609213 HARVARD FAP No. STP-0033(045)X Resurfacing and Box Widening on Ayer Road, from Route 2 to t
Solicitation number
BD-27-1030-0H100-0H002-130914
Issued by
Worcester County, Massachusetts

About this file

This is a bid items list for the Massachusetts Department of Transportation project 609213, which involves resurfacing and box widening on Ayer Road from Route 2 to the Ayer Town Line in Harvard, Massachusetts. The project encompasses a comprehensive range of construction activities including clearing and grubbing, tree removal and protection, extensive excavation and fill work, drainage structure installation and removal, pavement milling and resurfacing with multiple asphalt courses, curb and sidewalk installation, guardrail and fence work, erosion control measures, wetland replication and monitoring, utility relocations, traffic control signage, and pavement markings. The bid items list specifies 234 individual line items with quantities ranging from 1 unit for specialized structures such as 6-foot diameter special manholes and various electric service riser relocations to 86,250 days for reflectorized drums. Notable quantities include 25,000 square yards of pavement fine milling, 10,170 cubic yards of unclassified excavation, 9,000 cubic yards of gravel borrow, 4,250 tons of Superpave intermediate course asphalt, and 14,500 square yards of seeding work. The project also includes environmental and safety components such as an environmental health and safety program, licensed site professional services, invasive plant management, and NPDES stormwater pollution prevention planning.

The bid items list does not contain explicit pricing information, contract award dates, bidder meeting schedules, or site visit requirements within this document. However, the project includes a fixed-price schedule of operations item valued at $75,000 and engineer's field office staffing for 38 months. The project involves multiple specialized work categories indicating a complex, phased construction effort with significant coordination requirements for utility relocations, environmental compliance, and traffic management. The inclusion of 11 separate electric service riser relocations, six rectangular rapid flashing beacon installations, and extensive traffic control measures suggests an active roadway project requiring careful sequencing and public safety management. The project specifically notes that bidding should not be conducted through COMMBUYS, indicating it utilizes an alternative procurement mechanism.

Text of this file

PRO_FILENO = 609213,DESCPT = Resurfacing and Box Widening on Ayer Road, from Route 2 to the Ayer Town Line,Location = HARVARD,DB_CONTRACT = 134927

OFF_QUANT,UNITS,DESCPT1,ITEM_NO

"1.200","A","CLEARING AND GRUBBING","101."

"1000.000","FT","TREE TRIMMING","102.1"

"16.000","HR","HERBICIDE TREATMENT OF INVASIVE PLANTS","102.3"

"8.000","HR","INVASIVE PLANT MANAGEMENT STRATEGY","102.33"

"21.000","EA","TREE PROTECTION - ARMORING AND PRUNING","102.511"

"750.000","FT","TREE AND PLANT PROTECTION FENCE","102.521"

"40.000","HR","ARBORIST","102.55"

"11.000","EA","TREE REMOVED - DIAMETER UNDER 24 INCHES","103."

"1.000","EA","TREE REMOVED - DIAMETER 24 INCHES AND OVER","104."

"9.000","EA","STUMP REMOVED","105."

"10170.000","CY","UNCLASSIFIED EXCAVATION","120.1"

"310.000","CY","CLASS A TRENCH EXCAVATION","141."

"60.000","CY","TEST PIT FOR EXPLORATION","141.1"

"325.000","CY","CLASS B TRENCH EXCAVATION","142."

"10.000","CY","CLASS B ROCK EXCAVATION","144."

"23.000","EA","DRAINAGE STRUCTURE REMOVED","146."

"35.000","CY","DREDGING AND STOCKPILING OF MATERIAL","148.01"

"1000.000","CY","ORDINARY BORROW","150."

"9000.000","CY","GRAVEL BORROW","151."

"90.000","CY","GRAVEL BORROW FOR BACKFILLING STRUCTURES AND PIPES","151.2"

"2150.000","TON","CRUSHED STONE","156."

"325.000","CY","CONTROLLED LOW-STRENGTH MATERIAL - MECHANICAL EXCAVATABLE (101-300 PSI)","160.2"

"22000.000","SY","FINE GRADING AND COMPACTING - SUBGRADE AREA","170."

"1.000","LS","ENVIRONMENTAL HEALTH AND SAFETY PROGRAM","180.01"

"40.000","HR","PERSONAL PROTECTION LEVEL C UPGRADE","180.02"

"40.000","HR","LICENSED SITE PROFESSIONAL SERVICES","180.03"

"3100.000","TON","DISPOSAL OF UNREGULATED SOIL","181.11"

"70.000","TON","DISPOSAL OF REGULATED SOIL - IN-STATE FACILITY","181.12"

"70.000","TON","DISPOSAL OF REGULATED SOIL - OUT-OF-STATE FACILITY","181.13"

"35.000","TON","DISPOSAL OF HAZARDOUS WASTE","181.14"

"1.100","TON","DISPOSAL OF TREATED WOOD PRODUCTS","184.1"

"39.000","EA","CATCH BASIN","201."

"5.000","EA","SPECIAL CATCH BASIN","201.3"

"33.000","EA","MANHOLE","202."

"1.000","EA","SPECIAL MANHOLE - 5 FOOT DIAMETER","203.5"

"1.000","EA","SPECIAL MANHOLE - 6 FOOT DIAMETER","203.6"

"1.000","EA","GUTTER INLET","204."

"3.000","EA","DROP INLET, TYPE DF","209.1"

"57.000","EA","DRAINAGE STRUCTURE ADJUSTED","220."

"10.000","FT","DRAINAGE STRUCTURE REBUILT","220.2"

"1.000","EA","DRAINAGE STRUCTURE REMODELED","220.5"

"81.000","EA","FRAME AND GRATE (OR COVER) MUNICIPAL STANDARD","222.3"

"3.000","EA","FRAME AND GRATE (OR COVER) REMOVED AND DISCARDED","223.2"

"44.000","EA","12 INCH HOOD","224.12"

"15.000","CY","REMOVAL OF DRAINAGE STRUCTURE SEDIMENT","227.3"

"90.000","FT","REMOVAL OF DRAINAGE PIPE SEDIMENT","227.31"

"500.000","FT","12 INCH DRAINAGE PIPE - OPTION","234.12"

"20.000","FT","12 INCH DUCTILE IRON PIPE","238.12"

"40.000","FT","18 INCH DUCTILE IRON PIPE","238.18"

"3500.000","FT","12 INCH REINFORCED CONCRETE PIPE CLASS III","241.12"

"550.000","FT","15 INCH REINFORCED CONCRETE PIPE CLASS III","241.15"

"525.000","FT","18 INCH REINFORCED CONCRETE PIPE CLASS III","241.18"

"200.000","FT","24 INCH REINFORCED CONCRETE PIPE CLASS III","241.24"

"20.000","FT","36 INCH REINFORCED CONCRETE PIPE CLASS III","241.36"

"75.000","FT","48 INCH REINFORCED CONCRETE ARCH PIPE","241.481"

"1.000","EA","15 INCH REINFORCED CONCRETE PIPE FLARED END","242.15"

"775.000","FT","12 INCH REINFORCED CONCRETE PIPE CLASS IV","243.12"

"600.000","FT","15 INCH REINFORCED CONCRETE PIPE CLASS IV","243.15"

"30.000","SY","STONE FOR PIPE ENDS","258."

"1450.000","FT","12 INCH AND UNDER PIPE REMOVED AND DISCARDED","271.121"

"400.000","FT","18 INCH PIPE REMOVED AND DISCARDED","271.181"

"200.000","FT","24 INCH PIPE REMOVED AND DISCARDED","271.241"

"40.000","FT","30 INCH PIPE REMOVED AND DISCARDED","271.301"

"980.000","CY","DENSE GRADED CRUSHED STONE FOR SUB-BASE","402."

"25000.000","SY","PAVEMENT FINE MILLING","415.2"

"55.000","SY","HIGH EARLY STRENGTH CEMENT CONCRETE BASE COURSE","431."

"24000.000","LB","CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL","440."

"85.000","MGL","WATER FOR ROADWAY DUST CONTROL","443."

"775.000","TON","SUPERPAVE SURFACE COURSE – 9.5 (SSC – 9.5)","450.22"

"1275.000","TON","SUPERPAVE SURFACE COURSE - 12.5 (SSC - 12.5)","450.23"

"3350.000","TON","SUPERPAVE SURFACE COURSE - 12.5 POLYMER (SSC - 12.5 - P)","450.231"

"4250.000","TON","SUPERPAVE INTERMEDIATE COURSE - 19.0 (SIC - 19.0)","450.32"

"1900.000","TON","SUPERPAVE BASE COURSE - 37.5 (SBC - 37.5)","450.42"

"275.000","TON","SUPERPAVE LEVELING COURSE - 9.5 (SLC - 9.5)","450.52"

"700.000","TON","HMA FOR PATCHING","451."

"7000.000","GAL","ASPHALT EMULSION FOR TACK COAT","452."

"49000.000","FT","HMA JOINT ADHESIVE","453."

"385.000","FT","HOT MIX ASPHALT BERM, TYPE A – MODIFIED","470.2"

"850.000","TON","TEMPORARY ASPHALT PATCHING","472."

"9000.000","FT","MILLED RUMBLE STRIP (TYPE C)","477.2"

"8500.000","FT","SAWCUTTING ASPHALT PAVEMENT FOR BOX WIDENING","482.5"

"6300.000","FT","GRANITE CURB TYPE VB - STRAIGHT","506."

"380.000","FT","GRANITE CURB TYPE VB - CURVED","506.1"

"400.000","FT","GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - STRAIGHT","509."

"800.000","FT","GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - CURVED","509.1"

"26.000","EA","GRANITE CURB INLET - STRAIGHT","514."

"155.000","FT","HOT MIX ASPHALT CURB TYPE 2","570.2"

"20.000","FT","HOT MIX ASPHALT CURB TYPE 3","570.3"

"500.000","FT","GUARDRAIL, TL-2 (SINGLE FACED)","620.12"

"600.000","FT","GUARDRAIL, DEEP POST (SINGLE FACED)","620.131"

"115.000","FT","GUARDRAIL - CURVED, TL-2 (SINGLE FACED)","620.32"

"2.000","EA","TRAILING ANCHORAGE","627.1"

"8.000","EA","GUARDRAIL TANGENT END TREATMENT, TL-2","627.82"

"2.000","EA","GUARDRAIL FLARED END TREATMENT, TL-3","627.93"

"4.000","EA","TRANSITION TO NCHRP 350 GUARDRAIL","628.21"

"2.000","EA","TEMPORARY IMPACT ATTENUATOR, REDIRECTIVE, TL-2","628.314"

"4.000","EA","TEMPORARY IMPACT ATTENUATOR, REMOVED AND RESET","628.4"

"2.000","EA","CONCRETE BARRIER REMOVED AND STACKED","629.01"

"1200.000","FT","HIGHWAY GUARD REMOVED AND DISCARDED","630.2"

"475.000","FT","POST AND RAIL WOOD FENCE","655.3"

"10.000","FT","FENCE REMOVED AND STACKED","669."

"20.000","CY","STONE MASONRY WALL REMOVED AND STACKED","690.11"

"1800.000","FT","BALANCE STONE WALL REMOVED AND REBUILT","691."

"140.000","FT","BALANCE STONE WALL REMOVED AND STACKED","691.1"

"550.000","FT","SEDIMENTATION FENCE","697."

"75.000","EA","SILT SACK","697.1"

"30.000","SY","GEOTEXTILE FABRIC FOR SEPARATION","698.3"

"100.000","SY","GEOTEXTILE FABRIC FOR PERMANENT EROSION CONTROL","698.4"

"10.000","SY","CEMENT CONCRETE SIDEWALK","701."

"800.000","SY","CEMENT CONCRETE PEDESTRIAN CURB RAMP","701.2"

"1050.000","TON","HOT MIX ASPHALT SIDEWALK OR DRIVEWAY","702."

"1.000","LS","PLANTER REMOVED AND STACKED, LOCATION 1","707.011"

"1.000","LS","PLANTER REMOVED AND STACKED, LOCATION 2","707.012"

"32.000","EA","BOULDER REMOVED AND STACKED","707.03"

"4.000","EA","POST REMOVED AND STACKED","707.82"

"4.000","EA","BOUND REMOVED AND RESET","711."

"1.000","EA","IRON PIN REMOVED AND RESET","711.01"

"1.000","EA","BOUND REMOVED AND STACKED","712."

"34.000","EA","RURAL MAIL BOX REMOVED AND RESET","715."

"1.000","LS","SCHEDULE OF OPERATIONS (TYPE C) - FIXED PRICE $75000","722.3"

"38.000","MO","ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE A)","740."

"1.000","LS","MOBILIZATION","748."

"1300.000","CY","LOAM FOR ROADSIDES","751."

"700.000","CY","LOAM FOR LAWNS","751.1"

"15.000","CY","COMPOST BLANKET","751.7"

"1.000","LS","INLAND WETLAND REPLICATION AREA","755.35"

"40.000","HR","WETLAND SPECIALIST","755.75"

"1.000","LS","WETLANDS MONITORING REPORTS","755.76"

"1.000","LS","NPDES STORMWATER POLLUTION PREVENTION PLAN","756."

"14500.000","SY","SEEDING","765."

"25.000","LB","ANNUAL COVER CROP FOR NATIVE SEEDING","765.21"

"12.000","LB","NATIVE SHORT GRASSLAND MIX","765.415"

"3500.000","SY","NATIVE SEEDING AND ESTABLISHMENT","765.635"

"5200.000","FT","SEDIMENT CONTROL BARRIER","767.121"

"700.000","FT","SEDIMENT BARRIER - COIR LOG","767.122"

"100.000","SY","JUTE MESH","767.9"

"1650.000","FT","PAVEMENT MILLING MULCH UNDER GUARD RAIL","769."

"725.000","FT","3 INCH ELECTRICAL CONDUIT TYPE NM - PLASTIC -(UL)","804.3"

"16.000","EA","PULL BOX 12 X 12 INCHES - SD2.031","811.31"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 1","813.811"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 2","813.812"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 3","813.813"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 4","813.814"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 5","813.815"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 6","813.816"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 7","813.817"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 8","813.818"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 9","813.819"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 10","813.820"

"1.000","LS","ELECTRIC SERVICE RISER RELOCATION LOCATION NO. 11","813.821"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 1","825.101"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 2","825.102"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 3","825.103"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 4","825.104"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 5","825.105"

"1.000","LS","RECTANGULAR RAPID FLASHING BEACON (AC POWER) LOCATION 6","825.106"

"80.000","SF","ROADSIDE GUIDE SIGN (D6/D8) - ALUMINUM PANEL (TYPE A)","831."

"265.000","SF","WARNING-REGULATORY AND ROUTE MARKER - ALUMINUM PANEL (TYPE A)","832."

"1.000","EA","SUPPORTS FOR GUIDE SIGN (D6-5 INCH TUBULAR POST) STEEL","841.2"

"2.000","EA","SUPPORTS FOR GUIDE SIGN (MA-D1-7) STEEL","841.81"

"66.000","EA","SIGN SUP (NOT GUIDE)+RTE MKR W/1 BRKWAY POST ASSEMBLY - STEEL","847.1" "2.000","EA","SIGN SUP (NOT GUIDE)+RTE MKR W/2 BRKWAY POST ASSEMBLIES-STEEL","848.1"

"700.000","SF","SAFETY SIGNING FOR TRAFFIC MANAGEMENT","852."

"4.000","EA","PORTABLE BREAKAWAY BARRICADE TYPE III","853.1"

"200.000","FT","TEMPORARY BARRIER (TL-2)","853.2"

"400.000","FT","TEMPORARY BARRIER REMOVED AND RESET","853.21"

"40000.000","FT","TEMPORARY PAVING MARKINGS - 6 INCH (PAINTED)","854.016"

"3500.000","FT","TEMPORARY PAVING MARKINGS - 6 INCH (TAPE)","854.036"

"1920.000","DAY","ARROW BOARD","856."

"2880.000","DAY","PORTABLE CHANGEABLE MESSAGE SIGN","856.12"

"86250.000","DAY","REFLECTORIZED DRUM","859."

"120.000","DAY","REFLECTORIZED DRUMS WITH SEQUENTIAL FLASHING WARNING LIGHTS","859.1" "18500.000","FT","FAST DRY MULTI-COMPONENT PAVEMENT MARKINGS, RECESSED, WET REFLECTIVE (6 INCH WHITE LINE)","862.506" "19500.000","FT","FAST DRY MULTI-COMPONENT PAVEMENT MARKINGS, RECESSED, WET REFLECTIVE (6 INCH YELLOW LINE)","863.506" "315.000","SF","PAVEMENT ARROWS AND LEGENDS REFLECTORIZED WHITE (THERMOPLASTIC)","864.04"

"4200.000","FT","12 INCH REFLECTORIZED WHITE LINE (THERMOPLASTIC)","866.112"

"400.000","FT","12 INCH REFLECTORIZED YELLOW LINE (THERMOPLASTIC)","867.112"

"10.000","EA","STREET NAME SIGN","874."

"34.000","EA","TRAFFIC SIGN REMOVED AND RESET","874.2"

"40.000","EA","TRAFFIC SIGN REMOVED AND STACKED","874.4"

"4.000","EA","MISCELLANEOUS SIGNS REMOVED AND STACKED","874.7"

"40.000","CY","4000 PSI, 3/4 INCH, 610 CEMENT CONCRETE","904."

"550.000","LB","STEEL REINFORCEMENT FOR STRUCTURES","910."

"35.000","CY","STREAMBED RESTORATION","983.521"

"1.000","LS","CONTROL OF WATER - LOCATION NO. 1","991.11"

"1.000","LS","CONTROL OF WATER - LOCATION NO. 2","991.112"

Other files

File Type Posted
HARVARD-609213-134927-A-4.pdf PDF
A00820-609213.pdf PDF
A00831-609213.pdf PDF
HARVARD-609213-134927-A-2.pdf PDF
A00816-609213.pdf PDF
A00810-609213.pdf PDF
A00861-609213.pdf PDF
609213 - Notice to Contractors.pdf PDF
A00808-609213.pdf PDF
A00870-609213.pdf PDF
A00801-609213.pdf PDF
A00875-609213.pdf PDF
HARVARD-609213-134927-A-3.pdf PDF
A00860-609213.pdf PDF
A00830-609213.pdf PDF
609213 - Plan Holders List 7-15-2026.pdf PDF
A00802-609213.pdf PDF
HARVARD-609213-134927-A-1.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .