This document package includes preliminary plans and specifications for a federal construction project to repair bridges and perform related work on the Denali Park Road in Alaska. The project involves minor repairs to three bridges, painting bridge rails, installing riprap to stabilize streams, and other minor work items. The project is located approximately 145 miles southwest of Fairbanks, Alaska within the Denali Borough. The solicitation will be set aside for small businesses. Interested vendors must register on FBO.gov to view the vendor list and receive notifications. The estimated price range for the work is between $1 million and $2 million, with an anticipated completion date of summer 2019. The federal agencies involved are the National Park Service and the Federal Highway Administration.

Preliminary Plans

View the file

Other files

File Type Posted
Prelim_Letter_DENA1048.pdf PDF
AK_DENA10(48).pdf PDF
PROJECT_DESCRIPTION.pdf PDF
DENA1047_Preliminary-Plans-Letter.pdf PDF
PROJECT_DESCRIPTION_DENA_10(47).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

INDEX TO SHEETS

PROJECT MANAGER

NATIONAL

PARK

SERVICE

Department of the Interior

9 10

KENAI

FJORDS

N.P.

LAKE CLARK

NAT'L PARK

WRANGELL-

ST. ELIAS

NAT'L PARK

DENALI

NATIONAL

PARK

ALASKA KEY MAP

SOUTH CENTRAL

C A

N A

D A

U N I T

E D

S T

A T

E S

Junction

Delta

FAIRBANKS

Tok

Glennallen

Valdez

Cordova

Whittier

ANCHORAGE

Palmer

Kenai

Homer

Seward

Hot Springs

Manley Hot Springs

Circle

N

B. CHON

STANDARD DRAWINGS

STONY CREEK BRIDGE REPAIR DETAILS

SECTION

TOKLAT RIVER BRIDGE 1 SCOUR MITIGATION

TOKLAT RIVER BRIDGE 1 SCOUR MITIGATION PLAN

SANCTUARY RIVER BRIDGE REPAIR DETAILS

SUMMARY OF QUANTITIES

VICINITY MAP

PLAN SYMBOLS AND ABBREVIATIONS

TITLE SHEET

9-14

8.

7.

6.

5.

4.

3.

2.

1.

STATE PROJECT

NUMBER

SHEET

U

S S u r ft c m y fi le s p w p r o d u c ti o n d d e n a a a .d g n

AK NPS DENA 10(47)

A

M

A u g u s t

C h e c k e d b y

D e s ig n e d b y

Project Location

FEDERAL HIGHWAY ADMINISTRATION

U.S. DEPARTMENT OF TRANSPORTATION

TYPE OF CONSTRUCTION:

DESIGN DESIGNATION:

SPECIFICATION:

PLANS FOR PROPOSED PROJECT

VANCOUVER, WASHINGTON

WESTERN FEDERAL LANDS HIGHWAY DIVISION

PLANS PREPARED BY

on Federal Highway Projects, FP-14

Construction of Roads and Bridges

Standard Specifications for

NPS PMIS NO. 164258A

AK NPS DENA 10(47)

DENALI NATIONAL PARK AND PRESERVE

NATIONAL PARK SERVICE

U. S. DEPARTMENT OF THE INTERIOR

DENALI PARK ROAD BRIDGES

REPAIR THREE

ALASKA

DENALI BOROUGH

SCALE IN MILES

2 4 6 82

W I L D E R N E S S

P A R K

N A T I O N A L

D E N A L I

Mountain

Divide

S a n c tu a ry

R iv e r

T e k la n ik a

R iv e r

T o k la t

River

E a s t

F o rk

T o k la t

River

D en al i

Pa rk

Roa d

Campground

River

Sanctuary

Overlook

Stony Hill

Lake

Bergh

APPROVED:

DATE

DATE

DATE

National Park Service

Regional Director, Alaska Region, Western Federal Lands Highway Division

Chief of Engineering, MP 22.9

MP 53.3

MP 60.7

Wright

Mt

Primrose Ridge

Not Applicable

35 MPH

<100

<100 e (max)

V

ADT (2039)

ADT (2019)

and stream stabilization

Minor bridge repair, bridge rail painting, LENGTH: SITE WORK - 3 SITES

AND PRESERVE

DENALI NATIONAL PARK

(Denali National Park and Preserve)

