6514.24_N_Cargo_Sanitary_Sewer_Service_Ph2_Revised_01.16.25_-_Probable_Cost.pdf

PDF 703 KB Posted

Attached to
Loomis Rd Sanitary Sewer Replacement & Relocation - Phase 2 - Rebid
Solicitation number
25-002-GEN
Issued by
Kenton County, Kentucky

About this file

This document is a 90% Design Estimate for the North Cargo Village Sanitary Sewer Service - Phase 2 Revised project, located at the Cincinnati/Northern Kentucky International Airport. The project is being managed by Gresham Smith with Connico as the project number 6514.24, and is currently in its second revision with dates of 8-Jan-2025 and 16-Jan-2025. The project involves comprehensive sanitary sewer infrastructure work, including mobilization, clearing and grubbing, traffic maintenance, erosion control, and various pipeline installations. The scope includes installing multiple sizes of sanitary sewer pipes (12-inch, 15-inch, and 24-inch) using different methods like trenchless technology and Type 1 bedding, constructing manholes of 48-inch and 72-inch sizes, and performing permanent pavement replacements.

The total Opinion of Probable Construction Cost is $2,203,915, which includes several cost components and markups. The project has a 4.0% allocation for permits, bonds, and insurance, a 24.0% General Contractor markup for profit and overhead, and a 10.0% contingency. The cost estimate breaks down various line items with specific quantities and unit costs, ranging from mobilization ($200,400) to specific pipe installations and tie-ins. Notably, all additional costs such as general conditions, permits, markup, and contingency are included within the unit costs of individual line items, providing a comprehensive and integrated cost structure for the infrastructure project.

View the file

Other files

File Type Posted
Loomis_Rd_Sanitary_Sewer_Replacement_&_Relocation_-_Phase_2_-_Rebid_(Addendum_#2_Revision).pdf PDF
Resident_&_Non-Resident_Bidder_Affidavits.pdf PDF
CCTV_Latest_Findings.pdf PDF
CCTV_104.04.26_to_104.04.26.01_Report.pdf PDF
33_0523-GSBE-Trenchless_Installation_of_Utilities-02.07.25.pdf PDF
CCTV_104.04.26_to_104.04.26.01_Video.mp4 MP4 file
CCTV_104.04.25_to_104.04.26_Report.pdf PDF
CCTV_104.04.25_to_104.04.26_Video.mp4 MP4 file
25-002-GEN_Loomis_Rd_CTL_Summary_of_Findings_Rev1.pdf PDF
Loomis_Rd_Sanitary_Sewer_Phase_1_Plans_-_IFC_11.11.24_-_Ref_Docs.pdf PDF
25-002-GEN_Loomis_Rd_Sani_Sewer-Ph_2_Rebid_-_Contract_&_Bonds-Exh_B.pdf PDF
Loomis_Rd_Sanitary_Sewer_Ph_2_Plans_-_Addendum_1_-_2.11.25.pdf PDF
25-002-GEN_Loomis_Rd_Sani_Sewer-Ph_2_Rebid_-_Proposal_Forms-Exh_A.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Ph_2_Rebid_-_Notice_to_Bidders_-_2nd_Ad.pdf PDF
6514.24_N_Cargo_Sanitary_Sewer_Service_Ph2_Revised_01.16.25_-_Probable_Cost.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Ph_2_Rebid_-_Notice_to_Bidders.pdf PDF
25-002-GEN_Loomis_Rd_Sanitary_Sewer_Phase_2-Rebid_-_Specs.pdf PDF
Business_Case_-_Sanitary_Sewer_Loomis_-_Construction_(Phase_1_and_Phase_2).xlsx XLSX spreadsheet
#25-000-GEN_Constr_Contractors_List_-_Bidders_List.xlsx XLSX spreadsheet
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Add Logo in Cell A1 Project Title North Cargo Village Sanitary Sewer Service - Phase 2 Revised Location Cincinnati/Northern Kentucky International Airport Submittal Stage 90% Design Estimate Client Name Gresham Smith Client Project No. 47153.02 Revision 2 Original Date 8-Jan-2025 Revision Date 16-Jan-2025 Assumed Bid Opening Date

Connico PN 6514.24

Project Lead JSJ Checked by MGF

DESCRIPTION TOTAL

NORTH CARGO VILLAGE SANITARY SERVICE - PHASE 2 2,203,915$

The following markups are included in the project costs:

