QA_12-09-2020.pdf

PDF 96 KB Posted

Attached to
WA NPS BP MORA 2019(1), NISQUALLY GLACIER BRIDGE PRESERVATION
Solicitation number
69056720B000029
Issued by

About this file

This document contains correspondence between a contractor and federal agency regarding technical questions on a bridge preservation project solicitation. The solicitation was for the WA NPS BP MORA 2019(1) Nisqually Glacier Bridge Preservation project issued by the Department of Transportation Federal Highway Administration. Contractors had questions about painting requirements and limits referred to in Note 3 of plan Sheet E.1. However, the agency clarified that the plan set referenced in the question does not apply to this solicitation. Contractors were directed to review the plan set and solicitation documents available on SAM.gov under opportunity number 69056720B000029 to prepare their bids according to the correct project requirements.

View the file

Other files

File Type Posted
BidSum.pdf PDF
Sign-in sheet.pdf PDF
A001.pdf PDF
QA_12-23-2020.pdf PDF
QA_12-08-2020.pdf PDF
Nisqually Glacier Bridge - 2018 Inspection.pdf PDF
Nisqually Glacier Bridge - As-built 1957.pdf PDF
Nisually Bridge Plans.pdf PDF
IFB Nisqually Bridge.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WA NPS BP MORA 2019(1)

Nisqually Glacier Bridge Preservation

# General Technical Question Answer Date

1 X

Per the plans, Sheet 1 of 3 Bridge Preservation Details, Note 3 states, “ Additional small areas of damaged existing paint with peeling and /or rusting may exist outside of the shown painting limits of painting, Steel Structure. The CO will identify these areas. Paint these areas similar to the areas shown within limits of painting, Steel Structure.”

Question: These locations are not identified on the drawing nor is there a bid item listing a quantity. How do we determine the amount of locations and how do these items get paid.

The plans you are looking at are the Pre‐Ad Plans because Sheet E.1 does not have a Note 3. Please bid according to the solicitation documents at the following link.

https://beta.sam.gov/opp/04a3135b246b4 89da997430c1b2be129/view

12/8/2020

2 X

Yes you are correct. That is the discrepancy.

Please look at attached drawing. I have highlighted Note 3 in red. If the MORA Plans are not to be included in the bidding process please let me know that as that will eliminate that work in Note No. 3.

We don’t understand your question. The attached pdf is Plan Sheet E.1 of the Pre‐Ad Plan Set that does not apply to this solicitation. The plan set that applies to this solicitation is at the beta.sam website link we’ve previously provided and Sheet E.1 of the solicitation plan set does not have the Note 3 that was in the Pre‐Ad Plan Set. Bid according to the solicitation plan set and other requirements in the solicitation documents.

12/8/2020