This Invitation to Bid (ITB) is issued by the City of Little Rock, Arkansas Parks and Recreation Department for the Green Network Project at Reservoir and Murray Parks in Pulaski County. The project involves tree and sapling planting services, including site preparation, invasive species removal, procurement, installation, and one-year post-planting maintenance and monitoring. The scope requires planting approximately 7,550 trees and saplings consisting of 7,100 mixed-species bare root native seedlings and 450 semi-mature three-inch caliper trees (102 White Oak, 102 Red Oak, 96 Hickory, 78 Walnut, and 72 Eastern Redbud). The contractor must achieve a minimum 90 percent survival rate through 2027. The pre-bid walk-through meetings are scheduled for May 21, 2026, at Reservoir Park (10:00 a.m.) and Murray Park (2:30 p.m.). Vendor questions must be submitted by June 3, 2026, at 10:00 a.m., with bids due by June 10, 2026, at 10:00 a.m. Bid opening will occur via Microsoft Teams at 10:15 a.m. on June 10, 2026. The award will be made on an "all or none basis" to the lowest qualified bidder meeting all specified requirements. Work must commence within ten calendar days of receiving the Notice to Proceed and be completed within 180 consecutive calendar days thereafter.
Bidders must submit pricing for both Reservoir Park and Murray Park separately, with all costs including site preparation, procurement, planting, maintenance, and reporting included in the quoted price. Pricing must remain valid for 90 days following the bid opening. The project is funded through an Environmental Protection Agency assistance agreement under the Inflation Reduction Act's Climate Pollution Reduction Grants program (Federal Award Identification Number 02F75801). Qualified bidders must hold a valid Arkansas contractor license, possess a minimum of three years' experience in tree planting and invasive species removal, maintain SAM registration, provide proof of valid pesticide and herbicide applicator licenses, and demonstrate capability for multi-year monitoring and reporting. Contractors must carry comprehensive general liability insurance of one million dollars, personal injury coverage of one million dollars, and property damage coverage of one million dollars, naming the City of Little Rock as an additional insured. The contract includes federal compliance requirements including Davis-Bacon and Related Acts (DBRA) provisions, Byrd Anti-Lobbying Amendment certification for awards exceeding $100,000, and disadvantaged business enterprise participation requirements under 40 CFR Part 33. Monthly vendor update meetings will be required, with quarterly performance reports on procurement, installation, post-planting treatments, and survival rates. Payment will follow standard 30-day net terms through the City's Accounts Payable Division.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION TO BID
Bid Event # 235927 Job # 02F75801
Green Network Project - Reservoir and Murray Park
Pulaski County
City of Little Rock, Arkansas
The capital city of Arkansas is also the state’s largest municipality with over 202,000 people calling it home. The City of Little Rock employs over 2,500 employees in 16 departments. It is our mission to ensure our City is a safe, secure, and prospering place to live, work, and play.
Mayor Frank Scott Jr.
City of Little Rock Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
City of Little Rock, 500 W. Markham St., Little Rock Arkansas 72201 (501) 371-4560
Contents
SCHEDULE AND ACCESS INFORMATION
SECTION 1 – GENERAL INFORMATION
1.1 PURPOSE
1.2 BACKGROUND INFORMATION
1.3 DEFINITION OF REQUIREMENT
1.4 DEFINITIONS OF TERMS
1.5 RESPONSE DOCUMENTS
1.6 NONCOLLUSION
1.7 PROPRIETARY INFORMATION
1.8 ISRAEL BOYCOTT NOTICE
1.9 BOYCOTT OF THE ENERGY, FOSSIL FUEL, FIREARMS, AND AMO INDUSTRIES
1.10 REQUIREMENT OF ADDENDUM
1.11 PAST PERFORMANCE
SECTION 2 – PROJECT SCOPE OF SERVICES
2.1 GOAL
2.2 TERMS OF AWARD
2.3 MINIMUM QUALIFICATIONS
2.4 GENERAL REQUIREMENTS
2.5 INSURANCE AND WARRANTIES
2.6 PAYMENT STRUCTURE
2.7 PRICING
SECTION 3 – PERFORMANCE MATRIX
SECTION 4 – CONTRACT MANAGEMENT
4.1 COMMUNICATION PLAN
4.2 JOINT VENTURE
SECTION 5 – SUPPLEMENTAL DOCUMENTATION
SECTION 6 – CONTRACT
6.1 NEGOITATIONS
6.2 ISSUANCE OF CONTRACT
6.3 COOPERATIVE USE
6.4 LIABILITY
SECTION 7 – INQUIRES AND SUBMISSION INSTRUCTIONS
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
SECTION 8 – TERMS AND CONDITIONS
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
SCHEDULE AND ACCESS INFORMATION
Schedule of Solicitations
Project ID | Title: ITB - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
Department: Parks and Recreation
Release Date: May 13, 2026 @ 10:00am
Pre-Bid Walk-Thru Meeting
May 21, 2026
- Reservoir Park; 8321 Reservoir Park Rd.; Little Rock, AR at 10:00 A.M at the ballfield parking lot.