Permit, Bond and Insurance 4.0%

GC Markup - Profit / OH 24.0%

Contingency 10.0%

Owner's Soft Costs 0.0% Program Management 0.0% Construction Manager 0.0% Planning & Preconstruction 0.0% Architectural / Engineering Design 0.0% Architectural / Engineering Construction Admin 0.0% Temporary Easements 0.0% Materials Testing / Inspection / Commissioning 0.0% Plan Check Services 0.0% Cost Estimating & Scheduling 0.0% Miscellaneous Owner Costs (i.e. Legal) 0.0% Owner's Construction Contingency 0.0% Project Contingency 0.0%

LOOMIS ROAD SANITARY SEWER RELOCATION

SUMMARY

Any modification, duplication or use of this document without the express written consent of Connico is prohibited and Connico assumes no responsibility for any such unauthorized use, duplication or modification of this document.

Project Title North Cargo Village Sanitary Sewer Service - Phase 2 Revised Location Cincinnati/Northern Kentucky International Airport Submittal Stage 90% Design Estimate Client Name Gresham Smith Client Project No. 47153.02 Revision 2 Original Date 8-Jan-2025 Revision Date 16-Jan-2025 Assumed Bid Opening Date Connico PN 6514.24 Project Lead JSJ Checked by MGF

ITEM

NO.

SPEC NO. DESCRIPTION QUANTITY UNIT UNIT COST TOTAL

1 Mobilization 1 ls 200,400.00$ 200,400$ 2 Clearing and Grubbing 1 ls 7,250.00$ 7,250$ 3 Maintaining Traffic 1 ls 35,000.00$ 35,000$ 4 Erosion and Sediment Control 1 ls 14,500.00$ 14,500$ 5 Seeding and Mulching, Class 1 1,414 sy 22.00$ 31,108$ 6 Permanent Pavement Replacement:

Concrete Sidewalk 1 ls 1,450.00$ 1,450$

7 Permanent Pavement Replacement: Asphalt 29 cy 362.00$ 10,498$ 8 Permanent Pavement Replacement:

Compacted Gravel 375 cy 152.00$ 57,000$

9 Cap and Fill Abandoned Lines 1 ls 3,650.00$ 3,650$ 10 Manhole: 48 Inch with Heavy Lid 5 ea 29,350.00$ 146,750$ 11 Manhole: 72 Inch with Heavy Lid 6 ea 73,350.00$ 440,100$ 12 Sanitary Sewer, 15 Inch Cured In Place Pipe 600 lf 471.00$ 282,600$ 13 Sanitary Sewer, 12 Inch PVC, 25 to 30 ft of

Cover, Trenchless 375 lf 222.00$ 83,250$

14 Sanitary Sewer, 15 Inch PVC, 10 to 15 ft of Cover, Trenchless

188 lf 656.00$ 123,328$

15 Sanitary Sewer, 24 Inch PVC, 30 to 35 ft of Cover, Trenchless

250 lf 365.00$ 91,250$

16 Sanitary Sewer, 15 Inch PVC with Type 1 Bedding, 15 to 20 ft Of Cover

327 lf 258.00$ 84,366$

17 Sanitary Sewer, 15 Inch PVC with Type 1 Bedding, 25 to 30 ft Of Cover

144 lf 320.00$ 46,080$

18 Sanitary Sewer, 24 Inch PVC with Type 1 Bedding, 25 to 30 ft Of Cover

387 lf 385.00$ 148,995$

19 Sanitary Sewer, 24 Inch PVC with Type 1 Bedding, 30 to 35 ft Of Cover

904 lf 410.00$ 370,640$

20 Sanitary, Tie-In 15" PVC, Upstream Material:

VCP

1 ea 11,000.00$ 11,000$

21 Sanitary, Tie-In 12" PVC, Upstream Material:

Conc

2 ea 7,350.00$ 14,700$

Subtotal 2,203,915$

2% General Condition Included in Unit Cost 4.0% Permit, Bond and Insurance Included in Unit Cost

24.0% GC Markup - Profit / OH Included in Unit Cost 10.0% Contingency Included in Unit Cost

Opinion of Probable Construction Cost 2,203,915$

NORTH CARGO VILLAGE SANITARY SERVICE - PHASE 2