Superintendent, NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

PRELIM

IN

ARY

N

VICINITY MAP

FOOTNOTE:

Exact location to be determined by CO.[1]

STATE PROJECT

NUMBER

SHEET

U

S S u r ft m y fi le s p w p r o d u c ti o n d d e n a a c .d g n

AK NPS DENA 10(47)

A u g u s t

C h e c k e d b y

D e s ig n e d b y

Sanctuary River Bridge

MP 22.9

River Bridge 1

Toklat

MP 53.3

Stony Creek Bridge

MP 60.7

Long 149°28'41.01"W

Lat 63°43'11.94"N

Long 150°1'50.99"W

Lat 63°31'7.12N

Long 150°14'23.07"W

Lat 63°27'10.89"N egdiR esor mir

P

W I L D E R N E S S

P A R K

N A T I O N A L

D E N A L I

Mountain

Divide

S a n c tu a ry

R iv e r

T e k la n ik a

R iv e r

T o k la t

River

E a s t

F o rk

T o k la t

River

D en al i

Pa rk

Ro ad

Campground

River

Sanctuary

Overlook

Stony Hill

Lake

Bergh

Mt Wright

SCALE IN MILES

2 4 6 82

(MP 30.320)

Teklanika Gate

(MP 27.2)

Teklanika Pit

Cabin

Ranger

Sable Mountain

[1]Water Source

Pass

Highway

Pass

Thorofare

Visitors Center

Eielson

Mt Galen

Mt Sheldon

Pendleton

Mount

W I L D E R N E S S

D E N A L I

Parks Hwy.

To George 23 miles

Sanctuary River Bridge

MP 22.9

Toklat River Bridge 1

MP 53.3

AND PRESERVE

DENALI NATIONAL PARK

Truck Turnaround

(MP 53.476)

Truck Turn Around

Toklat Compound and

Truck Turnaround

Truck Turn Around

Stony Creek Bridge

MP 60.7

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

PRELIM

c--~-

64'-8½"

Clean and paint steel railings

65'-2" 64'-8½"

C : - === : -J;:i-----......----.-=-·...-·-=-.·.-·-= ... ·---=....-· -,-...., ___ - ... - =-_,· ... - = .... ----=.-·--........ ----......... --..,-....., ___ ......,=---... -= .... ----= ... ---........ ----......... --.... -,,.,_ - -~ -: ) Clean and reseal

12'-0"

, , (Typ.)

PLAN

194'-7"

ELEVATION

Along centerline lT·_-_l______ ------------ 1 -_____________ T _____ --,-- -- 7"

I j I J_ J_

1'-9" 8'-0" 4'-0" 4'-0"

Remove existing ~ _0 _ jo;n; ,~,: fil/e, ~ j' ~ ~ .

L~ -1-~ I:~ .. :J Existing =-17[ I I J reinforcement "----'-------c;T ,;:-__c__J (To remain) 11 Ir

11 11

11 11

11 11 c--_J L~

EXISTING

NO. DATE BY REVISIONS

Remove and recast joint headers with elastomeric concrete

SECTION A-A

NO. DATE BY

TYPICAL SECTION

1'-0"

L"----'-----~ c--_J

1"

PROPOSED

REVISIONS

pier joints

12'-0"

B'-0"

L2x2x¾ with 2¾"x¾" /ZJ stud anchor@ 1 '-0"

Precompressed silicone

Epoxy adhesive both sides

DESIGNED BY

AF

·1-2~

___ TJ

_L 1'-9"

Item#

55222-0000

56301-2000

Field applied silicone corner beads and silicone band

Impregnated foam

DRAWN BY CHECKED BY SCALE

AF No scale

STATE PROJECT

AK NPS DENA 10(47)

GENERAL NOTES:

SPECIFICATIONS:

Construction:

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14.

Estimate of Quantities

Description Unit Quantity

Repair Concrete (Sanctuary River Bridge Joints) LPSM 1

Painting, Steel Structure (Sanctuary River Bridge Rails) LPSM 1

Scope of work:

1. Clean and repaint steel railings (392 LNFT).

2. Clean and reseal pier joints. Remove and recast joint headers with elastomeric concrete (65 LNFT).

Structure Number 9830-00lP

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

WESTERN FEDERAL LANDS HIGHWAY DIVISION

DENALI NATIONAL PARK AND PRESERVE

SANCTUARY RIVER BRIDGE

REPAIR DETAILS

SHEET

NO.

