This document outlines a master subcontracting plan template for a multiple award task order contract to provide highway, bridge, and road construction services in Yellowstone National Park, Grand Teton National Park, and surrounding areas in Wyoming. Up to eight contractors may be awarded IDIQ contracts valued between $25,000 minimum and $350 million maximum over five years. Projects will range from $2 million to $40 million and be awarded competitively on a lowest price technically acceptable basis. Small businesses will receive two set-aside awards. Contractors must appoint a subcontracting administrator and make good faith efforts to utilize small, women-owned, veteran-owned, HUBZone, and disadvantaged small businesses. Quarterly subcontracting reports will track these efforts.

Master Subcontracting Plan

View the file

Other files

File Type Posted
Amendment_A001.pdf PDF
RFP_Yellowstone.pdf PDF
Technical_Information_Form_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MASTER SUBCONTRACTING PLAN

Yellowstone, Grand Teton, & Surrounding Area Multiple Award Task Order Contract (MATOC)

MASTER SUBCONTRACTING PLAN for solicitation number 69056718R000003

INTRODUCTION

“Master subcontracting plan” means a subcontracting plan that contains all the required elements of an individual subcontracting plan, except goals, and may be incorporated into individual subcontracting plans, provided the master subcontracting plan has been approved.

Purpose: The purpose of the Master Subcontracting Plan is to identify the approach the prime contractor will follow to ensure subcontracting requirements are solicited and selected in a manner that facilitates maximum competition and quality workmanship. The competition is not only for allowing maximum participation of small businesses and local businesses, but also ensures subcontract work is competitively priced to support the Government receiving fair and reasonable prices. The Master Subcontracting Plan must be completed by all large business offerors. This plan must be submitted prior to award of the contract and may require discussion prior to acceptance by the government. This plan will be incorporated into the contract after award.

For each Task Order the contractor shall submit a subcontracting plan specific to the Task Order.

Consider the following FHWA small business goals in development of Task Order Subcontracting plans and efforts:

FHWA Small Business Goals (As of FY 2018) Business Size Goal

SB 41.4%

SDB 5%

HUBzone 3%

WOSB 5%

SDVOSB 3%

INSTRUCTIONS:

Where subcontracting opportunities will not exist for the solicitation, the bidder/offeror shall submit a response outlining the rationale for making this determination with its proposal/bid. The statement shall be signed by an official authorized to make decisions on behalf of the firm.

Text lines may be added to this format as needed.

1. The following individual will administer the subcontracting program:

Name: _______________________________________________ Title: ________________________________________________ Address: _____________________________________________ Telephone & e-mail:_____________________________________

This individual's specific duties, as they relate to the subcontracting program, are as follows:

2. The following efforts will be taken to ensure that SB, SDVOSB, HUBZone, SDB, and

WOSB subcontractors will have an equitable opportunity to compete for subcontracts:

It is agreed that FAR Clause 52.219-8, Utilization of Small Business Concerns, will be included in all subcontracts, which offer further subcontracting opportunities. It is further agreed that all subcontractors (except small business concerns) at all tiers below the prime contractor who receive subcontracts in excess of $700,000 ($1.5M for construction of any public facility with further subcontracting possibilities) will be required to adopt and comply with a subcontracting plan in accordance with FAR Clause 52.219-9.

3. The following types of records will be maintained concerning procedures that have been adopted to comply with the requirements and goals in the plan (i.e., establishment of source lists, guides and other data that identify SB, SDVOSB, HUBZone, SDB and WOSB concerns; a description of the offeror’s efforts to locate SB, SDVOSB, HUBZone, SDB and WOSB concerns and to award subcontracts to them, etc.) and shall be maintained through completion of the contract:

4. In accordance with FAR Subpart 19.704(a)(10) through (15), the Contractor further agrees to:

a. Cooperate in any studies or surveys as may be required;

b. Submit periodic reports as may be required so that the Government can determine the extent of compliance by the Contractor with the subcontracting plan;

c. After November 30, 2017, include subcontracting data for each order when reporting subcontracting achievements for indefinite-delivery, indefinite-quantity contracts intended for use by multiple agencies;

d. Submit the Individual Subcontract Report (ISR), and the Summary Subcontract Report

(SSR) using the Electronic Subcontracting Reporting System (eSRS) at http://www.esrs.gov/ within the timeframes identified at FAR Subpart 19.704(a)(10)(iv);

e. Ensure that other than small business subcontractors with subcontracting plans agree to submit eSRS documents online as required;

f. Provide its prime contract number and its unique entity identifier, and the e-mail address of the offeror’s official responsible for acknowledging receipt of or rejecting the ISRs to all first-tier subcontractors with subcontracting plans so they can enter this information into the eSRS when submitting their ISRs;

g. Require that each subcontractor with a subcontracting plan provide the prime contract number, its own unique entity identifier, and the e-mail address of the subcontractor’s official responsible for acknowledging receipt of or rejecting the ISRs, to its subcontractors with subcontracting plans;

h. Make a good faith effort to acquire articles, equipment, supplies, services, or materials, or obtain the performance of construction work from the small business concerns that the offeror used in preparing the bid or proposal, in the same or greater scope, amount, and quality used in preparing and submitting the bid or proposal;

i. Provide the contracting officer with a written explanation if the contractor fails to acquire articles, equipment, supplies, services or materials or obtain the performance of construction work as described in FAR 19.704(a)(12) of this section. This written explanation will be submitted to the contracting officer within 30 days of contract completion;

j. Will not prohibit a subcontractor from discussing with the contracting officer any material matter pertaining to payment to or utilization of a subcontractor; and

k. Pay its small business subcontractors on time and in accordance with the terms and conditions of the subcontract, and notify the contracting officer if the offeror pays a reduced or an untimely payment to a small business subcontractor (see FAR 52.242-5).

Submitted by:

Signed Title

Printed Name Email Address