RFP_Yellowstone.pdf
PDF 588 KB Posted
- Solicitation number
- 69056718R000003
About this file
This document provides details for a new Multiple Award Task Order Contract (MATOC) solicitation for highway, bridge, and road construction projects in Yellowstone National Park, Grand Teton National Park, and surrounding areas within 100 air-miles. The Federal Highway Administration plans to award two to eight Indefinite Delivery Indefinite Quantity contracts valued up to $350 million total over five years. Two awards will be reserved for small businesses. Task orders will range from $2 million to $50 million. Offerors must review the forthcoming Request for Proposals for submission instructions and evaluation criteria. Interested vendors should register at FBO.gov to receive notification and view the vendor list when solicitation documents are posted in fall/winter 2018.
Request for Proposals
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_A001.pdf | ||
| Technical_Information_Form_1.pdf | ||
| Master_Subcontracting_Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MULTIPLE AWARD TASK ORDER CONTRACT
(MATOC) REQUEST FOR PROPOSALS (RFP)
Solicitation #: 69056718R000003
(Proposals Due Date: See Page A-3, Block 13A)
Yellowstone, Grand Teton, & Surrounding area MATOC
ISSUING OFFICE: U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
610 EAST FIFTH STREET
VANCOUVER, WA 98661-3801
Phone: (360) 619-7520 – FAX: (360) 619-7932 email: wfl.contracts@dot.gov
PROPOSAL REMINDERS
Electronic proposals will be accepted. Submit proposals in accordance with the instruction in section L. Before submitting your proposal, please review the following:
• Have you completed the Authority to Sign?
• Have you completed and signed the SF1442, Solicitation, Offer & Award?
• Have you acknowledged all amendments?
• Have you registered and completed your
Representations & Certifications in the System of Award Management?
• Have you completed the general information and technical proposal?
QUICK INDEX
Part I – The Schedule
Part II – Contract Clauses
Part III – List of Documents, Exhibits, and Attachments
Part IV – Representations and Instructions mailto:wfl.contracts@dot.gov
PROJECT NAME Yellowstone, Grand Teton, & Surrounding area
MATOC
NATIONAL FOREST/PARK Multiple
COUNTY Multiple
STATE Multiple
Offer Submittal Checklist Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contract (MATOC)
OFFER SUBMITTAL CHECKLIST
Before submitting your offer, please review the following:
Done?
Is this in the
Email?
Offer Delivery
Did I send proposal attachments to the correct email box?
Does the subject line for the delivery email structured correctly?
69056718R000003 – Contractor Name – Email X of Y
Did I attach all required submittals?
Pages A-3 & A-4 (SF 1442, Solicitation Offer & Award) Did I include our firm name and address in block 14?
Did I include our firm’s phone number in block 15?
Did I include our firm’s remittance address in block 16?
(Use when different than block 14)
Did I include my Unique Entity Identifier (formerly DUNS) and my Cage Code?
Did I include the number & date of all amendments in block 19?
Did the appropriate official sign/date in block 20A, 20B & 20C?
Authority to Sign Did I include a completed form for each person signing the SF1442?
Proposal Submittal See Sections L and M Did I include the General Information and Technical Proposal?
Did I include a Technical Information Form 1 for each project submitted for Evaluation Factor 1?
Did I include a letter from my bonding agent indicating current bonding limits for Evaluation Factor 2?
Did I include Past Performance Information made available from project owners for Factor 3, if applicable?
Did I include all other written submittals required by the Factors and Subfactors listed in section M?
System for Award Management (SAM) https://www.sam.gov/portal/public/SAM/
Is our SAM record active and information up-to-date?
Have we completed our online representations and certifications in
SAM?
Veteran Reporting (FAR Clause 52.222-37) If applicable, did I ensure our firm has completed this annual report?
NOTE: The Contractor is fully responsible to verify that all data is correct each time a offer package is submitted. Failure to properly input and/or update your data may cause the offer to be rejected.
Offer Submittal Checklist
Driving Directions to our Vancouver Washington Office:
Directions to WFLHD
Authority to Sign
INSTRUCTIONS: When the offeror/principal is a corporation, include this certification with your offer/bid.
Corporate Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the corporation named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this corporation;
that the offer was duly signed for and on behalf of said corporation by authority and scope of its governing body, and within the scope of its corporate powers.
_____________________________________ (signature) Affix Corporate Seal
_____________________________________ (title)
INSTRUCTIONS: When the offeror/principal is a limited liability company, include this certification with your offer/bid.
