdf | ||
| QA_08-12-2024.pdf | ||
| Amendment A001.pdf | ||
| QA_07-29-2024.pdf | ||
| mta-dot236-2_WinifredNorth_Final Geotechnical Report-Signed.pdf | ||
| mta-dot236-2_WinifredNorth_plans.pdf | ||
| IFB 69056724B000007.pdf | ||
| mta-dot236-2_WinifredNorth_Grizzly_Bear_Sightings_Log.docx | DOCX document | |
| mta-dot236-2_WinifredNorth_Hydraulics_Memo_Final.pdf | ||
| mta-dot236-2_WinifredNorth_control-points.xlsx | XLSX spreadsheet |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MT FLAP DOT 236(2)
Winifred North
# General Technical Question Answer Date
1 X Is it OK to provide you with 4–12‐foot Cattle
Guards? (You are requesting 2‐24 foot)
The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.
Please monitor the SAM site for the actual date of solicitation release
(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.
7/25/2024
2 X What are the load specs for the Cattle Guards needed? ie U‐54?, U‐80?, etc
The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.
Please monitor the SAM site for the actual date of solicitation release
(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.
7/25/2024
3 X Wanted to verify the color you wanted (green or yellow?)
The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.
Please monitor the SAM site for the actual date of solicitation release
(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.
7/25/2024
Check General or Technical
4 X Can you provide Drawings for the project?
The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.
Please monitor the SAM site for the actual date of solicitation release
(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.
7/25/2024
5 X
It appears there is a typo in Section 52.211‐10
“The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 10/31/2025 subject to such extensions as may be authorized. The time stated for completion shall include final cleanup of the premises. The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 10/28/2025. “
Is the NTP meant to be 10/28/2024?
Yes. This will be addressed under
Amendment A001.
7/29/2024
6 X
My company recently became a registered entity and I am currently set to “Pending” on approval for a data entry role, and we cannot see interested bidders. Would you be able to provide any guidance or help point us in the right direction on how to obtain access to interested bidders?
If you need additional assistance, you can reach the Federal Service Desk at 866‐606‐
8220 or https://www.fsd.gov/gsafsd_sp?id=gsa_ind ex.
7/30/2024
7 X
SCR 703.05A (f) States 70 percent minimum fractured faces. Does this include more than a single fractured face on the aggregate or just a single fractured face?
In accordance with SCR 703.05A, comply with ASTM D 5821, and please submit bids according to the solicitation documents.
8/12/2024
8 X
Insteand of using a motor grader as specified under SCR 311.06 for spreading material, would a Box Aggregate Spreader such as a DOMOR
R600C be acceptable?
Comply with the requirements of SCR
311.06, and please submit bids according to the solicitation documents.
8/12/2024
9 X
Why is there is no bid item for “Traffic Control
Supervisor.” Was that omitted in error or is it incidental to the project? It may benefit to all parties involved to include that bid item.
The Government chose not to have a pay item for this. Please submit bids according to the solicitation documents.
8/14/2024
10 X
SCR 303.07(b) refers one to Subsection 303.06, which says “Repair soft and unstable areas to the full aggregate surface depth according to
Subsection 204.07”, and Subsection 204.07 says
“Excavate material to the required limits.
Dispose of unsuitable material according to
Subsection 204.14... Place backfill material...
etc." Does this work get paid for under the
“A0200 Unclassified Excavation” and “A0220
Unclassified Borrow” items for is it all incidental to the Type 2 Roadway Reconditioning? If it is all incidental can the government at least give us an estimate on the quantity of soft areas to be removed and replaced? Without that quantity it seems like an unreasonable risk to place on the contractor if the soft areas are not quantified. There will be material and hauling costs that are not quantifiable. In such a remote area we will need to know how much borrow material to generate and haul to put together an accurate estimate.
The Government does not intend to provide additional information on this. See
Subsection 109.05 for how the
Government will pay for work, and please submit bids according to the solicitation documents, which includes the bid schedule.
8/19/2024