This document contains questions and answers regarding a federal contract solicitation for road repair work. The solicitation is for WA FS ERFO 2017(1)-23(3), Okanogan-Wenatchee 2017 Repairs, Phase 3 with the Department of Transportation Federal Highway Administration. The work consists of installing culverts and aquatic organism pipes, rebuilding damaged road slopes, rehabilitating roadways, reconstructing ditches and placing aggregate and chip seal surfacing along 1.942 miles of roadway. The estimated price range for the contract is between $1 million to $2 million. The tentative fixed completion date once the solicitation is issued is Fall 2020. The questions and answers provide clarification that some excavated material from the sites may be suitable for use as fill material on other sites, and that excavation work shown on one typical section is considered incidental to the roadway reconditioning work.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WA FS ERFO 2017(1)‐23(3)
Okanogan‐Wenatchee 2017 Repairs, Phase 3
# General Technical Question Answer Date
1 X
Per the specs in Section 204.06 Roadway Excavation, it states the “All excavated material is unsuitable.” Is it intended that all of the excavated material at each site be hauled off and replaced with import borrow?
See Subsections 204.10 and 204.14 of FP‐ 14.
1/6/2020
2 X Can any of the excavated material be used as fill material on any of the sites that require fill?
In accordance with Subsections 204.10 and 208.03, suitable material from excavations may be incorporated into embankment construction.
1/6/2020
3 X
Line item A0520 Roadway reconditioning has 690 LF of work in section FSR 5100‐100. The typical section of this area on plan page C.6 shows “est. 450 cu yds) of excavation to take place here. The line item for roadway excavation does not contain a quantity here. Is this excavation incidental to the roadway reconditioning or will it be measured and paid under section 204.
Typical Section 13 on Sheet C.6 says remove slide material via roadway reconditioning which is covered under Section 303.
1/16/2020
Check General or Technical