Limited Liability Certificate
I, ____________________________________________ (name), certify that I am the
________________________________________(title), of the limited liability company named as the Offeror/Principal herein;
that _________________________________________(name), who signed this offer and/or bid bond on behalf of ___________________________ (company name) is
________________________________________ (title) of this company;
that the offer was duly signed for and on behalf of said company by authority and scope of its governing body, and within the scope of its powers.
_____________________________________ (signature) Affix Company Seal (as applicable) __________ _________________________ (title)
INSTRUCTIONS: When the offeror/principal is a partnership, include this
Authority to Bind Partnership
This certifies that the names and signatures of all partners are listed below, and that the person signing the proposal has the authority to actually bind the partnership pursuant to its partnership agreement. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all partners)
INSTRUCTIONS: When the offeror/principal is a joint venture, include this
Authority to Bind Joint Venture
This certifies that the person signing the proposal has the authority to actually bind the joint venture pursuant to its joint venture agreement, and that each of the named persons listed below individually has full authority to enter into and execute contractual instruments on behalf of said joint venture, except as follows:
(State “None” or describe limitations, if any)
This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to and acknowledge by the Contracting Officer.
(Include names and signatures of all applicable individuals)
INSTRUCTIONS: When the offeror/principal is a sole proprietorship, the signature on the offer/bid and on the bonds must be as follows:
Sole Proprietorship Requirement
An Offeror/Principal that is a sole proprietorship must submit an offer/bid and a bond signed by the sole proprietor, or by one duly authorized to sign for the sole proprietor.
If the signature is by someone other than the sole proprietor, a copy of the power of attorney authorizing the individual to sign must be provided with the offer/bid.
RESERVED
Table of Contents
TABLE OF CONTENTS
Contents PART I – THE SCHEDULE ...................................................................................................... A-1
SECTION A. SOLICITATION/CONTRACT FORM NOTICE TO OFFERORS SF 1442,
SOLICITATION, OFFER AND AWARD ............................................................................. A-1
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS ...................................... B-1
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK ................. C-1
SECTION D – PACKAGING AND MARKING .................................................................. D-1
SECTION E – INSPECTION AND ACCEPTANCE ............................................................. E-1
SECTION F – DELIVERIES OR PERFORMANCE ............................................................. F-1
SECTION G – CONTRACT ADMINISTRATION DATA .................................................. G-1
SECTION H – SPECIAL CONTRACT REQUIREMENTS ................................................. H-1
PART II – CONTRACT CLAUSES ............................................................................................ I-1
SECTION I – FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES .......... I-1
Part III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS .................. J-1
SECTION J – LIST OF ATTACHMENTS ............................................................................. J-1
PART IV – REPRESENTATION AND INSTRUCTIONS ....................................................... K-1
SECTION K – REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS
OF OFFERORS OR RESPONDENTS .................................................................................. K-1
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS OR
RESPONDENTS ..................................................................................................................... L-1
SECTION M – EVALUATION FACTORS FOR AWARD ................................................ M-1
Table of Contents
A-1
Notice to Offerors Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contract (MATOC)
PART I – THE SCHEDULE
SECTION A. SOLICITATION/CONTRACT FORM NOTICE TO OFFERORS SF 1442,
SOLICITATION, OFFER AND AWARD
A.1 NOTICE TO OFFERORS
I. Solicitation Overview The primary objective of this solicitation is to solicit qualified firms for Multiple Award Task Order Contracts (MATOC) covering a 5-year period for Highway/Bridge/Road projects in Yellowstone National Park, Grand Teton National Park, and projects in the surrounding area (within approximately 100 air-miles of any Yellowstone or Grand Teton Park boundary). We plan to award between two and eight Indefinite Delivery, Indefinite Quantity (IDIQ) construction contracts; anticipating at least two will be reserved for Small Business concerns.
II. Pre-proposal Information This solicitation and subsequent contract are governed by the Federal Acquisition Regulation (FAR) and agency supplemental regulations. Task Orders to be issued under a contract will be subject to the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14 U.S. Customary Units or any subsequent FP that may be applied to the task order, as well as supplemental specifications and plan sheets. Obtain paper copies of the FP- 14 by calling 360.619.7520, e-mailing at plans_spec@dot.gov, or writing Federal Highway Administration, 610 East Fifth Street, Vancouver, WA 98661. An electronic version may be found at http://flh.fhwa.dot.gov/resources/pse/specs/
REPS & CERTS - Submit or update Representations and Certifications online at https://sam.gov before proposal submittal. For more details go to FAR Provision 52.204-8 Annual Representations and Certifications (see page K-1). If you have previously registered on-line and the NAICS code for this solicitation is different than the code listed in your online file, please note the amended changes on the lines provided in FAR 52.204-8.
