This document is a set of questions and answers related to a federal contract opportunity for the MT FLAP DOT 236(2), Winifred North project. The key details are:

The preliminary documents for this project have been posted on SAM.gov to help prospective bidders identify the location and type of work. Bidders are advised to monitor SAM.gov for the actual solicitation release date and duration of the advertisement period, and to submit any questions during the advertisement period. The project appears to involve the installation of cattle guards, with specific requirements around the number, size, and load specifications. There are also questions about the color of the cattle guards and the availability of project drawings. The solicitation includes a key milestone date of 10/31/2025 for project completion, with a notice to proceed expected by 10/28/2024. Bidders are advised to comply with the stated requirements in the solicitation documents when submitting their bids.

View the file

Other files for this federal contract opportunity

Other files attached to MT FLAP DOT 236(2), Winifred North, newest first.
File Type Posted
BidTab MT FLAP DOT 236(2).pdf PDF
BidSum_MT FLAP DOT 236(2).pdf PDF
QA_08-19-2024.pdf PDF
QA_08-12-2024.pdf PDF
Amendment A001.pdf PDF
QA_07-29-2024.pdf PDF
mta-dot236-2_WinifredNorth_Final Geotechnical Report-Signed.pdf PDF
mta-dot236-2_WinifredNorth_Grizzly_Bear_Sightings_Log.docx DOCX document
mta-dot236-2_WinifredNorth_plans.pdf PDF
mta-dot236-2_WinifredNorth_Hydraulics_Memo_Final.pdf PDF
mta-dot236-2_WinifredNorth_control-points.xlsx XLSX spreadsheet
IFB 69056724B000007.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MT FLAP DOT 236(2)

Winifred North

# General Technical Question Answer Date

1 X Is it OK to provide you with 4–12‐foot Cattle

Guards? (You are requesting 2‐24 foot)

The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.

Please monitor the SAM site for the actual date of solicitation release

(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

7/25/2024

2 X What are the load specs for the Cattle Guards needed? ie U‐54?, U‐80?, etc

The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.

Please monitor the SAM site for the actual date of solicitation release

(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

7/25/2024

3 X Wanted to verify the color you wanted (green or yellow?)

The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.

Please monitor the SAM site for the actual date of solicitation release

(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

7/25/2024

Check General or Technical

4 X Can you provide Drawings for the project?

The preliminary documents posted on sam.gov have been posted to aid prospective bidders in identifying the location and type of work for this project.

Please monitor the SAM site for the actual date of solicitation release

(https://sam.gov/), and the duration of the advertisement period; and submit your questions during the advertisement period for the project. To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

7/25/2024

5 X

It appears there is a typo in Section 52.211‐10

“The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 10/31/2025 subject to such extensions as may be authorized. The time stated for completion shall include final cleanup of the premises. The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 10/28/2025. “

Is the NTP meant to be 10/28/2024?

Yes. This will be addressed under

Amendment A001.

7/29/2024

6 X

My company recently became a registered entity and I am currently set to “Pending” on approval for a data entry role, and we cannot see interested bidders. Would you be able to provide any guidance or help point us in the right direction on how to obtain access to interested bidders?

If you need additional assistance, you can reach the Federal Service Desk at 866‐606‐

8220 or https://www.fsd.gov/gsafsd_sp?id=gsa_ind ex.

7/30/2024

7 X

SCR 703.05A (f) States 70 percent minimum fractured faces. Does this include more than a single fractured face on the aggregate or just a single fractured face?

In accordance with SCR 703.05A, comply with ASTM D 5821, and please submit bids according to the solicitation documents.

8/12/2024

8 X

Insteand of using a motor grader as specified under SCR 311.06 for spreading material, would a Box Aggregate Spreader such as a DOMOR

R600C be acceptable?

Comply with the requirements of SCR

311.06, and please submit bids according to the solicitation documents.

8/12/2024

File details come from the government source that posted it. Updated .