PROJECT TEAM LEADER BRIDGE DRAWING DATE DRAWING NO.

B. OLTMANN JUNE 2018

k "O

QJ

-"' u

QJ

.r:: u

.D

"O

QJ

C:

Cl "iii

QJ

B~

B~

A l Existing / bridge abutment _____,/

Removal of structures and obstructions (gabion baskets/revetment mattress)

Temporary diversion channel

A

J

STATE

AK

PROJECT

NPS DENA 10(47)

NPS PMIS No. 164258A

NPS Drwg. No. XXX/XXXXXX

Existing bridge structure ~

SCALE IN FEET

15 6 1~ 30

TOKLAT RIVER BRIDGE 1

SCOUR MITIGATION

PLAN

SHEET

NUMBER

PRELIM

NO SCALE SECTIONS

SCOUR MITIGATION

TOKLAT RIVER BRIDGE 1

STATE PROJECT

NUMBER

SHEET

U

S S u r ft m y fi le s p w p r o d u c ti o n d d e n a a g .d g n

AK NPS DENA 10(47)

A u g u s t

C h e c k e d b y

D e s ig n e d b y

DESCRIPTIONITEM NO. UNIT QUANTITY

RIPRAP QUANTITIES

64704-1000

25101-0500

20701-0300

20304-1000

20304-1000

15702-1000

CY

CY

SQYD

LPSM

LPSM

LPSM

[1]

[2]

[3]

STREAMBED MATERIAL (CONSERVED)

PLACED RIPRAP, METHOD A, CLASS 5

SEPARATION-STABILIZATION GEOTEXTILE, CLASS 1, TYPE C

REMOVAL OF STRUCTURES AND OBSTUCTIONS (STEEL SHEET PILE WALL)

REMOVAL OF STRUCTURES AND OBSTUCTIONS (GABION BASKETS/REVETMENT MATTRESS)

SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL

SECTION A - A

SECTION B - B

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

8'-0"

Existing roadway edge 10'-0"

8'-0" 24'-0" embankment

Regrade road

Proposed grade

8'-0"

8'-0"

Bridge abutment

Bridge structure

24'-0"

Proposed grade

Bridge low chord

20'-0" diversion channel

Temporary diversion channel

Temporary bottom stream

Existing geotextile, class 1, type C

Separation-stabilization geotextile, class 1, type C

Separation-stabilization revetment mattress) obstructions (gabion baskets/

Removal of structures and

(min.)

4'-0" m in m in

(min.)

4'-0"

Streambed material (conserved)

Existing gradeStreambed material (conserved)

Set revetment crest 2' below bridge low chord

Existing stream bottom method A, class 5

Placed riprap, method A, class 5

Placed riprap, material backfill

Conserved

FOOTNOTE:

136 LNFT[3]

XX LNFT[2]

710 LNFT[1]

obstructions (steel sheet pile wall)

Removal of structures and

ESTIMATED QUANTITIES

PRELIM

34'-8½" 35'-2" 34'-8½"

I I I I f = = i ~" , " " , " k " , 0 " : ~: , " "~ " : ~ r = = :::: ) . : : I : : I : : •

Repair erosion with : I I • [ I · [ [ I[:

Class 1 riprap [ . : I : : I : • • I

- - - - - 17T - - - - - 171 - - - - - i 1i- - [ Extend scuppers~ · I · I · , I• [ . (8 locations) · · · · · • • ,

· I I 111 111 11 C::::. -== • • = J r=-"=-u ~ _-uc-~~ ~ ~~ =--; ~ ~ ~~ ~ =~ ~ ~~ ~ ---=.;_ ~~ ::.;-~. ~ l • = = -. :: )