NOTICE OF SAM REGISTRATION – You must have an active System for Award Management (SAM) profile prior to submittal of your offer. Failure to register prior to submittal of your offer will make your offer non-responsive.. See FAR Subpart 4.1103(b).
Register online at https://.sam.gov.
Solicitation Discrepancies: If an Offeror believes the requirements in this solicitation contain an error, omission, or are otherwise unsound, the Offeror shall immediately notify the Contracting Officer (CO) in writing with supporting rationale.
Form SF 1442 - Particular attention should be paid to Standard Form l442, Solicitation, Offer and Award, to assure that Blocks 14, 15, 16, 19, 20A, and 20C are completed correctly. Sign Block 20B. You must submit a completed ‘Authority to Sign’ document. You must also complete the representations and certifications contained in the Contract Provisions beginning on page K-1.
Failure to furnish or complete any of the above may result in your offer being rejected.
A-2
Notice to Offerors Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contract (MATOC)
Fax and Email – Email offers are required for this solicitation. Facsimile offers are not authorized for this solicitation. Offers may be modified or withdrawn by facsimile and email, if such notice is received by the time specified for receipt of offers. The Government will not be responsible for any failure attributable to the transmission or receipt of facsimile or Email data. See FAR Provision 52.215-1, Instructions to Offerors – Competitive Acquisition. Fax 360.619.7932, Email WFL.Contracts@dot.gov .
Proposal Submittals - See Subsections L and M.
Fraud Alert - Current and potential U.S. Department of Transportation (DOT) Contractors have recently been receiving fraudulent letters purporting to be issued by DOT. These fraudulent letters request that the Contractors resubmit their banking information to DOT. If you receive such a letter, please DO NOT complete the requested worksheet that is attached to the letters and DO NOT release any information. To register or update information, Contractors are required to go directly through the System for Award Management (SAM) website and never through a third party. You can access SAM at https://sam.gov.
III. Post Award Information
Contractor Performance Evaluations. This office posts performance evaluations in the Contractor Performance Assessment Reporting System (CPARS). Upon receiving an email notice of evaluation availability, you will have 30 days to review the evaluation online and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
Task Orders – All work will be issued by Task Order.
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 8/2014)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
3. DATE ISSUED PAGE OF PAGES
69056718R000003
Federal Highway Administration Western Federal Lands Highway Division 610 East Fifth Street Vancouver, WA 98661-3801
This solicitation is designated Yellowstone, Grand Teton, & Surrounding area Multiple Award Task Order Contract (MATOC).
IN STRICT ACCORDANCE WITH:
MATOC Description/Specifications/Statement of Work Federal Acquisition Regulations (FAR) and Transportation acquisition Regulations (TAR).
Period of Performance: Date of Award through 5 years.
Federal Highway Administration Western Federal Lands Highway Division 610 East Fifth Street Vancouver, WA 98661-3801
WFL.Contracts@dot.gov
See Page A-5 360-619-7520
See block 10
1 210/19/2018
11/28/2018
Specified on each TO-RFP*
WFLHD
A-3
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE.
AWARD (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 8/2014) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Unique Entity Identifier (Formerly DUNS):
Cage Code:
As determined on each Task Order
WFLHD
26. ADMINISTERED BY
Federal Highway Administration Western Federal Lands Highway Div. 610 East Fifth Street Vancouver, WA 98661-3801
27. PAYMENT WILL BE MADE BY
Federal Highway Administration Western Federal Lands Highway Div. 610 East Fifth Street Vancouver, WA 98661-3801
As determined on each Task Order
Angy Liljedahl
As determined on each Task Order
As determined on each Task Order
See Task Order
A-4
A-5
Continuation SF 1442
Block 9 FOR GENERAL INFORMATION, call 360.619.7520 from the hours of 8:00 a.m. to 4:00 p.m. local time or e-mail us at wfl.contracts@dot.gov.
FOR TECHNICAL INFORMATION (plan and specification questions only), requests for technical information about this project will only be accepted in writing. Submit questions via fax (360.619.7932) or e-mail at wfl.plans-spec@dot.gov.
QUESTIONS/ANSWERS POSTED ONLINE. You can view questions and answers on the Federal Business Opportunities (FBO) Website https://www.fbo.gov/ .
Insert the solicitation number in “Keyword / Solicitation #:”
Scroll to the project.
Make sure you are on the most recent view and look in the right section of the page for the most recent Q&A document.
