659-22-405_Bid Set Specifications_Rev 1_.docx

DOCX document 4 MB Posted

Attached to
Y1DZ--659-22-405 | Install Campus Generator | Salisbury VAMC
Solicitation number
36C24626B0011
Issued by

About this file

This is a comprehensive bid set specification document for the Campus Generator Project at the Salisbury VA Medical Center (VAMC) located at 1606 Brenner Avenue, Salisbury, North Carolina 28144. The project (659-22-405) requires installation of an emergency backup power system to replace outdated generator equipment and provide campus-wide emergency power capability. The Period of Performance is 420 calendar days with a mandatory one-year warranty on all materials and equipment. The project is managed by Above Group, Inc. (305 East Dr. Suite H, Melbourne, FL 32904) serving as the Architect-Engineer, with the Department of Veterans Affairs Salisbury VAMC as the contracting entity.

The specification encompasses extensive construction requirements across 33 divisions covering general conditions, site work, structural systems, mechanical, electrical, plumbing, HVAC, fire protection, communications, and security systems. Key deliverables include detailed shop drawings, a Critical Path Method (CPM) schedule, quality control plans, safety documentation including an Accident Prevention Plan and Activity Hazard Analyses, commissioning activities for building systems, testing and inspection reports, operation and maintenance manuals, warranty management documentation, photographic documentation with BIM interface capabilities, and as-built drawings. Critical submittal requirements include pre-construction conferences, contractor qualifications, CPM developer approval, equipment startup checklists, and coordination with State of North Carolina permits (NPDES General Permit SWG030000, Oil Pollution Prevention compliance per 40 CFR Part 112). The contractor must maintain VA security protocols including badge requirements, restricted photography policies, and compliance with the VA's infection control risk assessments and pre-construction risk assessments relevant to occupied medical facility operations.

View the file

Other files

File Type Posted
36C24626B0011 0003.docx DOCX document
08 71 00.docx DOCX document
RFIs_Response_Rev2.docx DOCX document
36C24626B0011 0002.docx DOCX document
01 91 00 VA Mark up.docx DOCX document
659-22-405 M-801-Blt 2.pdf PDF
659-22-405_Install Campus Generator_Site Visit Sign In Sheet_03.17.2026.docx.pdf PDF
01 33 23 - SHOP DRAWINGS PRODUCT DATA SAMPLES.docx DOCX document
36C24626B0011 0001.docx DOCX document
01 91 00 - VA Mark-up.docx DOCX document
01 91 00 - GEN_COMMISSIONING REQUIR.docx DOCX document
01 45 00 - QUALITY CONTROL.docx DOCX document
01 32 16.15 - PROJECT SCHEDULES - Small Projects – DesignBidBuild.docx DOCX document
657-22-405 Salisbury Emergency Generator Bid Set_.pdf PDF
36C24626B0011_2_Solicitation.docx DOCX document
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Campus Generator Project Salisbury, NC VAMC 100% Final Specifications 36C24623C0090 | 659-22-405 October 7 , 2024

Above Group, Inc. 305 East Dr. Suite H Melbourne, FL 32904

321.345.9026 ph www.abovegroupinc.com

Department of Veterans Affairs Salisbury VAMC, 1606 Brenner Ave, Salisbury, NC 28144

DEPARTMENT OF VETERANS AFFAIRS VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO
DIVISION AND SECTION TITLES
DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15
List of Drawing Sheets
05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00
General Requirements
11-21
01 32 16.01
Architectural and Engineering CPM Schedules
03-20
01 33 23
Shop Drawings, Product Data, and Samples
11-23
01 35 26
Safety Requirements for Major Projects
12-23
01 42 19
Reference Standards
11-20
01 45 00
Quality Control
02-21
01 45 29
Testing Laboratory Services
11-18
01 57 19
Temporary Environmental Controls
01-21
01 74 19
Construction Waste Management
04-22
01 91 00
General Commissioning Requirements
04-22

DIVISION 02 – EXISTING CONDITIONS

02 21 13
Site Surveys
12-23
02 41 00
Demolition
08-17
02 65 00
Underground Storage Tank Removal
01-21

DIVISION 03 – CONCRETE

03 30 00
Cast-in-Place Concrete
01-21

DIVISION 04 – MASONRY

04 05 13
Masonry Mortaring
10-17
04 05 16
Masonry Grouting
01-21
04 20 00
Unit Masonry
08-17

DIVISION 05 – METALS

05 12 00
Structural Steel Framing
11-18
05 21 00
Steel Joist Framing
11-18
05 31 00
Steel Decking
01-21
05 50 00
Metal Fabrications
08-18
05 51 00
Metal Stairs
01-21

