(6) LARGE CONTAINER STATEMENT OF WORK.pdf

PDF 294 KB Posted

Attached to
Fabrication of Screw Disposal Containers, Large & Small
Solicitation number
N3904024R0006
Issued by

About this file

This combined synopsis and solicitation document from the Department of the Navy seeks quotations for the fabrication of three types of disposal containers. Specifically, it requests the fabrication of two small shear block disposal containers, ten large shear block disposal containers made of ASTM A36 steel, and one lead screw disposal container made of ASTM A36 steel. The solicitation is reserved for small businesses only and sets a February 9, 2024 deadline for submissions. It describes technical and past performance evaluation criteria and notes that price will not be scored but evaluated for reasonableness. The statement of work provides additional requirements regarding material certifications, inspection points, and shipment notification.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

DOC #: 3290V106

Large Shear Block Disposal Containers (RF-2202)

1. Each Large Shear Block Disposal Container (SBDC) is to be manufactured in accordance with Portsmouth Naval Shipyard (PNSY) drawing 2370A0000388, Revision A. A total of ten (10) complete Large Shear Block Disposal Containers are required to be built.

2. The PNSY technical Point of Contact (POC) in Code 2370 is Jeff Turgeon (207-438-5375), Ryan Knight (207-438-5669), or Phil Mitchell (207-438-4559).

3. PNSY Code 2370 requires a technical review of contractor bid prior to contract award.

4. The contractor will comply with all specifications and provide all certifications and test reports as outlined in PNSY drawing 2370A0000388, Revision A, for the Large Shear Block Disposal Containers.

5. PNSY plans to inspect the containers at an approximate half way point of construction and at completion of construction. Contractor shall notify PNSY with projected work schedule.

Halfway point of construction shall be determined by the contractor and PNSY after award of contract.

6. PNSY reserves the right to inspect the containers at any time during fabrication in addition to the mid-construction visit outlined above. A minimum of two working days notice will be given to the contractor for unplanned visits by a PNSY representative.

7. The local DCMA office shall conduct an "on-site" contractor post-award to verify that the contractor maintains facilities and fully understands the contract terms, conditions and responsibilities, ensuring contract specifications and requirements are able to be met. The buyer reserves the right to attend the post-award verification along with DCMA.

8. Contractor shall contact PNSY a minimum of two working days prior to shipment of completed containers to Portsmouth Naval Shipyard.

File details come from the government source that posted it. Updated .