SUBCONTRACTING PLAN. This Request for Proposals requires an offeror who is a large business to submit a Master Subcontracting Plan prior to MATOC Award. Do not include a Subcontracting Plan with your proposal. A large business is one whose average gross annual receipts over the past 3 years equal $36.5 million or more. For your information the subcontracting plan form is included in the appendix section of this solicitation. For your information the subcontracting plan form is included as an attachment to this RFP. This requirement does not apply to SMALL businesses.
A-6
Continuation SF 1442
B-1
SECTION B - Supplies or Services and Prices/Costs Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contract (MATOC)
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 SERVICES AND PRICE/COSTS
ITEM
No.
DESCRIPTION
Construction, Multiple Award Task Order Contract (MATOC).
Highway/Bridge/Road projects in Yellowstone National Park, Grand Teton National Park, and projects in the surrounding area (within approximately 100 air-miles of any Yellowstone or Grand Teton Park boundary)..
Offerors determined to be Technically Acceptable for this solicitation must submit a price proposal in accordance with the requirements contained in Section M. Award will be based on the evaluation criteria listed in Section M.
CLAUSES AND PROVISIONS
1. Clauses and provisions from the Federal Acquisition Regulation (FAR) and supplements thereto are incorporated in this document by reference and in full text. Those incorporated by reference have the same force and effect as if they were given in full text.
2. Clauses and provisions in this document are numbered in sequence, but do not necessarily appear in consecutive order.
3. Section K, L and M will be physically removed from the award but deemed incorporated by reference.
B-2
SECTION B - Supplies or Services and Prices/Costs
C-1
SECTION C – Description/Specifications/Statement of Work
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C.1. OVERVIEW
Western Federal Lands Highway Division (WFLHD) is in need of highway/bridge/road construction in Yellowstone and Grand Teton National Parks & the Surrounding area (within approximately 100 miles of any Yellowstone or Grand Teton Park boundary).
The scope of work includes but is not limited to bridge, highway and road construction.
Associated work such as survey, utility relocation, parking lots, and trails may be included.
Umbrella Contracts – We intend to award a minimum of two and up to eight Indefinite Delivery-Indefinite-Quantity Multiple-Award Task Order Contracts (MATOC). The number of actual awards is dependent upon the merits of the proposals received. This solicitation is a Partial Small Business Reserve and two MATOCs are reserved for small business concerns. The combined maximum quantity to be ordered over the life of all awarded contracts is $350,000,000. The combined maximum quantity for the MATOC contracts is calculated as the sum of all Task Order awards and Task Order Modifications. Each MATOC contract will be for a 5-year period.
MATOC Minimum Guarantee - The minimum amount guaranteed over the life of each MATOC contract is $25,000.
Task Orders - All work will be awarded on a Task Order basis. Task Orders will vary in size ranging from approximately $2 million to $50 million. At the Contracting Officer’s discretion, Task Orders under or over this range may be awarded.
As requirements develop and funding becomes available, Task Order Requests for Proposal (TO- RFP) will be issued. Unless there is a set aside for small business, TO-RFP will be issued to all MATOC contractors. If a project is set aside for small business, the TO-RFP will be issued only to small business MATOC contractors.
Types of Task Orders - Task orders may be Firm-Fixed-Price (FFP) of FFP with economic price adjustments.
Anticipated Projects - Table 1 lists the currently anticipated projects. This list is provided for informational purposes only. The Government is not guaranteeing the delivery of these projects via this MATOC contract.