- Murray Park; 5900 Rebsamen Park Rd.; Little Rock, AR at 2:30 P.M. at sand volleyball parking lot.
Vendor Questions Close Deadline:
June 3, 2026, 10:00am
Close Date: June 10, 2026 @ 10:00am
Bid Opening Information (Optional)
Bid Opening MS Teams
Date: 06/10/2026 Time: 10:15 A.M., Central Time
Web Link: ITB - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County - Bid Reading | Meeting-Join | Microsoft Teams
Meeting ID: 269 138 240 555 444
Passcode: yB3ti3Cz
Dial-In: +1 972-371-0918,164046306# United States, Dallas
Phone Confer. ID: 186 856 842#
Resources
Business Contact Little Rock Business Portal | City of Little Rock
Procurement Purchasing Division | City of Little Rock
LRPROCURE
powered by EUNA littlerock.bonfirehub.com https://teams.microsoft.com/l/meetup-join/19%3ameeting_YjM0NTQyMTUtOTExOC00OTc2LTlhMzItZWZlMmZkMmU3MzI3%40thread.v2/0?context=%7b%22Tid%22%3a%2284d336e2-3cb3-4ee8-91ca-5e4f107776ce%22%2c%22Oid%22%3a%220482e7ca-b0e2-4a95-9ca7-449438c919bf%22%7d https://teams.microsoft.com/l/meetup-join/19%3ameeting_YjM0NTQyMTUtOTExOC00OTc2LTlhMzItZWZlMmZkMmU3MzI3%40thread.v2/0?context=%7b%22Tid%22%3a%2284d336e2-3cb3-4ee8-91ca-5e4f107776ce%22%2c%22Oid%22%3a%220482e7ca-b0e2-4a95-9ca7-449438c919bf%22%7d tel:+19723710918,,164046306 https://www.littlerock.gov/business/little-rock-business-portal/ https://www.littlerock.gov/city-administration/city-departments/finance/divisions/procurement/ https://littlerock.bonfirehub.com/portal/?tab=openOpportunities
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
Israel Boycott Restriction Confirmation
By submitting a formal proposal to this Bid Solicitation, a Prospective Vendor agrees and certifies that they do not boycott Israel, and if selected will not boycott Israel during the aggregate term of the contract. Vendor must attach a signed copy of the Combined Certification for Contracting with the City of Little Rock form to the proposal submission.
Boycott of the Energy, Fossil Fuel, Firearms, and AMO Industries
By submitting a formal proposal to this Bid Solicitation, a Prospective Vendor agrees and certifies that it does not boycott the energy, fossil fuel, firearms, and ammunition industries and will not boycott the energy, fossil fuel, firearms, and ammunition industries during the term of the contract.
Vendor must attach a signed copy of the Combined Certification for Contracting with the City of Little Rock form to the proposal submission.
Vendors must submit responses to this request online at LRProcure on or before the designated due date and time.
Responses should comply with all requirements stated in this bid solicitation. The Vendor is required to be both responsive and responsible as per the terms of this bid. If any conflict is identified in key terms (such as the quantity or type of work to be performed), the City of Little Rock reserves the right to disqualify the Vendor's response at its sole discretion.
The City reserves the right to revise the bid submission deadline. If the City needs to make changes or revisions, an addendum will be available on City of Little Rock bid portal under Public Notices.
The City has worked hard to make sure this request is correct, but it is up to the Bidder to check the proposal carefully because the City and its team are not responsible if there are mistakes or missing information. The responsibility for determining the full extent of the exposure to risk and verifying all information herein shall rest solely on those parties’ making proposals. The City, its representatives, and its agents shall not be responsible for any error or omission in this ITB, nor shall they be responsible for any Vendors or representatives' failure to verify the information herein and to determine the full extent of that exposure.
3 a http://www.littlerock.bonfire.hub.com/
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
SECTION 1 – GENERAL INFORMATION
1.1 PURPOSE
The City of Little Rock has issued this Invitation to Bid (ITB) to businesses authorized in the State of Arkansas and qualified to provide the requested service(s) outlined in this bid document.
Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
1.2 BACKGROUND INFORMATION
Little Rock is the State Capital and the largest city in Arkansas. It was chartered in 1835 and is in the central part of the state, approximately 135 miles west of Memphis, Tennessee. The city has a population of 202,591 according to the 2020 census certified by the Arkansas State Treasurer. The 2026 operating budget revenues as approved by Ordinance No. 22079 are $350,389,573 including the General Fund revenue budget of $271,999,104.
It is also a major cultural, economic, and governmental center in central Arkansas. Several cultural institutions are in Little Rock, such as the Arkansas Museum of Fine Arts, the Arkansas Repertory Theatre, the Arkansas Symphony Orchestra, The Museum of Discovery, William J. Clinton Presidential Library & Museum, and the Mosaic Templars Cultural Center, including a diverse array of outdoor recreational opportunities.
1.3 DEFINITION OF REQUIREMENT
A. The words “must” and “shall” signify a requirement of this solicitation and that Bidder’s agreement to and compliance with that item is mandatory.
B. Exceptions taken to any requirement in this solicitation, whether submitted in the Vendor’s response or in subsequent correspondence, may cause the Responder’s response to be disqualified.
C. Bidders may request exceptions to non-mandatory items. Bidder must clearly explain the requested exception and should reference the specific solicitation item number to which the exception applies.
1.4 DEFINITIONS OF TERMS
A. The City has made every effort to use industry-accepted terminology in this bid solicitation and will attempt further to clarify any point of an item in question as indicated in the Clarification and Discussion of Proposal.
B. “Best Interests” used herein means practicing economical, professionalism, and a firm commitment to the publicly stated goals of the City
C. “Bid Opening Meeting” is the formal process in which sealed bids are opened and the contents are revealed to all Bidders and the public (optional attendance).
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
D. “Commodity Code” is the standardized system of numbers used to identify goods and services being purchased. The City of Little Rock utilizes the NIGP Code.
E. “City” means the City of Little Rock, Arkansas. When the term “City” is used herein to reference any obligation of the City under a contract that results from this solicitation.
F. “Public Notice” is the EUNA bulletin board where the City can issue changes or new information about a project. Vendors can find this in the [Messages] section titled “Public Notices.” Vendors who have viewed a project will receive an email notification when a new public notice is posted.
G. “Prospective Vendor” means a person who submits a bid in response to this solicitation.
H. “Responsible bid” means a Vendor response that has the capability in all respects to fully perform the contract requirements and the integrity and reliability that will assure good faith performance.
I. “Responsive bid” A bid solicitation that is deemed to meet all the requirements set forward in the bid solicitation such as but not limited to bid instructions, technical requirements, general requirements, acceptance of terms and conditions, and provide complete information.
J. “Notice of Award” is the written notice of the acceptance of a bid from the City to the successful Vendor.
K. “Notice to Proceed” is written communication issued by the City to the contractor authorizing them to proceed with the work and establishing the date of commencement of the work.
L. “Specifications" A part of the contract documents consisting of written descriptions of a technical nature of materials, equipment, construction systems, standards, and workmanship.
M. “Supplementary Conditions” are modifications to adapt the specific requirements of the project and that may be imposed by applicable federal, state, and local laws.
N. “Work” is all labor necessary to produce the construction required by the contract documents, and all materials and equipment incorporated or to be incorporated in the project. The contractor shall, if required, furnish satisfactory evidence as to the kind and quality of materials.
O. “Written Notice” is any notice to any party relative to any part of this Agreement shall be in writing and considered delivered and the service thereof completed, when posted by certified or registered mail to the said party or his authorized representative.
P. “Vendor” means a person who sells or contracts to sell commodities and/or services.
Q. The words “Responder,” “Bidder,” and “Vendor” are used synonymously in this document.
R. The terms “Invitation to Bid,” “ITB,” and “Solicitation” are used synonymously in this document.
S. The terms “bid,” “response,” and "submission" are used synonymously in this document.
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
1.5 RESPONSE DOCUMENTS
The Bidder’s responsive/responsible proposal must be submitted thru LRPROCURE Bid Opportunities Portal on or before the closing date and time. Other documents and/or information required must be attached to bid solicitation upon submission.
1.6 NONCOLLUSION
Bidder shall represent and warrant that in connection with a response to this solicitation:
A. The Bidder has not been a party to any collusion among Responder(s) in the restraint of freedom of competition by agreement to bid at a fixed price or to refrain from bidding.
B. The Bidder has not been a party to any collusion with any official or employee of the City of Little Rock as to quantity, quality, or price in the prospective contract or any other terms of said prospective contract.
C. The Bidder has not been a party in any discussion between Bidders and any official of City concerning the exchange of money or other things of value for special consideration in the letting of a contract.
D. Bidder's failure to disclose such a relationship may result in one of the following:
1. The City’s rejection of the Responder's response.
2. The City’s cancellation of any resultant contract.
1.7 PROPRIETARY INFORMATION
A. Response documents pertaining to this solicitation will become the property of the City of Little Rock and shall be subject to the Arkansas Freedom of Information Act (FOIA).
1.2 ISRAEL BOYCOTT NOTICE
A. Pursuant to Arkansas Code Annotated § 25-1-503, a public entity shall not enter into a contract valued at $1,000 or greater with a company unless the contract includes a written certification that the person or company is not currently engaged in and agrees for the duration of the contract not to engage in, a boycott of Israel.
B. Vendor's signature on the Combined Certification for Contracting with the City of Little Rock form shall represent and warrant they do not boycott Israel and will not boycott Israel during the remaining aggregate term of the contract.
1.9 BOYCOTT OF THE ENERGY, FOSSIL FUEL, FIREARMS, AND AMO INDUSTRIES
Pursuant to Arkansas Code Annotated § 25-1-1002, a public entity shall not enter into a contract valued at $1,000 or greater with a company unless the contract includes a written certification that the person or company is not
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County currently engaged in and agrees for the duration of the contract not to engage in a boycott of the energy, fossil fuel, firearms, and ammunition industries. The signed Combined Certification for Contracting with the City of Little Rock form shall represent the Bidder’s compliance.
1.10 REQUIREMENT OF ADDENDUM
This solicitation shall be modified only by an addendum written and authorized by the City.
1.1 PAST PERFORMANCE
A Vendor's past performance with the City may be used to determine if the Bidder is “responsible”. Responses submitted by the Bidder determined to be non-responsible shall be disqualified.
SECTION 2 – PROJECT SCOPE OF SERVICES
2.1 GOAL
To plant trees and saplings through contracted services with one (1) year of watering and warranty of trees at Reservoir and Murray Parks. The work will involve site preparation for planting, including invasive plant species removal and ground preparation for 7,550 trees and saplings. The planting installation of 7,100 mixed species bare root seedlings and 450 semi-mature three (3) inch caliper trees, maintenance and monitoring for one (1) year post planting to ensure a minimum 90% survival rate through 2027.
2.2 TERMS OF AWARD
A. The bid shall be awarded on an “all or none basis,” to the lowest qualified bidder who meets all specified requirements, and who has the absolute capability to provide the required services. Responses to this bid solicitation will be used by the City of Little Rock to determine if the vendor has the appropriate experience, licensures, and qualifications to be considered for the project.
B. The Vendor must have a license to operate in the State of Arkansas.
C. The City of Little Rock Treasury Management Division will determine validity of all business licenses.
D. For more information regarding business licenses requirements, contact the Treasury Division | City of Little Rock.
E. The City reserves the right to reject all bids and to waive any informality or irregularity in any bid.
F. Bidder must attach a signed copy of the Combined Certification for Contracting with the City of Little Rock form to the bid submission.
2.3 MINIMUM QUALIFICATIONS
https://www.littlerock.gov/city-administration/city-departments/finance/divisions/treasury/ https://www.littlerock.gov/city-administration/city-departments/finance/divisions/treasury/
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
Qualified bidders must submit a Statement of Vendor’s Qualifications responding to ALL the following questions.
The responses provided must be clear and comprehensive. The statement shall be submitted in the form of a PDF attachment with your bid. The bidder may provide supplemental information, if deemed necessary.
A. Name of Bidder B. Mailing Address (if more than one office, identify primary office responsible for bid) C. Telephone and fax numbers.
D. Email address and contact information attached.
E. Date when organization was formed.
F. If incorporated, what year did you incorporate?
G. How many years have you engaged in the contracting business under your present firm or trade name?
H. Detail the background and experience of the principal members of your organization, including the officers.
I. What are your contracts on hand? Provide a schedule of contracts and anticipated date(s) of completion.
J. Describe your firm’s qualifications and character of work.
K. Have you ever failed to successfully and/or satisfactorily complete any work awarded to you?
L. Have you ever been in default on a contract? If so, where, and why?
M. For the past five (5) years have your firm had any judgements filed against it for failure to pay materials suppliers, any damages to property or any other reason under contract? If so, please provide a list of judgments and explanations, if applicable.
N. For the past five (5) years have your firm had any liens, judgements, or certificates of indebtedness for failure to pay taxes or workers’ compensation insurance? If so, please provide a list of any liens, judgements, or certificate of indebtedness and explanations, if applicable.
O. Upon request, can you provide any other information that may be required by the City of Little Rock?
2.4 PROJECT SPECIFIC REQUIREMENTS
A. Proof of experience in tree and sapling planting, monitoring and care, invasive species removal, site preparation, and/or groundwork.
B. Proof of SAM registration and able to bid on and get paid for federal contracts or to receive federal funds.
C. Minimum three (3) years’ experience in tree and sapling planting, monitoring and care, invasive plant species removal, site preparation, groundwork for planting, ecological restoration, reforestation, or medium to large scale native planting projects.
D. Experience in invasive species removal using mechanical and herbicide methods in Arkansas or similar ecosystems.
E. Proof of valid pesticide applicator license, and/or applicable valid herbicide license.
F. Demonstrate ability to conduct multi-year monitoring and reporting.
G. Cover letter: Explain why your organization is the best choice for this project. State your understanding of the work to be completed and your ability to be successful.
2.5 GENERAL REQUIREMENTS
A. All aspects of the project must meet current Federal ADA Regulations and Standards.
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
B. Vendors shall be in compliance with the requirement of Act 150 of 1965 of the State of Arkansas, effective June 3, 1965, (codified as amended at Ark. Code Ann. §§ 17-25-301 through 17-25-316), which is the current Arkansas State Licensing Law for Contractors. The Vendor shall indicate on the bid form the current license number as issued by the applicable licensing entity.
C. The Vendor shall agree to commence work under this contract with 10 calendar days after they receive the written “Notice to Proceed” of the City and to fully complete the project within 180 consecutive calendar days thereafter as stipulated in the specifications.
D. It is expressly agreed that Contractor is acting as an independent contractor in performing the Work described herein.
2.6 SCOPE OF WORK
A. To plant trees and saplings through contracted services with one-year of watering and warranty of trees at Reservoir and Murray parks. Installation of 7,550 trees and saplings, 7,100 mixed-species bare root seedlings and 450 semi-mature 3-inch caliper trees, (a mix of 102 White Oak, 102 Red Oak, 96 Hickory, 78 Walnut and 72 Eastern Redbud).
B. Procure and plant approximately 7,100 mixed-species bare root native seedlings from an approved provider.
C. Procure and plant approximately 450 semi-mature 3-inch caliper trees as noted above from an approved provider.
D. Planting density shall be approximately 200 seedlings per acre.
E. Planting for seedlings and semi-mature trees shall follow the planting map provided by the City for the location of plantings in Reservoir Park and Murray Park.
F. Maintenance and monitoring for post planting to ensure a minimum 90% survival rate through 2027.
G. Vendor shall report to the designated LR Parks department person-in-charge to ensure proper tree and seedling planting, monitoring and care, invasive species removal, site preparation and/or groundwork and should have previous experience with similar projects.
H. Contractor shall conduct invasive species removal using mechanical and chemical methods consistent with the Arkansas Natural Heritage’s Commission (ANHC) vegetation management standards.
I. Approved herbicides used in invasive species removal must be used in suitable weather conditions.
J. All vehicles and equipment utilized for contracted activities entering tree planting areas shall be cleaned prior to site entry.
K. Any equipment utilized by the contractor must avoid rutting or soil damage.
L. Contractor shall perform ground prep such as mowing or light grading as needed to ensure optimum conditions for planting.
M. For monitoring and maintenance, provide quarterly treatment for seedling and trees as needed to keep the area free of new invasive species and competition that reduces survival rates.
N. Submit quarterly reports on survival rates, if survival rates falls below target thresholds, provide recommendations for interventions for the City.
O. Report habitat improvements and invasive species reoccurrence in bi-annual reports.
P. Community engagement is not required but is preferred and option for planting events that recruit volunteer engagement and education.
Q. Prior to issuing the notice to proceed to the Contractor, the City of Little Rock will hold a pre-work meeting with the Contractor with the City’s assigned Project Manager and other necessary City staff.
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
2.6 INSURANCE AND WARRANTIES
The Vendor shall carry the following insurances throughout the term of the contract and any extension thereof.
Prior to award of a resulting contract, the Vendor must provide a Certificate of Insurance naming the City of Little Rock as additional insured.
Workmen’s Compensation (statutory requirements) Comprehensive General Liability – one million dollars ($1,000,000) Personal Injury – one million dollars ($1,000,000) Property Damage and other liabilities – one million dollars ($1,000,000)
2.7 PAYMENT STRUCTURE
A. The Vendor shall submit all invoices resulting from contract purchase order to the City of Little Rock’s Accounts
Payable Division, Department of Finance, Room 315, 500 West Markham, Little Rock, AR 72201 at:
accountspayable@littlerock.gov. Email invoice preferred.
B. The City follows a standard thirty (30) day net terms.
2.8 PRICING
A. Any cost not identified by the successful Vendor but subsequently incurred in order to achieve successful operation shall be borne by the Vendor.
B. To allow time to evaluate responses, prices shall be valid for ninety (90) days following the bid opening.
C. Pricing shall include all associated costs. The City will not pay any cost not listed in the Vendor’s price proposal—unless the City agrees in writing—even if it’s later required for services, equipment, or service quality.
D. The City should receive any discounts offered by, or available to the Vendor. For term contracts the beginning date for computing discounts will be the date of invoice or the date of delivery and acceptance, whichever is later.
E. Prices quoted are to be net prices. If the Vendor makes an error in extending total prices, the City may accept the lesser amount whether reflected by extension or by the correct multiple of the unit price.
F. Any prices in the response have been arrived at without collusion.
G. All bid pricing shall be quoted in U.S. dollars and cents ($).
H. Vendor shall provide a bid or cost for completing the required tree and sapling planting work of site preparations, procuring, planting, maintenance and reporting for Reservoir Park.
mailto:accountspayable@littlerock.gov
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
I. Vendor shall provide a bid or cost for completing the required tree and sapling planting work of site preparations, procuring, planting, maintenance and reporting for Murray Park.
J. Vendor must provide the most up to date const information available there is a change in rates and to ensure the new price for services is reasonable as required by 2 CFR 200.324(a) & 404.
SECTION 3 – PERFORMANCE MATRIX
The City seeks to collaborate with the Vendor and other stakeholders to enhance accountability and contract management, improve results, and adjust the delivery of products and/or services based on learning what works.
Metric Data Source Data Frequency Responsibility Review Cadence
1. Did vendor successfully procure and install the required number of saplings and semi-mature trees in accordance with project requirements?
Department Records Quarterly Vendor Quarterly
2. Did the vendor assess implementation of post-planting, quarterly treatments, site prep as needed and invasive species control by mechanical or chemical standards?
Department Records Quarterly Vendor Quarterly
3. Did the vendor submit bi-annual assessments on survival rates, habitat improvements, invasive species recurrence and/or recommendations?
Department Records Quarterly Vendor Quarterly
4. Did the vendor comply with site protection, environmental
Department Records Quarterly Vendor Quarterly
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County standards, equipment cleaning, avoidance of soil rutting, and execution of ground preparation?
Vendor Performance Report (Ad-hoc)
Vendor Performance Review Form
As Needed – At Least Once Per Contract
City of Little Rock Procurement Division
Annually
Vendor Performance Review
Annually City of Little Rock Procurement Division
Annually
SECTION 4 – CONTRACT MANAGEMENT
4.1 COMMUNICATION PLAN
A. To manage this contract and the goals outlined in sections herein, the City will collect quarterly performance data and regularly discuss performance metrics with selected Vendors.
B. The Vendor update meeting shall occur monthly at an agreed-upon time and date. Upon mutual agreement, the parties may move this meeting, if necessary to avoid scheduling conflicts, holidays, or similar occurrences. Any changes or cancellations to a meeting shall be communicated at least twenty-four (24) hours in advance.
4.2 JOINT VENTURE
A. A joint proposal submitted by two or more Vendors is acceptable.
B. In the event of a joint venture, documentation must be submitted with the proposals identifying all participating business entities.
C. Prior to the award, a binding agreement between the participants must be provided. The City will recognize both companies as one entity.
D. The City shall have a single point of operational contact with the entity that is formed pursuant to this provision.
E. Two companies with the same physical address or with a single point of operational contact will be considered one entity.
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
SECTION 5 – SUPPLEMENTAL DOCUMENTATION
A. City of Little Rock Ordinance 20,482 § 1, 10-3-11, Sections 18.51 – 18.53:
https://library.municode.com/ar/little_rock/codes/code_of_ordinances?nodeId=COOR_CH18MIPROF_AR
TIIOFINPUPEOR
B. Act 1068 – “To Repeal The Arkansas Prevailing Wage Law; And To Provide Flexibility To Cities And Counties For Capital Construction Projects; And To Declare An Emergency:
https://www.arkleg.state.ar.us/Bills/Detail?ddBienniumSession=2017%2F2017R&measureno=sb601
SECTION 6 – CONTRACT
6.1 NEGOITATIONS
A. If the City chooses, negotiations may be conducted with the highest-ranking prospective Vendor. Negotiations are conducted at the sole discretion of the City.
B. If negotiations fail to result in a contract, the City may begin the negotiation process with the next highest ranking prospective Vendor. The negotiation process may be repeated until the anticipated successful Vendor has been determined, or until such a time the City decides not to move forward with an award.
6.2 ISSUANCE OF CONTRACT
A. Any resultant contract of this bid solicitation is subject to City approval processes which may include board review.
6.3 COOPERATIVE USE
A. The City of Little Rock, as the issuing office for this solicitation, shall be the leading agency for this contract.
Other governmental entities may participate in any contract resulting from this solicitation that falls under its scope of work throughout the life of the contract.
B. The Vendor must agree to offer the same pricing, terms, and conditions to participating governmental entities as outlined in this solicitation.
6.4 LIABILITY
The City of Little Rock shall not assume liability or obligation on behalf of any other governmental entity that may use any contract resulting from this solicitation. All purchases and payment transactions shall be made directly between the Vendor and the requesting entity
SECTION 7 – INQUIRES AND SUBMISSION INSTRUCTIONS
Bid submissions must be submitted electronically via LRPROCURE powered EUNA Brand Solutions prior to the bid closing data. Bid Closing Date is listed under “Important Events.
https://library.municode.com/ar/little_rock/codes/code_of_ordinances?nodeId=COOR_CH18MIPROF_ARTIIOFINPUPEOR https://library.municode.com/ar/little_rock/codes/code_of_ordinances?nodeId=COOR_CH18MIPROF_ARTIIOFINPUPEOR https://www.arkleg.state.ar.us/Bills/Detail?ddBienniumSession=2017%2F2017R&measureno=sb601 https://littlerock.bonfirehub.com/
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County
Any questions or inquiries regarding a bid solicitation must be submitted prior to the Questions Due Date.
Questions Due Date is listed under “Important Events.” Once this date has passed, no further communication shall occur between City of Little Rock and suppliers or service providers.
For any system-related questions, technical errors and/or help, please contact EUNA Technical Support or using the Help Button or at support@gobonfire.com Mon-Fri 8:00am-8:00pm EST.
Bids Submissions may be revised and resubmitted prior to the Bid Closing Date. Only submitted submissions will be considered.
SECTION 8 – TERMS AND CONDITIONS
All prospective Vendors who submit a proposal agree to be bound by the City of Little Rock Standard Terms and Conditions for Vendors and the online EUNA Terms & Conditions.
8.1 GENERAL FEDERAL REQUIREMENTS
Federal regulations applicable to this award include, without limitation, the following:
A. Uniform Administrative Requirements ("UGG"). Cost Principles, and Audit Requirements for Federal
Awards, 2 CFR Part 200, other than such provisions as EPA may determine are inapplicable to this Award including adherence to the accounting principles and procedures required therein, use adequate internal controls, and maintain necessary source documentation for all costs incurred.
B. Authorizing Program Statute. This grant was created by Section 60114 of the Inflation Reduction Act, Climate
Pollution Reduction Grants, 42 U.S. Code § 7437 (or Public Law 117- 169, title VI, Aug. 16, 2022, 136 Stat.
2076), which amended the Clean Air Act (CAA) by creating Section 137 for Greenhouse Gas Air Pollution Plans and Implementation Grants; and
C. EPA General Terms and Conditions. The current Environmental Protection Agency (EPA) General Terms and
Conditions available at: https://www.epa.gov/system/files/documents/2025- 10/fy_2026_epa_general_terms_and_conditions_effective_october_1_2025_or_later.pdf and These terms and conditions are in addition to the assurances and certifications made as part of the award and the terms, conditions, or restrictions cited throughout the award; and The EPA Repository for general terms and conditions by year can be found at https://www.epa.gov/grants/grant-terms-and-conditions
D. Program guidance is available at: https://www.epa.gov/inflation-reduction-act/climate-pollution-reduction-grants
E. Flow Down Provisions See https://www.epa.gov/system/files/documents/2023-11/external-clauses-2023-11- 01.pdfor most recently revised version of EPA's Solicitation Clauses (11/01/2023) for Information on Requirements that Pass-Through Entities must 'Flow Down' to Subrecipients, applicable to contractors and subcontractors.
8.2 CONTRACTOR AND SUBCONTRACTOR FEDERAL REQUIREMENTS
The City has worked hard to make sure this request is correct, but it is up to you to check everything carefully because the City and its team are not responsible if there are mistakes or missing information. The responsibility for determining the full extent of the exposure to risk and verifying all information herein shall rest solely on those parties’ making proposals. The City, its mailto:support@gobonfire.com https://www.littlerock.gov/media/22981/standards-and-conditions-2025.pdf https://www.littlerock.gov/media/22981/standards-and-conditions-2025.pdf https://www.bonfire.com/terms-and-conditions/
Invitation to Bid - 235927 - Job # 02F75801 - Green Network Project - Reservoir and Murray Park - Pulaski County representatives, and its agents shall not be responsible for any error or omission in this ITB, nor shall they be responsible for any Bidders or representatives' failure to verify the information herein and to determine the full extent of that exposure. It is the bidder’s responsibility to check the Little Rock website for addenda to this Invitation to Bid. All addenda so issued shall become part of the Contract Documents.
A. The contractor acknowledges that by responding to this bid it is an opportunity funded by an Environmental Protection Agency assistance agreement (grant) under Federal Award Identification Number 02F75801, the contractor agrees to comply with the terms and conditions in accordance with 29 CFR 5.5, if this contract is for activities covered under Davis-Bacon and Related Acts (DBRA) and exceeds (or will exceed) $2,000.
Definitions for many of the terms used are provided in 29 CFR 5.2.
• DBRA Requirements for Contractors and Subcontractors Under EPA Grants (pdf) (291.78 KB)
• DBRA Requirements for Contracts in Excess of $100,000 Under EPA Grants (pdf) (202.61 KB)
B. Retain all records relating to inspection and certification, the Contractor's billing statements, and any other files necessary to document the performance and completion of the work in accordance with requirements of 2 CFR Part 200 29 CFR 5.5.
C. Compliance with Executive Order 14332 and it’s amendments to 2 CFR 200.340(a).
D. Compliance in reporting and participation by the contractor or subcontractor with Disadvantaged Business Enterprises in the United States Environmental Protection Program 40 CFR Part 33.
F. As provided in 2 CFR 200.319(b), “In order to ensure objective contractor performance and eliminate unfair competitive advantage, contractors that develop or draft specifications, requirements, statements of work, or invitations for bids or requests for proposals must be excluded from competing for such procurements.”
G. Byrd Anti-Lobbying Amendment (31 U.S.C. 1352)—Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352.
Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the non-Federal award.
https://www.ecfr.gov/current/title-29/section-5.5 https://www.ecfr.gov/current/title-29/section-5.2 https://www.epa.gov/system/files/documents/2023-10/dbra_requirements_for_contractors_and_subcontractors_under_epa_grants.pdf https://www.epa.gov/system/files/documents/2023-10/dbra_requirements_for_contracts_in_excess_of_100_000_under_epa_grants.pdf https://www.ecfr.gov/current/title-29/section-5.5 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.federalregister.gov%2Fdocuments%2F2025%2F08%2F12%2F2025-15344%2Fimproving-oversight-of-federal-grantmaking&data=05%7C02%7Cmlefevre%40littlerock.gov%7Ced7208f355d543761c6908de90ff0bce%7C84d336e23cb34ee891ca5e4f107776ce%7C0%7C0%7C639107622698273537%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=aJi75gwQOHi0aqgs%2BdBgQkki2gnZuG%2BW9KrDIJr%2FwQw%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.federalregister.gov%2Fdocuments%2F2025%2F08%2F12%2F2025-15344%2Fimproving-oversight-of-federal-grantmaking&data=05%7C02%7Cmlefevre%40littlerock.gov%7Ced7208f355d543761c6908de90ff0bce%7C84d336e23cb34ee891ca5e4f107776ce%7C0%7C0%7C639107622698287472%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=EKoXLll1cj0gwtdq2z4HvUy1AAMtChxt%2FoTfUPjlWgo%3D&reserved=0 https://www.ecfr.gov/current/title-40/chapter-I/subchapter-B/part-33 https://www.govinfo.gov/link/uscode/31/1352 https://www.govinfo.gov/link/uscode/31/1352
| SCHEDULE AND ACCESS INFORMATION |
| SECTION 1 – GENERAL INFORMATION |
| 1.1 PURPOSE |
| 1.2 BACKGROUND INFORMATION |
| 1.3 DEFINITION OF REQUIREMENT |
| 1.4 DEFINITIONS OF TERMS |
| 1.5 RESPONSE DOCUMENTS |
| 1.6 NONCOLLUSION |
| 1.7 PROPRIETARY INFORMATION |
| 1.2 ISRAEL BOYCOTT NOTICE |
| 1.9 BOYCOTT OF THE ENERGY, FOSSIL FUEL, FIREARMS, AND AMO INDUSTRIES |
| 1.10 REQUIREMENT OF ADDENDUM |
| 1.1 PAST PERFORMANCE |
| SECTION 2 – PROJECT SCOPE OF SERVICES |
| 2.1 GOAL |
| 2.2 TERMS OF AWARD |
| 2.3 MINIMUM QUALIFICATIONS |
| 2.4 PROJECT SPECIFIC REQUIREMENTS |
| 2.6 INSURANCE AND WARRANTIES |
| 2.7 PAYMENT STRUCTURE |
| 2.8 PRICING |
| SECTION 3 – PERFORMANCE MATRIX |
| SECTION 4 – CONTRACT MANAGEMENT |
| 4.1 COMMUNICATION PLAN |
| 4.2 JOINT VENTURE |
| SECTION 5 – SUPPLEMENTAL DOCUMENTATION |
| SECTION 6 – CONTRACT |
| 6.1 NEGOITATIONS |
| 6.2 ISSUANCE OF CONTRACT |
| 6.3 COOPERATIVE USE |
| 6.4 LIABILITY |
| SECTION 7 – INQUIRES AND SUBMISSION INSTRUCTIONS |
| SECTION 8 – TERMS AND CONDITIONS |