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

06 10 00
Rough Carpentry
10-17

01-01-24

00 01 10-1

SECTION NO
DIVISION AND SECTION TITLES
DATE

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 21 13
Thermal Insulation
01-21
07 22 00
Roof and Deck Insulation
01-21
07 27 27
Fluid Applied Membrane Vapor Retarders
07 54 23
Thermoplastic Polyolefin (TPO) Roofing
01-21
07 60 00
Flashing and Sheet Metal
01-21
07 71 00
Roof Specialties
01-21
07 72 00
Roof Accessories
01-21
07 84 00
Firestopping
01-21
07 92 00
Joint Sealants
04-22

DIVISION 08 - OPENINGS

08 11 13
Hollow Metal Doors and Frames
01-21
08 39 53
Blast Resistant Doors and Frames
08 71 00
Door Hardware
01-24
08 90 00
Louvers and Vents
01-21

DIVISION 09 – FINISHES

09 65 13
Resilient Base & Accessories
09 84 33
Sound-Absorbing Wall Units
01-21
09 91 00
Painting
01-21

DIVISION 10 – Specialties

10 14 00
Signage
01-21

DIVISION 21- FIRE SUPPRESSION

21 08 00
Commissioning of Fire Suppression System
11-16
21 13 13
Wet-Pipe Sprinkler Systems
06-15

DIVISION 22 – PLUMBING

22 05 11
Common Work Results for Plumbing
01-23
22 05 23
General-Duty Valves for Plumbing Piping
09-20
22 07 11
Plumbing Insulation
09-19
22 08 00
Commissioning of Plumbing Systems
11-16
22 11 00
Facility Water Distribution
05-21
22 13 00
Facility Sanitary and Vent Piping
09-20
22 40 00
Plumbing Fixtures
12-22

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11
Common Work Results for HVAC
03-23
23 05 12
General Motor Requirements for HVAC and Steam

Generation Equipment 03-23

23 05 41
Noise & Vibration Control HVAC Piping Equipment
SECTION NO
DIVISION AND SECTION TITLES
DATE
23 09 23
Direct-Digital Control System for HVAC
03-23
23 10 00
Facility Fuel Systems
04-20
23 23 00
Refrigerant Piping
03-23
23 31 00
HVAC Ducts and Casings
03-23
23 33 00
Air Duct Accessories
23 34 00
HVAC Fans
03-23
23 37 00
Air Outlets and Inlets
03-23
23 40 00
HVAC Air Cleaning Devices
03-23
23 51 00
Breechings, Chimneys, and Stacks
04-20
23 81 00
Decentralized Unitary HVAC Equipment
03-23
23 81 43
Air-Source Unitary Heat Pumps
03-23
23 82 00
Convection Heating and Cooling Units

DIVISION 26 – ELECTRICAL

26 05 11
Requirements for Electrical Installations
11-22
26 05 13
Medium-Voltage Cables
11-22
26 05 19
Low-Voltage Electrical Power Conductors and Cables
11-22
26 05 26
Grounding and Bonding for Electrical Systems
11-22
26 05 33
Raceway and Boxes for Electrical Systems
11-22
26 05 41
Underground Electrical Construction
11-22
26 05 73
Overcurrent Protective Device Coordination Study
11-22
26 08 00
Commissioning of Electrical Systems
11-22
26 11 16
Secondary Unit Substations
11-22
26 13 13
Medium-Voltage Circuit Breaker Switchgear
11-22
26 13 16
Medium-Voltage Interrupter Switches
11-22
26 23 13
Generator Paralleling Controls
11-22
26 24 13
Distribution Switchboards
11-22
26 24 16
Panelboards
11-22
26 27 26
Wiring Devices
11-22
26 29 21
Enclosed Switches and Circuit Breakers
11-22
26 32 13
Engine Generators
11-22
26 41 00
Facility Lightning Protection
11-22
26 43 13
Surge Protective Devices
11-22
26 51 00
Interior Lighting
11-22
26 56 00
Exterior Lighting
11-22

DIVISION 27 – COMMUNICATIONS

27 05 11
Requirements for Communications Installations
09-19
27 05 26
Grounding and Bonding for Communications Systems
06-15
27 05 33
Raceways and Boxes for Communications Systems
10-18
27 11 00
Telecommunications Room Fittings
06-15
27 15 00
Communications Structured Cabling
01-16