C-2
Park
Award Year
(FY)
Project Name
FHWA #
Construction Estimate (million)
YELL 2019
Canyon to Tower, Phase 3 and Roosevelt Lodge Parking
WY NPS YELL
10(22)
More than $10,000,000
GRTE 2019 Moose Wilson - MP 4.8 - 6.2 TBD Between $1,000,000 and
$5,000,000
YELL 2019 North Entrance
MT NPS YELL
11(2)
Between $5,000,000 and $10,000,000
YELL 2019 Lewis River Bridge
WY NPS YELL
14(1)
More than $10,000,000
GRTE 2019 Gros Ventre Repair TBD Between $1,000,000 and
$5,000,000
GRTE 2019
Moran to Yellowstone Boundary
TBD
Between $1,000,000 and
$5,000,000
GRTE 2019 Large Pavement Pres Project TBD Between $5,000,000 and
$10,000,000
GRTE 2020 Moose Wilson - MP 6.2 - 6.9 TBD Between $1,000,000 and
$5,000,000
YELL 2020 Old Faithful to West Thumb
WY NPS YELL
10(23)
More than $10,000,000
GRTE 2121 Pathways Phase VI TBD Between $1,000,000 and
$5,000,000
GRTE 2121
Colter Bay Visitor Parking Area (Phase 1)
TBD
Between $1,000,000 and
$5,000,000
GRTE 2121 Moose Wilson - MP 3.0 - 4.8 TBD Between $5,000,000 and
$10,000,000
YELL 2121
Norris to Golden Gate, Phase 3 and Norris Geyser Basin Parking
WY NPS YELL
10(24)
More than $10,000,000
YELL 2021 Yellowstone River Bridge
WY NPS YELL
12(2)
More than $10,000,000
GRTE 2022
Teton Park Road - Moose to Taggart Lake
TBD
Between $1,000,000 and
$5,000,000
GRTE 2022
Colter Bay Visitor Parking Area (Phase 2)
TBD
Between $1,000,000 and
$5,000,000
GRTE 2022 Moose Wilson - MP 1.3 - 3.0 TBD Between $5,000,000 and
$10,000,000
YELL 2022
Northeast Entrance Road, Phase 1
More than $10,000,000
GRTE 2023 Moose Wilson MP 0.65 - 1.3 TBD Between $1,000,000 and
$5,000,000
YELL 2024
Northeast Entrance Road, Phase 2
More than $10,000,000
C-3
Park
Award Year
(FY)
Project Name
FHWA #
Construction Estimate (million)
GRTE 2024
Moose Wilson - Death Canyon
TH
TBD
Between $1,000,000 and
$5,000,000
GRTE 2024 Moose Wilson MP 0.0 - 0.65 TBD Between $5,000,000 and
$10,000,000
Unanticipated projects reserve (i.e. emergency repairs, allowance for price escalation, potential additional projects) $65.0
Total Estimated Value $350
C.2. SPECIFICATIONS
It is anticipated that the majority of work will generally incorporate the specifications and design standards of American Association State Highway Transportation Officials (AASHTO), and specifications based on the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14 and future versions Customary/Metric).
Websites - The following web sites contain information that may be used in the development of task orders. Other information not contained in the below websites also may be used in the development of task orders.
Standard Specifications (FP) - The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-14 and future versions) are issued primarily for constructing roads and bridges on Federal Highway projects under the direct administration of the Federal Highway Administration. View the FP online at:
http://flh.fhwa.dot.gov/resources/pse/specs/
Western Federal Lands Highway (WFLHD) Library of Supplemental Specifications (FP-14 and future versions) - Special Contract Requirements (SCRs) supplement the FP. A library of SCRs may be viewed at https://flh.fhwa.dot.gov/resources/specs/fp- 14/wfl/. These documents are periodically updated and do not include all the SCR’s that may be developed for a project.
Federal Lands Highway (FLH) Standard Drawings - FLH standard drawings include various design details that may be included in a project. Files are available in MicroStation® and Acrobat® formats http://flh.fhwa.dot.gov/resources/pse/standard/.
Construction Management Resources – At this link contractors can access various manuals, forms, tests and so on for use during contract administration. You can view these documents at: https://flh.fhwa.dot.gov/resources/construction/forms/wfl/.
C-4
C.3. WAGE RATES
Construction Wage Rate Requirements are applicable to construction task orders awarded under this contract.
C.4. ORDERING PROCEDURES FOR COMPETITIVE TASK ORDERS.
It is anticipated that most, if not all, of the Task Orders will be awarded based on competition between all MATOC contract holders.
Task Orders will not be publicly opened or released. Unsuccessful offerors' task proposal information will not be made available to the public, however, the information will be shared among other bidders (bid tabs will be shared with all MATOC holders after each Task Order bid opening.)
(1) Task Order Synopsis - When the Government requires work under the MATOC and time allows, a Task Order-Synopsis will be posted on FedBizOps (https://www.fbo.gov/). The synopsis will provide a brief description of the project and the anticipated solicitation issue date. In some instances, the synopsis may be issued via e-mail.
(2) Task Order Requests for Proposals (TO-RFP) - When the Government requires work under the MATOC, a TO-RFP will be issued. The TO-RFP will include information concerning the project such as, contract requirements, physical data, drawings, site visit details, evaluation criteria, and submission requirements (e.g. bid schedule, proposal requirements, etc).
(3) Task Order Pre-award Expenses - The Contractor will not be reimbursed for proposal preparation, attendance during negotiations, site visits, walk-through or other pre-award task order costs.
(4) Site Visits - Failure to visit the site cannot be used as an excuse for omission or miscalculation in offers. The Government may or may not schedule a joint site visit for individual task orders.
(5) Proposal Contents - Depending upon the requirements of each TO-RFP, the Contractor may be required to provide a price proposal only, or a technical proposal and a price proposal. Respond within the number of calendar days stated in the TO-RFP by submitting a proposal to the CO.
(6) Contract Prices - Bid Schedules - Payment for items listed in the Bid Schedule constitutes full compensation for furnishing all labor, equipment, services, and materials needed to complete construction. Include in the prices for the items listed in the Bid Schedule all costs for the specified work, whether or not specifically listed in the Bid Schedule.
(7) Bid Bonds. Submit bid bonds with the TO proposal as required in the TO-RFP.
C-5
(8) Proposal Deviations - Proposals that deviate from the TO requirements may be rejected or delay award.
(9) Declining a Task Order - With the exception of the TO-RFPs being issued with this solicitation to evaluate pricing, contractors are not required to submit a proposal for each TO-RFP. The Contractor must decline a project by written notice to the CO stating the reason and submit no later than 2 business days prior to the TO-RFP proposal due date.
MATOC Contractors who do not propose on at least 50% of available projects offered within a 24 month period may be determined at the Contracting Officer’s discretion to be ineligible for the MATOC minimum guarantee (see Section C.1).
(10) Fair Opportunity - All MATOC Contractors will be given fair opportunity to be considered for each order exceeding $3,500 issued under this MATOC except as provided below:
a. The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays;
b. Only one awardee is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized;
c. The order must be issued on a sole-source basis in the interest of economy and efficiency because it is a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order.
d. It is necessary to place an order to satisfy a minimum guarantee;
e. For orders exceeding the simplified acquisition threshold, a statute expressly authorizes or requires that the purchase be made from a specified source; or
f. The Contracting Officer sets aside the order for small businesses (see Section C.6).
In determining eligibility to compete, the CO considers such factors as performance on task orders under the MATOC contract, quality, timeliness, special expertise or other factors the CO determines are relevant to award of a particular task order. Failure to prosecute the work diligently on task orders may be cause for the CO to determine a contractor in-eligible to compete on a TO-RFP. Additional factors that may make a contractor ineligible include poor past performance, failure to propose on TO-RFPs or a Sole Source action is justified.
(11) Evaluation Method and Procedures - The basis of award for individual task orders may vary and will be described in the TO-RFP. Examples of a basis for award are:
1) Based on price only.
2) Based on both price and non-price factors, with the Task Order awarded to the
Contractor offering the best value to the Government. The Government reserves the right to accept other than the lowest priced offer. The TO-RFP will describe whether price is less important, more important, or equal in importance to non-price factors.
C-6
(12) Award Decision - Whenever possible, award will be made without discussions. Task orders will be FFP or FFP with an economic price adjustment. The Government reserves the right to reject all offers.
(13) Task Order Award
1) Award Notification - The task order becomes binding when the Contracting Officer signs the order. Notice of Task Order award will be via mail, email or facsimile. The Notice to Proceed (NTP) may be issued separately, normally after receipt of acceptable performance and payment bonds.
2) Insurance. Submit acceptable proof of insurance before beginning work.
3) Performance & Payment Bonds. Submit Performance and Payment Bond documents upon request. Ensure the IDIQ contract number AND the task order number are included on each Performance and Payment Bond document. Bond documents not containing the required information will be returned for correction.
4) Task Order contract documents. When electronic copies of the awarded task order are not feasible, the Contractor will be provided paper copies. All further reproduction shall be at the Contractor's expense.
C.5. EXCEPTIONS TO FAIR OPPORTUNITY (SOLE SOURCE) TASK ORDERS
(1) The CO reserves the right to award a sole source task order in the following instances:
(a) The agency need for the supplies or services is so urgent that providing a fair opportunity would result in unacceptable delays; OR
(b) Only one IDIQ Contractor is capable of providing the supplies or services required at the level of quality required because the supplies or services ordered are unique or highly specialized; OR
(c) The order must be issued on a sole-source basis in the interest of economy and efficiency as a logical follow-on to an order already issued under the contract, provided that all awardees were given a fair opportunity to be considered for the original order;
OR
(d) It is necessary to place an order to satisfy a minimum guarantee.
(2) Subcontractor costs under sole source task orders must show adequate competition.
Adequate competition may normally be assumed when there are at least three independent subcontractor/supplier quotes.
(3) Upon request, provide copies of subcontractor/supplier quotes with profit and overhead separately identified. The subcontractor/supplier quotes shall be in enough detail for the government to discern the scope of the services and materials included in the price.
(4) All prices must be fair and reasonable. If required, audits may be performed. The Government may conduct negotiations.
C.6. TASK ORDERS SET-ASIDE FOR SMALL BUSINESSES
The CO may, at their discretion, set aside a Task Order for small business concerns. Task Orders set aside for small business concerns will be competed among the small business MATOC contractors.
C-7
C.7. PERFORMANCE EVALUATIONS.
1. At the conclusion of each task order or when the Contractor’s performance is considered less than satisfactory, the Government will complete a Contractor’s performance evaluation. The evaluation will take into account all aspects of the Contractor’s performance. The Contractor will be provided a copy of the performance evaluation and an opportunity to discuss the evaluation.
2. This office posts performance evaluations in the Contractor Performance assessment Reporting System (CPARS) https://www.cpars.gov/. Upon receiving notice of evaluation availability, you will be given an opportunity to review the evaluation and submit comments. If you are unable to access the system, call 360.619.7520 for assistance or for a copy of the evaluation.
C.8. PROTESTS OF TASK ORDER AWARDS.
In accordance with FAR 16.505(a) (10), no protest under Subpart 33.1 is authorized in connection with the issuance or proposed issuance of an order under a task order contract except for a protest on the grounds that the order increases the scope, period, or maximum value of the contract or a protest of an order valued in excess of $10 million. Protests of orders in excess of $10 million may only be filed with the Government Accountability Office, in accordance with the procedures at FAR 33.104.
Ombudsman. If a Contractor believes they were not fairly considered for a particular task order, the Contractor may present the matter to the CO. The Contractor may appeal the explanation or decision of the Contracting Officer to the Ombudsman. The DOT Task and Delivery Order Ombudsman is the Associate Director, Office of Acquisition Policy, Oversight and Business Strategies (M-61) located in the Office of the Senior Procurement Executive (M-60). The Ombudsman will review the Contractor's complaint, and in coordination with the CO, ensure that the Contractor was afforded a fair opportunity to be considered for the task order.
C.9. GENERAL CONTRACT REQUIREMENTS.
1. Master Subcontracting Plan (applicable to Large Businesses). Implement and closely follow the approved “Master Subcontracting Plan.” The Contractor or the CO may request modifications to the Master Subcontracting Plan. Submit requests in writing. Changes will be incorporated by bilateral modification.
2. Task Order Subcontracting Plan (applicable to Large Businesses). Submit a Task Order Subcontracting plan as requested by the CO.
3. Additional MATOC awards. The Government reserves the right to issue additional solicitations and award additional contracts covering the same scope of work and with the same geographic constraints as this contract. In this event, new MATOC contractors, in accordance with the terms of their contracts, may compete for task orders with the Contractors selected under this solicitation.
C-8
C.10. MINIMUM STANDARDS FOR CRITICAL TASKS.
TO-RFPs may set minimum employee and firm qualifications for critical tasks. The Contractor may be required to provide personnel and firms that meet or exceed the minimum qualification standards established in the TO-RFP.
D - 1
SECTION D - Packaging and Marking Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contracts (MATOC)
SECTION D – PACKAGING AND MARKING
D - 2
SECTION D - Packaging and Marking
E-1
SECTION E – Inspection & Acceptance Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contracts (MATOC)
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 -- Inspection of Construction (Aug. 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not --
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary.
The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may --
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction.
However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
E-2
SECTION E – Inspection & Acceptance Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contracts (MATOC)
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of Clause)
F-1
SECTION F – Deliveries or Performance
SECTION F – DELIVERIES OR PERFORMANCE
F.1. CLAUSES
52.252-2 -- Clauses Incorporated by Reference (Feb 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
https://www.acquisition.gov/far
FAR Number Title Date 52.211-13 52.211-13 Time Extensions
**NOTE** (Applicable to projects with interim or multiple completion dates)
Sep 2000
52.211-18 Variation of Estimated Quantity Apr 1984 52.242-14 Suspension of Work Apr 1984
F.2 PERIOD OF SERVICE
This contract will be in effect for 60 months from the date of award. No work can be ordered after the 60 months have expired. All Task Orders will have their own completion date, which may extend beyond the end of the 60 month period.
F-2
SECTION F – Deliveries or Performance
G-1
SECTION G – Contract Administration Data
SECTION G – CONTRACT ADMINISTRATION DATA
G.1 ACCOUNTING & APPROPRIATION DATA
This data will be included in individual Task Order Award documents.