I I

PLAN

104'-7"

~~~I I - . -r ~ . : :_ - :_:_ ": ~ ~~ ~~-~ ~. ~ -=--~ ~ ~=:.__~ C == ~ ~-~ ~ -=-~~~- -=-~I . ~- ::b~i::. .. 7 ~ \ l I j ~ Clean and paint l I j . . . . . / ~ - - . - / - - - .

"--- \ I I steel superstructure I I

.. '. / .. '. I 11 11 / ..

' ' . ' '. I /

LJ LJ

~---1

ELEVATION

2'-3" 12'-0" 12'-0" 2'-3"

I I

~l

1'-9" I

TYPICAL SECTION

~ -½6" Bent plate

DETAIL A SECTION B-B

NO. DATE BY REVISIONS NO. DATE BY REVISIONS DESIGNED BY DRAWN BY CHECKED BY

AF AF

STATE PROJECT

AK NPS DENA 10(47)

GENERAL NOTES:

SPECIFICATIONS:

Construction:

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14.

Estimate of Quantities

Item# Description Unit Quantity

56301-2000 Painting, Steel Structure (Stony Creek Bridge) LPSM 1

57501-0000 Minor Bridge Work (Stony Creek Bridge) LPSM 1

Scope of work:

1. Clean and repaint steel superstructure.

2. Add extensions to all scuppers (8 locations).

SHEET

NO.

3. Repair erosion at end of southeast wingwa/1 (6 CUYD ).

SCALE PROJECT TEAM LEADER

B. OLTMANN

Structure Number 9830-0lSP

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

WESTERN FEDERAL LANDS HIGHWAY DIVISION

DENALI NATIONAL PARK AND PRESERVE

STONY CREEK BRIDGE

REPAIR DETAILS

BRIDGE DRAWING DATE DRAWING NO.

JUNE 2018

NO SCALE

157-5

STANDARD APPROVED FOR USE 6/2005

DRAFT: 3/2014

REVISED: 6/2007

DIVERSION CHANNELS

TEMPORARY

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a i.

p d f.

d g n

P

J u ly

FEDERAL LANDS HIGHWAY

U.S. CUSTOMARY STANDARD

STANDARD

PLASTIC LINED DIVERSION CHANNEL

RIPRAP LINED DIVERSION CHANNEL

TEMPORARY CULVERT

DIVERSION CHANNEL

SECTION B-B

SECTION A-A

SECTION A-A SECTION B-B

SECTION B-B

PLAN

W

B

W

B

W

B B

W

T T

Ø when scheduled)

Silt fence (typ.

Roadway embankment

Roadway embankment

Temporary culvert backfill

Subgrade

Bedding

Sandbags

Riprap lining Riprap lining backflow into natural channel

Use sandbags to prevent

Permanent natural channel

Earthwork limits when scheduled)

Silt fence (typ.

See Note 5

Permanent culvert

Roadway centerline temporary barrier

Use sandbags to construct

SandbagsPlastic liner

SSSS

SS SS

D

D D

D

SS

SS

SS SS

1.

2.

3.

4.

5.

FlowFlow

FlowFlow

Plastic liner when scheduled)

Silt fence (typ.

When specified replace the portion of the diversion channel through the roadway embankment with temporary culvert. Compact temporary culvert backfill using one of the methods listed in Subsection 204.11(a).

See Erosion Control Section for temporary culvert diameter, riprap class, channel dimensions and quantities.

Use plastic liner or riprap along the entire length and width of the temporary diversion channel.

Construct channel at a minimum grade of 0.5 percent.

Do not construct with longitudinal joints if using a plastic liner. Bury the upstream edge of the liner a minimum of

A

A

BB

GeotextileGeotextile

Flow

Natural ground and secure with sandbags (typ.)

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

6" deep and secure with riprap or sandbags.

2'2'

Bury plastic liner 6" deep

2'2'

NOTE:

with plastic liner or riprap

Temporary diversion channel

PRELIM

Spacing Slope

STAKES REQUIRED

1:1

1:2

1:3

1:4 or flatter for each roll

Stakes required

FIBER ROLL SPACING

Fiber roll length

DRAFT: 7/2016

REVISED:

DETAIL APPROVED FOR USE 10/2014

WESTERN FEDERAL LANDS HIGHWAY DIVISION

FIBER ROLL

(FT)

(FT)

W157-21

U.S. CUSTOMARY DETAIL

DETAIL

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a j.

p d f.

d g n

J u ly

Fl ow

T o e o f fi ll s lo p e

ELEVATION

PLAN

disturbed areas

Runoff from

INSTALLATION BEYOND TOE OF SLOPE

INSTALLATION ALONG SLOPES

FIBER ROLL STAKING DETAIL

PROPERLY STAKED AND ENTRENCHED FIBER ROLL

Existing ground (typ.)

Fiber roll

Flow direction

Slope

Direction of runof f from distur bed area s sp ac in g ch ar t

S ee F ib er R ol l

Fiber roll ff o n ur f o n oi t c er i

D along contours

Install fiber rolls

Fiber roll

Slope

Fi ll slo pe

Direction of runoff ground

Existing soil to match ground level

Backfilled and compacted

Flow larger than fiber roll wood stakes. See Note 2.

Pay lim its

Pay lim its

SLOPE PROTECTION INSTALLATION

ALTERNATE FIBER ROLL JOINT DETAIL

FIBER ROLL LAPPING DETAIL

on uphill side of fiber roll

Place excavated material Stagger joints (typ.)

2.

1.

permanent installations. Do not crush fiber roll while staking.

roll is secure to slope. Live stakes may be used for and install fiber rolls

Step 1: Excavate trench Step 2: Backfill soil against fiber rolls

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

2" (min.) Excavate trench 2"

1" x 1" or 1" Ø ove rlap

12" (m in.)

t o m in m in

1" x 1" Wood stake as specified in plans

3' min. or

3' (min.)

Drive stakes at each end and at 4-foot spacing until fiber fiber roll and space stakes at 4-foot max.

6-inches from fiber roll end angles towards the adjacent

Overlap fiber rolls 12-inch minimum. Drive stakes at

NOTE:

PRELIM

SIGN SPACING TABLE

ROAD TYPE

DISTANCE BETWEEN

A B C

ROAD WORK

END

WORK

ROAD

AHEAD

ROAD WORK

END

ROAD WORK

END

ROAD WORK

END

WORK

ROAD

AHEAD

WORK

ROAD

AHEAD

Expressway / Freeway

ROAD NAME

ROAD NAME

ROAD WORK

NEXT xx MILES

WORK

ROAD

xxxxxxx

WORK

ROAD

xxxxx

WORK

ROAD

xxxxxxx

WORK

ROAD

xxxxxxx

ROAD WORK

NEXT xx MILES

W13-1P

(optional)

W13-1P

(optional) xx

MPH

xx

MPH

STANDARD APPROVED FOR USE 6/2005

DRAFT: 6/2014

REVISED:

Rural greater than 50 MPH

Urban and Rural 35 MPH to 50 MPH

Urban and Rural 30 MPH and less

SIGNS IN FEET

635-1

ADVANCE SIGNING

TEMPORARY TRAFFIC CONTROL

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a k .p d f.

d g n

J u ly

FEDERAL LANDS HIGHWAY

U.S. CUSTOMARY STANDARD

STANDARD

G20-2

G20-2

G20-2

G20-1

See Note 11

G20-1

See Note 11

M in o r R o a d

M a jo r R o a d

W20-1

See Note 10

W20-1

See Note 10

W20-1 over

W16-8P

See Note 9

W20-1 over

W16-8P

See Note 9

W20-1

Ro ad N am e

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

W20-1

See Note 10

W20-1

See Note 10

G20-2

Erect all project advance warning signs before starting construction work.

Not all details shown on the temporary traffic control sheets may be applicable to this project. The Contractor may add or delete information and details in this traffic control plan as necessary to accommodate actual operations.

Where advance warning signs, placed as shown, interfere with permanent signs, locate the warning signs as determined by the CO for best results. Vary messages as required.

Additional or different message signs may be required to fit the actual construction conditions.

Install advisory speed plates under the W20 series warning signs as needed to indicate a maximum recommended speed through the construction area.

Ensure all sign supports exposed to impact by traffic meet the requirements of

NCHRP-350 or MASH for crashworthiness.

Maintain two-way traffic during all non-work hours except as approved by the CO.

Do not store traffic control devices along the roadway when not in use. Cover post-mounted signs when not applicable.

If W20-1 is placed on a roadway other than that on which the actual construction work occurs, include a supplementary plaque indicating the name of the road on which the construction does occur (applies to major roads only).