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 05 00
Common Work Results for Electronic Safety and Security
04-18
28 05 13
Conductors and Cables for Electronic Safety and

Security 10-18

SECTION NO
DIVISION AND SECTION TITLES
DATE
28 05 26
Grounding and Bonding for Electronic Safety and

Security 09-11

28 05 28.33
Conduits and Backboxes for Electronic Safety and

Security 09-11

28 08 00
Commissioning of Electronic Safety and Security Systems
11-16
28 13 00
Physical Access Control System
10-11
28 23 00
Video Surveillance
09-11
28 31 00
Fire Detection and Alarm
10-11

DIVISION 31 – EARTHWORK

31 20 11
Earthwork (Short Form)
10-12
31 23 19
Dewatering
10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23
Cement and Concrete for Exterior Improvements
08-16
32 17 23
Pavement Markings
08-16
32 90 00
Planting
08-16

DIVISION 33 – UTILITIES

33 08 00
Commissioning of Site Utility Systems
11-16
33 10 00
Water Utilities
03-17
33 40 00
Storm Sewer Utilities
12-17

SECTION 00 01 15 LIST OF DRAWING SHEETS

The drawings listed below accompanying this specification form a part of the contract.

Drawing No.
Title

GENERAL

GI001
VA COVER SHEET
GI001
NOTES, LEGENDS, & DETAILS

CIVIL

XP101
EXISTING CONDITIONS PLAN
BL101
SOIL BORINGS LOGS - 1
BL102
SOIL BORINGS LOGS - 2
GC101
SEDIMENT & EROSION CONTROL PLAN
GC501
EROSION & SEDIMENT CONTROL DETAILS
GC502
EROSION & SEDIMENT CONTROL DETAILS
GC503
EROSION& SEDIMENT CONTROL DETAILS
CD101
SITE DEMOLITION PLAN
CS101
SITE LAYOUT PLAN
CS501
SITE DETAILS
CU101
SITE UTILITY PLAN
CU201
SITE UTILITY PROFILES
CU501
UTILITY DETAILS
LS101
LANDSCAPE PLAN
LS501
LANDSCAPE DETAILS
CT101
TRUCK TURN PLAN

ARCHITECTURAL

GI100
CODE DATA
AS101
ARCHITECTURAL SITE PLAN
AE101
NEW WORK PLAN
AE102
ROOF PLAN
AC121
REFLECTED CEILING PLAN
AE201
EXTERIOR ELEVATIONS
AE301
BUILDING SECTIONS
AE311
WALL SECTIONS
AE312
WALL SECTIONS

CAMPUS EMERGENCY GENERATOR PROJECT 659-22-405

LIST OF DRAWING SHEETS

00 01 15 - 1

A601 DOOR SCHEDULE & DETAILS

STRUCTURAL

S-001GENERAL NOTES AND ABBREVIATIONS
SS101FOUNDATION AND SLAB ON GRADE PLAN
SS102ROOF FRAMING PLAN
S-301CONCRETE DETAILS AND SECTIONS
S-302CONCRETE DETAILS & SECTIONS
S-401MASONRY DETAILS AND SECTIONS
S-501STEEL DETAILS AND SECTIONS

FIRE ALARM

FA001FIRE ALARM LEGENDS & SYMBOLS
FA100FIRE ALARM SITE PLAN NEW WORK
FA101FLOOR PLAN – FA – NEW WORK
FA500FIRE ALARM DETAILS

FIRE PROTECTION

FP001FIRE PROTECTION LEGENDS & SYMBOLS
FP101FLOOR PLAN – FIRE PROTECTION – NEW WORK
FP501FIRE PROTECTION DETAILS

PLUMBING

P-001PLUMBING NOTES, LEGENDS, & SYMBOLS
PS101FLOOR PLAN – GRAVITY PIPING – NEW WORK
PP101FLOOR PLAN – PRESSURE PIPING – NEW WORK
P-801PLUMBING SCHEDULES

MECHANICAL

M-001MECHANICAL NOTES, LEGENDS, & SYMBOLS
MH101FIRST FLOOR PLAN – MECHANICAL DUCTWORK – NEW WORK
MH102ROOF PLAN – MECHANICAL DUCTWORK – NEW WORK
MP101FIRST FLOOR PLAN – MECHANICAL PIPING – NEW WORK
MI001MECHANICAL INSTRUMENTATION P&ID LEGEND AND TABLE
MI701MECH INSTRUMENTATION – GAS DETECTION SYSTEM P&ID
MI702MECH INSTRUMENTATION – GEN VENTLATION P&ID
MI703
MECH INSTRUMENTATION – BUILDING SYSTEMS P&ID
MI704
MECH INSTRUMENTATION – FUEL OIL SYSTEM P&ID
M-301
MECHANICAL SECTIONS
M-401
MECHANICAL ENLARGED PLANS
M-501
MECHANICAL DETAILS
M-801
MECHANICAL SCHEDULES

ELECTRICAL E-001

ELECTICAL LEGENDS & SYMBOLS

E-100
ELECTRICAL SITE PLAN
E-101
GENERATOR BUILDING PLAN
E-102
GEN BUILDING GROUNDING PLAN
E-103
GEN BUILDING ROOF PLAN
E-104
GEN ENCLOSURE CONDUIT ROUTING PLAN
E-501
ELECTRICAL DETAILS
E-502
ELECTRICAL DETAILS
E-601
EXISITING ELECTRICAL ONE LINE
E-602
PHASE 1 – NEW WORK ONE LINE
E-603
PHASE 2 – DEMOLITION ONE LINE
E-604
PHASE 2 – NEW WORK ONE LINE
E-605
RELAY COMM DIAGRAMS
E-801
ELECTRICAL SCHEDULES

TELECOM

T-001
TECHNOLOGY LEGEND, ABBREV, & GENERAL NOTES
T-100
TECH SITE PLAN NEW WORK
T-101
DATE ACCESS CONTROLL SSTV PLAN
T-501
TECHNOLOGY DETAILS

PART 1 - GENERAL

1.1 SAFETY REQUIREMENTS

SECTION 01 00 00 GENERAL REQUIREMENTS

Station Generator Project Salisbury VA Medical Center 659-22-405

GENERAL REQUIREMENTS

01 00 00 - 10

A. Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for VAMC Salisbury Station Emergency Generators as required by drawings and specifications.

B. Visits to the site by Bidders may be made only by appointment with the Medical Center Engineering Officer.

C. Offices of Above Group, Inc., as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three workdays unless otherwise designated by the COR.

E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, GENERAL CONSTRUCTION: BASE BID Work includes:

1. All construction for the new generator building, including but not limited to:

a. Alterations, roads, walks, grading, drainage, necessary removal of existing structures, relocation and addition of utilities, and site preparation required for the emergency generator systems and building.

b. All equipment required with the medium voltage emergency generator system(s).

c. All support infrastructure and utilities within the new generator building and interconnections with existing utilities required to properly operate the new generator systems.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting Officer. Patients and staff are not to be photographed at any time.

4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation . See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only. Contractor to coordinate with VA Medical Center Facility Manager.

1.6 OPERATIONS AND STORAGE AREAS (FAR 52.236-10)

A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.

B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting Officer, the buildings and utilities may be abandoned and need not be removed.

C. The Contractor shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.

D. Working space and space available for storing materials shall be as determined by the COR.

E. Workers are subject to rules of Medical Center applicable to their conduct.

F. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.

G. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others.

1. Do not store materials and equipment in other than assigned areas.

2. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

H. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved:

1. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

I. Phasing:

1. The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:

2. To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor J. All Buildings will be occupied during performance of work .

1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc. to facilitate patient and staff access. Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical Center operations will continue during the construction period.

K. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings. Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm (one inch) above grade. Remove the fence when directed by COR.

L. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.

2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

M. Utilities Services: Maintain existing utility services for the Medical Center and Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical Center and Cemetery. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.

N. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, shall be removed back to their source. Those which are indicated to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

O. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval.

2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.

P. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.

Q. Coordination of Construction with Cemetery Director: The burial activities at a National Cemetery shall take precedence over construction activities. The Contractor must cooperate and coordinate with the Cemetery Director, through the COR, in arranging construction schedule to cause the least possible interference with cemetery activities in actual burial areas. Construction noise during the interment services shall not disturb the service. Trucks and workers shall not pass through the service area during this period:

1. The Contractor is required to discontinue his work sufficiently in advance of Easter Sunday, Mother's Day, Father's Day, Memorial Day, Veteran's Day and/or Federal holidays, to permit him to clean up all areas of operation adjacent to existing burial plots before these dates.

2. Cleaning up shall include the removal of all equipment, tools, materials and debris and leaving the areas in a clean, neat condition.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by areas:

1. Shall note any discrepancies between drawings and existing conditions at site.

2. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR /, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center .

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS (FAR 52.236-9) A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.

B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the Contractor fails or refuses to repair the damage promptly, the Contracting Officer may have the necessary work performed and charge the cost to the Contractor.