G.2 GOVERNMENT-FURNISHED PROPERTY
When applicable, the Task Order Special Contract Requirements (SCRs) will include property information. Use and maintain the property in accordance with the applicable property clauses.
See Task Order clauses (Clauses begin on page C-1 of each Task Order) and Task Order specifications.
G.3 CONTRACTING OFFICERS
The Contracting Officer(s) responsible for the MATOC contracts and soliciting/awarding Task Orders may be contacted at:
Western Federal Lands Highway Division 610 East Fifth Street Vancouver WA 98661-3801 Email: WFL.Contracts@dot.gov Fax: (360) 619-7932 Phone: (360) 619-7520
G-2
SECTION G – Contract Administration Data
H-1
SECTION H – Special Contract Requirements
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1 SHOP DRAWINGS, SUBMITTALS, & AS-BUILTS
Prepare all shop drawings, submittals, and as-builts for each Task Order in accordance with requirements contained therein and in FAR clause 52.236-21 Specifications and Drawings for Construction.
H.2. USE OF RECOVERED MATERIALS ON FEDERAL LANDS HIGHWAY
PROJECTS
Section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act (RCRA) of 1976, as amended (42 U.S.C. 6901 et seq.), requires Federal, State, and local procuring agencies using appropriated Federal funds to purchase items composed of the highest percentage of recovered materials practical. Use of recovered materials is strongly encouraged on Federal Lands Highway Projects. Highway construction items covered by the Environmental Protection Agency's Comprehensive Guidelines for Procurement of Products Containing Recovered Materials include fly ash, ground granulated blast furnace slag, traffic barricades, traffic cones, hydraulic mulch and compost for mulch.
Use of fly ash and ground granulated blast furnace slag and construction materials containing fly ash and ground granulated blast furnace slag on Federal Lands Highway Projects:
It is the policy of the United States Government that fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag shall have maximum practicable opportunity for incorporation into its construction projects.
The Contractor agrees to investigate the use of fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag to the fullest extent consistent with the efficient performance of this contract. Both the contractor and the subcontractors are urged to seek out suppliers of fly ash and ground granulated blast furnace slag, cement and concrete containing fly ash and ground granulated blast furnace slag and to solicit bids for these materials.
Names of firms that supply fly ash and ground granulated blast furnace slag and materials containing fly ash and ground granulated blast furnace slag are available from the American Coal Ash Association and the National Slag Association.
H-2
SECTION H – Special Contract Requirements
PARTNERING**NOTE**(Included with TO-RFP when applicable)
A Partnership recognizes the Government and the Contractor are both responsible for and can affect the successful completion of this project. Partnering is a vehicle to ensure the partnership has structure and quality. It recognizes the strengths of each party and uses those strengths to identify and achieve shared goals. One of the primary objectives of Partnering is to facilitate the resolution of disputes in a timely, professional, and non-adversarial manner with the outcome focused on achieving those shared goals.
WFLHD supports the concepts and tenets of Partnering and as such is encouraging the Contractor and its Subcontractors to establish a Partnering relationship on this project.
Partnering can be formal or informal.
A formal Partnering meeting can help facilitate this relationship by helping to document the parties’ common purpose and goals, and ensuring alignment. The goals are mutually agreed to and address effective and efficient performance within the scope of the contract.
Participation in a formal Partnering meeting is voluntary. Costs of implementing and maintaining the partnership would be agreed to by both parties and shared equally. These costs would be in addition to the contract amount.
An informal Partnering meeting can help facilitate this relationship by improving communication and encouraging cooperation. The substance of an informal Partnering meeting would be determined by mutual agreement prior to or at the preconstruction conference.
Participation in an informal Partnering meeting is voluntary. Costs of implementing and maintaining the partnership would be the responsibility of the party incurring the cost.
I-1
Section I – Federal Acquisition Regulation Contract Clauses
PART II – CONTRACT CLAUSES
SECTION I – FEDERAL ACQUISITION REGULATION CONTRACT CLAUSES
NOTE: Each Task Order will contain the most up to date versions and required clauses as applicable.
52.252-2 Clauses Incorporated by Reference (Feb 1998).
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
https://www.acquisition.gov/far https://www.transportation.gov/administrations/assistant-secretary-administration/transportation-acquisition-regulation-tar
FAR NUMBER TITLE DATE
52.202‐1 Definitions Nov 2013 52.203‐3 Gratuities Apr 1984 52.203‐5 Covenant Against Contingent Fees May 2014 52.203‐6 Restrictions on Subcontractor Sales to the
Government Sep 2006
52.203‐7 Anti‐Kickback Procedures May 2014 52.203‐8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .