612748 A4.pdf
PDF 268 KB Posted
- Attached to
- 612748 - DISTRICT 6
- Solicitation number
- BD-23-1030-0H100-0H002-86333
- Issued by
- Suffolk County, Massachusetts
About this file
This document is an Addendum No. 4 for a state and local contract opportunity issued by the Massachusetts Department of Transportation (MassDOT) for the Inspection, Testing, Maintenance & Repairs of Fire Detection Systems at Various Locations in District 6. The project involves performing inspections, testing, maintenance, and repairs on fire detection systems at 38 different sites, including tunnels. The contract provides details on the allowed work hours, with tunnel devices to be inspected during third shift with proper closures. The contract requires the use of an approved barcoding provider for all testing, and coordination with the fire alarm monitoring company, American Alarm. The contract also requires the successful bidder to review construction projects and submittals related to the contract. The proposal is due to be opened and read on Wednesday, April 19, 2023 at 2:00 P.M.
The contract requires a valid F-1 License, and while a UL Testing certificate is preferred, it is not required. Bidders are responsible for coordinating any necessary road closures with the Department of Transportation Supervisor. The cost related to reviewing construction projects and submittals will be incidental to the appropriate item. There are no set-asides mentioned, and the incumbent contractor is not specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 612748 PHL.pdf | ||
| 612748 BidTabs.pdf | ||
| 612748 PD.pdf | ||
| 612748 A2.pdf | ||
| 612748 MWBE.pdf | ||
| 612748 NTC.pdf | ||
| 612748 SP.pdf | ||
| 612748 BidResults.pdf | ||
| 612748 A1.pdf | ||
| 612748 SL.pdf | ||
| BIL 612748.txt | TXT text file | |
| 612748 ACF.pdf | ||
| 612748 DFAR.pdf | ||
| 612748 A3.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ten Park Plaza, Suite 4160, Boston, MA 02116 Tel: 857-368-4636, TTY: 857-368-0655 mass.gov/massdot
April 14, 2023
Proposal No. 612748-121699
ADDENDUM NO. 4
To Prospective Bidders and Others on:
DISTRICT 6
Inspection, Testing, Maintenance & Repairs of Fire Detection Systems at
Various Locations
PROPOSAL TO BE OPENED AND READ: WEDNESDAY, APRIL 19, 2023 at 2:00 P.M.
Transmitting changes to the Contract Documents as follows:
RESPONSES TO BIDDERS’ QUESTIONS: Two pages attached.
Please take note of the above and acknowledge Addendum No. 4 in your Expedite Proposal file before submitting your bid.
Very truly yours, Eric M. Cardone, P.E.
Construction Contracts Engineer
MB
c: Youssef, Ancarlos, Project Manager
THIS PAGE INTENTIONALLY LEFT BLANK
DISTRICT 6
Inspection, Testing, Maintenance & Repairs of Fire Detection Systems at Various
Locations (612748-121699)
Responses to Bidders’ Questions Addendum No. 4, April 14, 2023
Pine Ridge Technologies, Inc., e-mail dated April 11, 2023
Question 3) The Q+A response #1 on addendum #3 does not answer the question. Please delineate the allowed work hours for each of the buildings/locations on this project.
Response 3) Buildings can be inspected/tested during first shift during normal business hours and tunnel devices are to be inspected during third shift with proper closures (this is where coordination with District Operations would be needed).
The RE will advise the contractor which locations need to be addressed first.
Aetna Fire Alarm Service Co., Inc., e-mail dated April 11, 2023
Question 4) Are all tunnel devices to be tested off hours, pending traffic shut downs?
Response 4) Yes
Question 5) Are occupied buildings’ AV testing performed off hours?
Response 5) No, however Contractors are allowed to start earlier by an hour or two.
Question 6) Is all testing required to be on an approved Barcoding provider?
Response 6) Yes (CLSS or Building Reports is acceptable)
Question 7) Will testing of the fireworks system be required for all 38 sites as a part of this contract?
Response 7) Yes
Question 8) Will we be responsible to coordinate with HOCs DYNAC as part of testing?
Response 8) Yes, signals must be checked to ensure they were received.
Question 9) Will we be responsible for testing the deluge, suppression and various sprinkler systems with the Sprinkler contractor?
Response 9) Yes
Question 10) Will coordinating road closures with DOT be the responsibility of the Fire
Alarm Contractor?
Response 10) Contractor must coordinate with DOT Supervisor.
DISTRICT 6
Inspection, Testing, Maintenance & Repairs of Fire Detection Systems at Various
Locations (612748-121699)
Responses to Bidders’ Questions Addendum No. 4, April 14, 2023
Question 11) Are we responsible for testing the thermal road system fire detection points?
Response 11) Yes
Question 12) Are we responsible for bi-directional antennae testing?
Response 12) No
Question 13) Is an F-1 License required?
Response 13) Yes
Question 14) Who is the Fire Alarm Monitoring Company?
Response 14) American Alarm
Question 15) Is a UL Testing certificate required?
Response 15) No but it is preferred.
Question 16) Is the Fire Alarm contractor responsible to review construction projects and submittals for the DOT at no cost to the DOT?
Response 16) Both Fire Alarm contractor and MassDOT will review construction projects and submittals. The cost related to reviewing construction projects and submittals will be incidental to the appropriate item.