C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils and the environment. Refer to Articles, "Alterations", "Restoration", and "Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.

D. Refer to FAR clause 52.236-7, "Permits and Responsibilities," which is included in General Conditions. A National Pollutant Discharge Elimination System (NPDES) permit is required for this project. The Contractor is considered an "operator" under the permit and has extensive responsibility for compliance with permit requirements. VA will make the permit application available at the (appropriate medical center) office. The apparent low bidder, contractor and affected subcontractors shall furnish all information and certifications that are required to comply with the permit process and permit requirements. Many of the permit requirements will be satisfied by completing construction as shown and specified. Some requirements involve the

Contractor's method of operations and operations planning and the Contractor is responsible for employing best management practices. The affected activities often include, but are not limited to the following:

1. Designating areas for equipment maintenance and repair;

2. Providing waste receptacles at convenient locations and provide regular collection of wastes;

3. Locating equipment wash down areas on site, and provide appropriate control of wash-waters;

4. Providing protected storage areas for chemicals, paints, solvents, fertilizers, and other potentially toxic materials; and

5. Providing adequately maintained sanitary facilities.

1.10 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.11 PHYSICAL DATA – SOIL CONDITIONS

A. Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Terracon - dated May 7 2024.

(FAR 52.236-4)

B. Subsurface conditions have been developed by core borings and test pits. Logs of subsurface exploration are shown diagrammatically on drawings.

C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical Center, Salisbury and shall be considered part of the contract documents.

D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.12 PROFESSIONAL SURVEYING SERVICES

A. A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.13 LAYOUT OF WORK

A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them. If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.

(FAR 52.236-17)

B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, roads, parking lots, are in accordance with lines and elevations shown on contract drawings.

C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:

1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.

D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings. Furnish such certification to the COR before any major items of concrete work are placed. In addition, Contractor shall also furnish to the COR certificates from a registered land surveyor or registered civil engineer that the following work is complete in every respect as required by contract drawings.

1. Lines of each building and/or addition.

2. Elevations of bottoms of footings and tops of floors of each building and/or addition.

3. Lines and elevations of sewers and of all outside distribution systems. 4.

5. Lines of elevations of all swales and interment areas.

6. Lines and elevations of roads, and streets .

E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.

F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy and reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work, including burial monuments and fifty foot stationing along new road centerlines. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.

G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of Article "Professional Surveying Services".

1.14 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.15 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit four sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance & Payment Bonds: The Performance & Payment Bonds /must remain effective throughout the construction period

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the Contractor shall respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/ reviewed at this meeting. In connection with these requirements and at the time of the Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

E. Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

a. Code 1-Life Safety Systems

1) Fire suppression systems.

2) Fire alarm system(s).

b. Code 1-Air Conditioning Systems

1) Air conditioning leak in part of the building, if causing damage.

2) Air conditioning system not cooling properly.

c. Code 1 Doors

1) Overhead doors not operational, causing a security, fire or safety problem.

2) Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

d. Code 3-Doors

1) Overhead doors not operational.

2) Interior/exterior personnel doors or hardware not functioning properly.

e. Code 1-Electrical

1) Power failure (entire area or any building operational after 1600 hours).

2) Security lights.

3) Smoke detectors.

f. Code 2-Electrical

1) Power failure (no power to a room or part of building). Receptacle and lights not operational (in a room or part of building).

g. Code 3-Electrical

1) Exterior lights not operational.

h. Code 1-Gas

1) Leaks and pipeline breaks.

i. Code 1-Heat

1) Power failure affecting heat.

j. Code 1-Plumbing

1) Hot water heater failure.

2) Leaking water supply pipes

k. Code 2-Plumbing

1) Flush valves not operating properly

2) Fixture drain, supply line or any water pipe leaking.

3) Toilet leaking at base.

l. Code 3- Plumbing

1) Leaky faucets.

m. Code 3-Interior

1) Floors damaged.

2) Paint chipping or peeling.

3) Casework damaged.

n. Code 1-Roof Leaks

1) Damage to property is occurring.

o. Code 2-Water (Exterior)

1) No water to facility.

p. Code 2-Water (Hot)

1) No hot water in portion of building listed.

q. Code 3

1) All work not listed above.

F. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

Warranty Tags

Type of product/material

Model number

Serial number

Contract number

Warranty period from/to

Inspector’s signature

Construction Contractor

Address

Telephone number

Warranty Contact

Address

Telephone number

Warranty response time priority code

1.16 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property and, when authorized by the COR, such temporary roads which are…

This is the start of the file's text. The full file is on GovTribe.