The message on the W20-1 signs may be "ROAD WORK AHEAD" or may specify the distance to the work area in feet or in miles. Install an additional W20-1 each end of the project. Show the distance on the G20-1 sign to the nearest whole mile.

If signing on a roadway under a jurisdiction other than the client agency, verify that an encroachment permit has been obtained.

State standards may be used as an alternative if approved by the CO.

Refer to the Section 635 of the Special Contract Requirements for allowable retroreflective sheeting types.

A

B

C

(S ee S ig n

Sp ac in g

Ta bl e)

ADVANCE

W

ARNI

NG

AREA

C

B as d et er m in ed b y th e

CO

W or k zo ne A re a of In flu en ce

Pr oj ec t L im its

A

A

(S ee S ig n

Sp ac in g

Ta bl e)

ADVANCE

W

ARNI

NG

AREA

A

A

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

For work zones that are 2 miles or more in length, install G20-1 signs at signs "B" feet apart according to the Sign Spacing Table.

sign when approach speeds exceed 50 MPH. When used place the two W20-1

NOTE:

PRELIM

LENGTH AND SPACING TABLE

SPEED*

APPROACH

AREA

TAPER

SPACE

BUFFER

SPACE

WORK

CHANNELIZING DEVICE

not the advisory speed.

Approach speed based on the regulatory posted speed, *

SIGN SPACING TABLE

ROAD TYPE

DISTANCE BETWEEN

A B C

LENGTH

BUFFER SPACE

Expressway / Freeway

WORK

ROAD

AHEAD

ONE LANE

ROAD

AHEAD

xx

MPH

xxx

FEET

ROAD WORK

END

635-6

STANDARD APPROVED FOR USE 6/2005

DRAFT: 8/2013

REVISED:

MPH FEET

Rural greater than 50 MPH

Urban and Rural 35 MPH to 50 MPH

Urban and Rural 30 MPH and less

SIGNS IN FEET

(WITH FLAGGERS)

SINGLE LANE CLOSURE LAYOUT

TEMPORARY TRAFFIC CONTROL

SPACING IN FEET

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a l.

p d f.

d g n

J u ly

FEDERAL LANDS HIGHWAY

U.S. CUSTOMARY STANDARD

STANDARD

Traffic flow

Traffic flow

See Note 4

W20-1 W20-7W20-4

See Note 4

G20-2

Spacing Table)

(See Length and

(optional)

WORK SPACE (optional)(optional)

(optional)

W13-1P

(optional)

W16-2P

7.

6.

5.

4.

3.

2.

1.

the buffer space.

Do not allow equipment, materials, or vehicles to be parked or stored in

Requirements, Section 156.

For project specific minimum width, refer to the Special Contract

For night time flagging operation, provide floodlighting at flagger stations.

WORK AHEAD" (W20-1) and "END ROAD WORK" (G20-2) signs.

If closure is completely within the project limits, eliminate the "ROAD name of the contractor on the pilot car.

a conspicuous location on the rear of vehicle. Prominently display the

For pilot car operation, mount the PILOT CAR FOLLOW ME (G20-4) sign at conditions as approved by the CO.

Final location and spacing of signs and devices may be changed to fit field those depicted for the opposite direction of travel.

Signs are shown for one direction of travel only. Place devices similar to

NOTE:

ATAPER AREABUFFER SPACEVARIABLEBUFFER SPACETAPER AREAABC

(See Length and Spacing Table)ADVANCE WARNING AREA (See Sign Spacing Table) TERMINATION AREA

Device spacing

BUFFER SPACE

Channelizing devices

Flagger location

Flagger location

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

50' - 100' 50' - 100' (optional)

See Note 6

10' min.

PRELIM

limit or 85 percentile speed prior

Shoulder taper formula:

Where:

L =

L =

Minimum length of taper

* Approach speed based on the regulatory posted speed, not the advisory speed.

**Lengthen taper as needed to provide minimum of three channelizing devices in taper at required spacing.

L =

W =

S =

LENGTH AND SPACING TABLE

APPROACH

SPEED* TAPER

AREA

BUFFER

SPACE

WORK

SPACE

CHANNELIZING DEVICE

WS

WS²

SIGN SPACING TABLE

ROAD TYPE

DISTANCE BETWEEN

A B C

ROAD WORK

END

ROAD WORK

END

WORK

ROAD

AHEAD

WORK

ROAD

AHEAD

MINIMUM TAPER LENGTH**

BUFFER SPACE

LENGTH

Expressway / Freeway

SHOULDER

WORK

xx

MPH

635-10

STANDARD APPROVED FOR USE 6/2005

DRAFT: 8/2013

REVISED:

MPH

FEET

for S ≤ 40 MPH for S ≥ 45 MPH

Width of offset in feet

Numerical value of posted speed to work in miles per hour

FEET

SPACING IN FEET

Rural greater than 50 MPH

Urban and Rural 35 MPH to 50 MPH

Urban and Rural 30 MPH and less

SIGNS IN FEET

SHOULDER CLOSURE LAYOUT

TEMPORARY TRAFFIC CONTROL

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a m .p d f.

d g n

J u ly

FEDERAL LANDS HIGHWAY

U.S. CUSTOMARY STANDARD

STANDARD

Traffic flow

Traffic flow

NOTE:

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

See Note 2

10' min.

W21-5W20-1

See Note 3

G20-2

See Note 3

W20-1

See Note 3

G20-2

See Note 3

(See Length and

Spacing Table)

(optional) TERMINATION AREA

W13-1P

(optional)

1.

2.

3.

4.

Final location and spacing of signs and devices may be changed to fit field conditions as approved by the CO.

For project specific minimum width, refer to Special

Contract Requirements, Section 156.

If shoulder closure is completely within the project limits, eliminate the "ROAD WORK AHEAD" (W20-1) and "END

ROAD WORK" (G20-2) signs.

Do not allow equipment, materials, or vehicles to be parked or stored in the buffer space.

Channelizing devices

W

A Device spacing

AVARIABLE WORK SPACEBUFFER SPACETAPER AREAAB

(See Length and Spacing Table)ADVANCE WARNING AREA (See Sign Spacing Table)

PRELIM

WIDTH

"X"

AREA

NUMBER

OF POSTS

POST SIZE D HOLE SIZE

WOOD POST SELECTION TABLE

NO SCALE

635-14

STANDARD APPROVED FOR USE 6/2005

DRAFT: 10/2017

REVISED:

Diamond ≤ 48"

> 30'

> 17'

12' - 16'

> 13'

< 10

65 - 95

65 - 95

50 - 65

50 - 65

20 - 50

10 - 20

10 - 20

6 x 6

4 x 6

4 x 6

6 x 6

4 x 6

4 x 4

6 x 6

4 x 6

4 x 4

(INCH) (INCH)

(INCH)(SQFT)

Other Shapes ≤ 48" Diamond ≤ 36"

Other Shapes ≤ 12' Diamond ≤ 48"

WOOD POSTS

SIGN INSTALLATION

TEMPORARY TRAFFIC CONTROL

1.5

1.5

1.5

1.5

STATE PROJECT

NUMBER

SHEET

U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION

NPS DENA 10(47) AK

U S

C c m y fi le s p w p r o d u c ti o n d d e n a a n .p d f.

d g n

J u ly

FEDERAL LANDS HIGHWAY

U.S. CUSTOMARY STANDARD

STANDARD

SINGLE POST SIGN TWO POST SIGN

SIGN INSTALLATION ANGLE

POST DETAIL

S e e N o te

S e e N o te

See Note 4 E d g e o f tr a v e le d w a y

E d g e o f p a v e d s h o u ld e r

CL Post

Local tangent

Bottom of sign panel

X

H

H

D

H

0.75X

X

X

H

Y D

H

0.2X

0.6X

0.2X

D

See post detail (typ.)

Break-away holes.

Long side of post

D

90°

93°

NPS Drwg. No. XXX/XXXXXX

NPS PMIS No. 164258A

6" x 6" or larger.

Use 7' minimum spacing between posts for sign posts and 6' minimum mounting height for secondary sign.

use 7' minimum mounting height for main sign a minimum lateral distance of 1' behind the face of lateral offset of 2' may be used. In areas with curbs, 200' m in m in

6' - 12'

" dia. bolts 4 1Attach sign panels with a minimum of 2 - 1.

2.

3.

4.

5.

6.

7. State standards may be used as an alternative if approved by the CO.

per post.

H1 and H2 = Overall post length.

Select post lengths to fit field conditions.

D = Post embedment depth for average soil conditions.

In areas where lateral distance is limited, a minimum the curb may be used.

In pedestrian locations, or in areas with obstructed views, NOTE:

See table for hole size parallel to sign face.

Field drill holes through post

PRELIM