6-CWU--L-2027-1 - Bid Form.docx

DOCX document 104 KB Posted

Attached to
CWU-L-2027-1/: Work Order Contracts for Construction, Renovation and Repair
Solicitation number
US.262366
Issued by
Clearfield County, Pennsylvania

About this file

This is a Bid Form document for Commonwealth University's State System of Higher Education, specifically for the Lock Haven Campus, which solicits multiple-award work order contracts for construction, renovation, and repair services across eleven trade disciplines. The contract encompasses General Construction, HVAC, Plumbing, Electrical, Painting, Roofing, Concrete, Masonry, Sitework, Asphalt and Concrete Paving, and Boiler Specialty work. These are indefinite quantity contracts with no predetermined project scope or dollar amounts; individual work orders will be issued as needed for emergency repairs, maintenance, renovations, and miscellaneous construction projects under $100,000 per work order. A mandatory pre-bid conference with site visit is scheduled for November 19, 2026, at 11:00 AM at East Campus Science Center, Room 215, Lock Haven Campus. Electronic bids are due by 1:00 PM EDT on December 15, 2026, through PennBid. Bidders must be located within a 75-mile radius (1.5-hour drive) of the University to meet emergency response requirements.

The Bid Form establishes hourly unit pricing matrices for prevailing wage and non-prevailing wage labor classifications, along with daily per diem rates for equipment rental. Material costs are subject to a 10% markup, and all unit prices must include labor burdens, overhead, and profit. For the Asphalt and Concrete Paving contract (CWU-L-2027/1.10), pricing is based on the PADOT ECMS Asphalt Cement Index at $713.00 per ton (November 2026, Zone 2, District 2). The Commonwealth University System may award contracts to multiple firms with the lowest base bids. Unit prices quoted become contractual pricing for all subsequent work orders, and the System reserves the right to increase or decrease quantities without adjusting unit prices. Manual bid forms take precedence over electronic submissions in PennBid. Subcontracted work requires prior approval, and contractors may be required to submit supporting documentation for cost substantiation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMONWEALTH UNIVERSITY

STATE SYSTEM OF HIGHER EDUCATION

COMMONWEALTH OF PENNSYLVANIA

BID FORM

Note: The Bid Form pricing information is included with the Bidding Documents for Reference. Bidders shall complete the attached manual bid form and electronic bid form within PennBid (“Prepare Your Submission” tab), inclusive of all pricing items and required supporting documents as identified. The manual bid form pricing submission information shall take precedent.

BID FOR:

Contract(s):CWU-L-2027/1.1 – GENERAL CONSTRUCTION
CWU-L-2027/1.2 – HVAC CONSTRUCTION
CWU-L-2027/1.3 – PLUMBING CONSTRUCTION
CWU-L-2027/1.4 – ELECTRICAL CONSTRUCTION
CWU-L-2027/1.5 – PAINTING
CWU-L-2027/1.6 – ROOFING
CWU-L-2027/1.7 – CONCRETE
CWU-L-2027/1.8 – MASONRY
CWU-L-2027/1.9 – SITEWORK
CWU-L-2027/1.10 – ASPHALT AND CONCRETE PAVING
CWU-L-2027/1.11 – BOILER SPECIALTY

Title of Project Work Order Contracts for Construction, Renovation, and Repair

Location Commonwealth University – Lock Haven Campus / Lock Haven, PA

BID FROM:

Firm Name

Federal ID No.

Address

Telephone

Fax

E-mail

Name of Contact for this Bid

The Proposer agrees to perform the work specified in the Contract Documents, under the terms and conditions specified in the Contract Documents, without exceptions or substitutions, and under any required additional certifications and conditions attached hereto, for the prices proposed on this Bid Form.

The Proposer additionally certifies that requirements in the Instructions to Bidders are met.

The Proposer acknowledges the Addenda hereinafter enumerated, which have been issued during the period of bidding, and agrees that contents of said Addenda shall become incorporated into the Contract.

Addenda No. Date Issued

The estimated quantities listed on this Bid Form are estimated and approximate, and are presented solely for the purpose of determining the Total Base Bid. The System may increase or decrease the quantities to be performed without any adjustment in the unit prices quoted on this Bid Form.

If accepted by the System, the unit prices quoted on this Bid Form will become the Contractual unit prices, and they shall be the only payment that the Contractor will receive for completed Work. Unless otherwise called for, all unit prices must be fully encumbered to include all labor burdens, and must include overhead and profit.

In order to receive payment for bid items consisting of a percent markup, instead of a unit price, the Contractor may be required to provide supporting documentation of the actual cost of materials, equipment, and/or subcontractors.

Any classification (labor, materials, and/or equipment) not included in the listed unit prices on the Bid Form, but required under an individual work order, shall be negotiated with the System. The Contractor may be required to submit supporting documentation.

Subcontracted work is subject to prior approval by the System.

The unit prices and extended unit prices as called for should be submitted in the spaces provided below. An omission of prices for any unit-price item called for will be sufficient cause for rejection of the bid as being incomplete and non-responsive.

Specification Section 012200, Unit Prices, provides detailed descriptions of bid items.

Abbreviations:

CY = Cubic Yard EA = Each LF = Linear Foot SF = Square Foot SY = Square Yard

UNIT PRICE MATRIX – GENERAL CONSTRUCTION, CWU-L-2027/1.1

1. LABOR – NON-PREVAILING WAGE

Item

Labor Classification

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Bricklayer, Stone Masons, Pointers, Caulkers, Cleaners - straight time
40.0
1b.
Carpenters – Piledriver/Welder – straight time
40.0
1c.
Carpenter, Drywall Hanger, Framers, Instrument Men, Lathers, Soft Floor Layers – straight time
40.0
1d.
Cement Finishers & Plasterers – straight time
40.0
1e.
Cement Masons – straight time
40.0
1f.
General Labor – straight time
40.0
1g.
Equipment Operator – straight time
40.0
1h.
Working Foreman – straight time
40.0
1i.
Superintendent – straight time
40.0
1j.
Truck Driver – straight time
40.0
1K.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1j)
LS

2. LABOR – PREVAILING WAGE

Bid Qty. Hours
PW Rate

Unit Price Extended Price

2a.
Bricklayer, Stone Masons, Pointers, Caulkers, Cleaners - straight time
40.0
2b.
Carpenters – Piledriver/Welder – straight time
40.0
2c.
Carpenter, Drywall Hanger, Framers, Instrument Men, Lathers, Soft Floor Layers – straight time
40.0
2d.
Cement Finishers & Plasterers – straight time
40.0
2e.
Cement Masons – straight time
40.0
2f.
General Labor – straight time
40.0
2g.
Equipment Operator – straight time
40.0
2h.
Working Foreman – straight time
40.0
2i.
Superintendent – straight time
40.0
2j.
Truck Driver – straight time
40.0
2K.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2j)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Equipment Type

Bid Quantity Days
Per Diem Rate
Extended Price
4a.
Backhoe
1.0
4b.
Compact Excavator or Skid Loader
1.0
4c.
Pettibone (Up to 9,000 lb. capacity with a 44' 6" lift height)
1.0
4d.
Boom Lift (30 ft.)
1.0
4e.
Boom Lift (60 ft.)
1.0
4f.
Scissor Lift (19 ft.)
1.0
4g.
Scissor Lift (32 ft.)
1.0
4h.
Dump Truck – 10 Ton
1.0
4i.
Dump Truck – Tri-Axle
1.0
4J.
SUBTOTAL – EQUIPMENT RATES (4a thru 4i)
LS

CWU-L-2027/1.1 - BASE BID TOTAL

(Combined totals of 1K, 2K and 4J)

CWU-L-2027/1.1 - GC

BASE BID:

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – HVAC, CWU-L-2027/1.2

1. LABOR NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price

Item Price

1a.
HVAC Technician – straight time
40.0
1b.
Sheet Metal Worker – straight time
40.0
1c.
Working Foreman – straight time
40.0
1d.
Equipment Operator – straight time
40.0
1E.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1d)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate

Unit Price

Item Price

2a.
HVAC Technician – straight time
40.0
2b.
Sheet Metal Worker – straight time
40.0
2c.
Working Foreman – straight time
40.0
2d.
Equipment Operator – straight time
40.0
2E.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2d)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate

Item Price

4a.
Pettibone (Up to 9,000 lb. capacity with a 44' 6" lift height)
1.0
4b.
Boom Lift (30 ft.)
1.0
4c.
Boom Lift (60 ft.)
1.0
4d.
Scissor Lift (19 ft.)
1.0
4e.
Scissor Lift (32 ft.)
1.0
4F.
SUBTOTAL – EQUIPMENT RATES (4a thru 4e)
LS

CWU-L-2027/1.2 - BASE BID TOTAL

(Combined totals of 1E, 2E and 4F)

CWU-L-2027/1.2 - HVAC

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – PLUMBING, CWU-L-2027/1.3

1. LABOR NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price

Item Price

1a.
Plumber/Pipefitter – straight time
40.0
1b.
Working Foreman – straight time
40.0
1c.
Equipment Operator – straight time
40.0
1D.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1c)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price

Item Price

2a.
Plumber/Pipefitter – straight time
40.0
2b.
Working Foreman – straight time
40.0
2c.
Equipment Operator – straight time
40.0
2D.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2c)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate

Item Price

4a.
Pettibone (Up to 9,000 lb. capacity with a 44' 6" lift height)
1.0
4b.
Boom Lift (30 ft.)
1.0
4c.
Boom Lift (60 ft.)
1.0
4d.
Scissor Lift (19 ft.)
1.0
4e.
Scissor Lift (32 ft.)
1.0
4F.
SUBTOTAL – EQUIPMENT RATES (4a thru 4e)
LS

CWU-L-2027/1.3 - BASE BID TOTAL

(Combined totals of 1D, 2D and 4F)

CWU-L-2027/1.3 - Plumbing

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – ELECTRICAL CWU-L-2027/1.4

1. LABOR NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price

Item Price

1a.
Apprentice Electrician - straight time
40.0
1b.
Electrician - straight time
40.0
1c.
Working Foreman – straight time
40.0
1d.
Equipment Operator – straight time
40.0
1E.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1d)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price

Item Price

2a.
Apprentice Electrician - straight time
40.0
2b.
Electrician - straight time
40.0
2c.
Working Foreman – straight time
40.0
2d.
Equipment Operator – straight time
40.0
2E.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2d)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate

Item Price

4a.
Pettibone (Up to 9,000 lb. capacity with a 44' 6" lift height)
1.0
4b.
Boom Lift (30 ft.)
1.0
4c.
Boom Lift (60 ft.)
1.0
4d.
Scissor Lift (19 ft.)
1.0
4e.
Scissor Lift (32 ft.)
1.0
4f.
Bucket Truck (30 ft.)
1.0
4G.
SUBTOTAL – EQUIPMENT RATES (4a thru 4f)
LS

CWU-L-2027/1.4- BASE BID TOTAL

(Combined totals of 1E, 2E and 4G)

CWU-L-2027/1.4 - Electrical

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – PAINTING, CWU-L-2027/1.5

1. LABOR – NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Painter – straight time
40.0
1b.
Working Foreman – straight time
40.0
1C.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1b)
LS

2. LABOR – PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price
Extended Price
2a.
Painter – straight time
40.0
2b.
Working Foreman – straight time
40.0
2C.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2b)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT – not applicable

CWU-L-2027/1.5 - BASE BID TOTAL

(Combined totals of 1C and 2C)

CWU-L-2027/1.5 - Painting

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – ROOFING, CWU-L-2027/1.6

1. LABOR-NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Roofer EPDM – straight time
40.0
1b.
Roofer Shingle – straight time
40.0
1c.
Roofer Slate – straight time
40.0
1d.
Working Foreman – straight time
40.0
1e.
Equipment Operator – straight time
40.0
1f.
Truck Driver – straight time
40.0
1G.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1f)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price
Extended

Price

2a.
Roofer EPDM – straight time
40.0
2b.
Roofer Shingle – straight time
40.0
2c.
Roofer Slate – straight time
40,0
2d.
Working Foreman – straight time
40.0
2e.
Equipment Operator – straight time
40.0
2f.
Truck Driver – straight time
40.0
2G.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2f)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate
Extended Price
4a.
Boom Lift (30 ft.)
1.0
4b.
Boom Lift (60 ft.)
1.0
4c.
Scissor Lift (19 ft.)
1.0
4d.
Scissor Lift (32 ft.)
1.0
4e.
Dump Truck – 10 Ton
1.0
4f.
Dump Truck – Tri-Axle
1.0
4G.
SUBTOTAL – EQUIPMENT RATES (4a thru 4f)
LS

CWU-L-2027/1.6 - BASE BID TOTAL

(Combined totals of 1G, 2G and 4G)

CWU-L-2027/1.6 - Roofing

_________________________________________________Dollars

Written

UNIT PRICE MATRIX – CONCRETE, CWU-L-2027/1.7

1. LABOR NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Cement Finisher – straight time
40.0
1b.
General Labor – straight time
40.0
1c.
Working Foreman – straight time
40.0
1d.
Equipment Operator – straight time
40.0
1e.
Truck Driver – straight time
40.0
The following unit prices are to include all labor, equipment, materials, mark-up, overhead & profit costs for on-site installation of the following:
Bid Qty.
Cost per Unit
Extended Price
1f.
Replace Curb (per L.F.)
50
1g.
Replace Radial Curb (per L.F.)
50
1h.
Replace Sidewalk (per S.F.)
1,000
1i.
Replace Integral Curb/Sidewalk (per S.F.)
300
1j.
Replace Wheelchair Ramp (per Each)
2
1k.
Replace Steps (per (S.F.)
500
1l.
New Curb (per L.F.)
50
1m.
New Radial Curb (per L.F.)
50
1n.
New Sidewalk (per S.F.)
1,000
1o.
New Integral Curb/Sidewalk (per S.F.)
300
1p.
New Wheel Chair Ramp (per Each)
2
1q.
New Steps (per S.F.)
500
1r.
New Aluminum Railing System (per L.F.)
100
1s.
New Steel Railing System (per L.F.)
100
1t.
New 2’ x 4’ x 4’ Catch Basin (per Each)
10
1u.
New Plastic P.E. Storm Pipe – 10” (per L.F.)
100
1V.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1u)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price
Extended

Price

2a.
Cement Finisher – straight time
40.0
2b.
General Labor – straight time
40.0
2c.
Working Foreman – straight time
40.0
2d.
Equipment Operator – straight time
40,0
2e.
Truck Driver – straight time
40.0
The following unit prices are to include all labor, equipment, materials, mark-up, overhead & profit costs for on-site installation of the following:
Bid Qty.
Cost per Unit
Extended Price
2f.
Replace Curb (per L.F.)
50
2g.
Replace Radial Curb (per L.F.)
50
2h.
Replace Sidewalk (per S.F.)
1,000
2i.
Replace Integral Curb/Sidewalk (per S.F.)
300
2j.
Replace Wheelchair Ramp (per Each)
2
2k.
Replace Steps (per (S.F.)
500
2l.
New Curb (per L.F.)
50
2m.
New Radial Curb (per L.F.)
50
2n.
New Sidewalk (per S.F.)
1,000
2o.
New Integral Curb/Sidewalk (per S.F.)
300
2p.
New Wheel Chair Ramp (per Each)
2
2q.
New Steps (per S.F.)
500
2r.
New Aluminum Railing System (per L.F.)
100
2s.
New Steel Railing System (per L.F.)
100
2t.
New 2’ x 4’ x 4’ Catch Basin (per Each)
10
2u.
New Plastic P.E. Storm Pipe – 10” (per L.F.)
100
2V.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2u)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Item
Equipment Type
Bid Quantity Days
Per Diem Rate
Extended Price
4a.
Backhoe
1.0
4b
Skid Loader
1.0
4c.
Trencher
1.0
4d.
Dump Truck – 10 Ton
1.0
4e.
Dump Truck – Tri-Axle
1.0
4F.
SUBTOTAL – EQUIPMENT RATES (4a thru 4e)
LS

CWU-L-2027/1.7 - BASE BID TOTAL

(Combined totals of 1V, 2V and 4F)

CWU-L-2027/1.7- Concrete

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – MASONRY, CWU-L-2027/1.8

1. LABOR-NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Bricklayers, Stone Masons, Pointers, Caulkers,

Cleaners – straight time 40.0

1b.
General Laborer – straight time
40.0
1c.
Working Foreman – straight time
40.0
1d.
Superintendent – straight time
40.0
1e.
Equipment Operator – straight time
40.0
1f.
Truck Driver – straight time
40.0
1G.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1f)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price
Extended

Price

2a.
Bricklayers, Stone Masons, Pointers, Caulkers,

Cleaners – straight time 40.0

2b.
General Laborer – straight time
40.0
2c.
Working Foreman – straight time
40,0
2d.
Superintendent – straight time
40.0
2e.
Equipment Operator – straight time
40.0
2f.
Truck Driver – straight time
40.0
2G.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2f)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate
Extended Price
4a.
Boom Lift (30 ft.)
1.0
4b.
Boom Lift (60 ft.)
1.0
4c.
Scissor Lift (19 ft.)
1.0
4d.
Scissor Lift (32 ft.)
1.0
4e.
Dump Truck – 10 Ton
1.0
4f.
Dump Truck – Tri-Axle
1.0
4G.
SUBTOTAL – EQUIPMENT RATES (4a thru 4f)
LS

CWU-L-2027/1.8 - BASE BID TOTAL

(Combined totals of 1G, 2G and 4G)

CWU-L-2027/1.8 - Masonry

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – SITEWORK - CWU-L-2027/1.9

1. LABOR NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price

Item Price

1a.
Cement Finisher – straight time
40.0
1b.
General Labor – straight time
40.0
1c.
Working Foreman – straight time
40.0
1d.
Equipment Operator – straight time
40.0
1e.
Welder – straight time
40.0
1f.
Truck Driver – straight time
40.0
1G.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1f)
LS

2. LABOR PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price

Item Price

2a.
Cement Finisher – straight time
40.0
2b.
General Labor – straight time
40.0
2c.
Working Foreman – straight time
40.0
2d.
Equipment Operator – straight time
40.0
2e.
Welder – straight time
40.0
2f.
Truck Driver – straight time
40.0
2G.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2f)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT

Bid Quantity Days
Per Diem Rate

Item Price

4a.
Excavator (up to 20 ton)
1.0
4b.
Mini Excavator (up to 20 ton)
1.0
4c.
Skid Loader (up to 100 HP)
1.0
4d.
Backhoe (up to 100 HP)
1.0
4e.
Trencher
1.0
4f.
Trench Compactor
1.0
4g.
Dump Truck – 5 Ton
1.0
4h.
Dump Truck – 10 Ton
1.0
4i.
Dump Truck – Tri-Axle
1.0
4j.
Welding Machine
1.0
4K.
SUBTOTAL – EQUIPMENT RATES (4a thru 4j)
LS

CWU-L-2027/1.9 - BASE BID TOTAL

(Combined totals of 1G, 2G and 4K)

CWU-L-2027/1.9 - Sitework

___________________________________________________Dollars

Written

UNIT PRICE MATRIX – ASPHALT AND CONCRETE PAVING - CWU-L-2027/1.10

UNIT PRICE BASE BIDS – PREVAILING WAGE UNIT PRICE BASE BIDS

EstimatedPWExtended
Item No.DescriptionQuantityUnitUnit PricePrice
1Remove soft and yielding100CY$____________$____________
sub-grade.

2 Remove stone sub-base course.

Quantities from 1 to 100 100 CY $____________ $____________

> 100 200 CY $____________ $____________

3 Remove bituminous paving.

Quantities from 1 to 100 100 SY $____________ $____________

> 100 300 SY $____________ $____________

4 Mill bituminous paving surface.

Quantities from 1 to 100 100 SY $____________ $____________

> 100 200 SY $____________ $____________

5 New excavation.

All Quantities 50 CY $____________ $____________

6 New stone sub-base course.

Quantities from 1 to 50 50 CY $____________ $____________

> 50 100 CY $____________ $____________

7 Install new 2 ½” bituminous concrete binder course.

Quantities from 1 to 100 100 SY $____________ $____________

> 100 200 SY $____________ $____________

8 Install new 1 ½” bituminous wearing course.

Quantities from 1 to 100 100 SY $____________ $____________

> 100 300 SY $____________ $____________

EstimatedPWExtended
Item No.DescriptionQuantityUnitUnit PricePrice

9 New Asphalt Walkway. 100 SY $____________ $____________

10 Tack coat.

Quantities from 1 to 100 100 SY $____________ $____________

> 100 200 SY $____________ $____________

11 Replace Existing Concrete Curb with New Concrete Curb

50 LF $____________ $____________

12 Replace Existing Concrete Paving with New 6” Concrete Paving

300 SF $____________ $____________

13 Replace Concrete Inlet. 3 EA $____________ $____________

14 New Concrete Inlet. . 5 EA $____________ $____________

15 Recyclable Geotextile. 300 SY $____________ $____________

16 New bituminous joint sealer. 1,000 LF $_____________ $____________

17 Seal coating . 30,000 SF $_____________ $____________

18 Line Painting / Yellow. 1,000 LF $_____________ $____________

19 Line Painting / White. 1,000 LF $_____________ $____________

20 STOP line/bar, 24” x 12’ 5 EA $_____________ $____________

UNIT PRICE BASE BIDS – NON-PREVAILING WAGE UNIT PRICE BASE BIDS

EstimatedNon-PWExtended
Item No.DescriptionQuantityUnitUnit PricePrice
21Remove soft and yielding
sub-grade.20CY$____________$____________

22 Remove existing stone sub-base course.

Quantities from 1 to 100 50 CY $____________ $____________

EstimatedNon-PWExtended
Item No.DescriptionQuantityUnitUnit PricePrice

23 New stone sub-base course.

Quantities from 1 to 100 100 SY $____________ $____________

24 Pot Hole Repair 50 SY $____________ $____________

25 Asphalt Repair 100 SY $____________ $____________

26New bituminous crack filling1,000LF$_____________$____________
< 1” wide.

27 Seal coating 25,000 SF $_____________ $____________

28 Line Painting / Yellow. 1,000 LF $_____________ $____________

29 Line Painting / White. 1,000 LF $_____________ $____________

30 STOP line/bar, 24” x 12’ 5 EA $_____________ $____________

TOTAL BASE BIDS (Extended Totals Bid Items 1 through 30) CWU-L-2027/1.10 – Asphalt and Concrete Paving

_________________________________________Dollars $___________________
(WRITTEN)(FIGURES)

List the PADOT ECMS Asphalt Cement Index price upon which pricing is based: $713.00/Ton (Nov 2026 – Zone 2, District 2)

UNIT PRICE MATRIX – BOILER SPECIALTY, CWU-L-2027/1.11

1. LABOR – NON-PREVAILING WAGE

Bid Qty. Hours
Non-PW Rate

Unit Price Extended Price

1a.
Boiler Technician – straight time
40.0
1b.
Sheet Metal Worker – straight time
40.0
1c.
Working Foreman – straight time
40.0
1D.
SUBTOTAL – NON PREVAILING WAGE RATES (1a thru 1c)
LS

2. LABOR – PREVAILING WAGE

Bid Qty. Hours
PW Rate Unit Price
Extended Price
2a.
Boiler Technician – straight time
40.0
2b.
Sheet Metal Worker – straight time
40.0
2c.
Working Foreman – straight time
40.0
2D.
SUBTOTAL – PREVAILING WAGE RATES (2a thru 2c)
LS

3. MATERIAL – 10% MARKUP

4. EQUIPMENT – not applicable

CWU-L-2027/1.11 - BASE BID TOTAL

(Combined totals of 1D and 2D)

CWU-L-2027/1.11 - Boiler

___________________________________________________Dollars

Written

BIDDER'S BUSINESS CERTIFICATION

TYPE OF BUSINESS (check one of the three options below, and circle the correct entries within)

The Bidder is a Pennsylvania Corporation, LP, LLP, or LLC (circle one), organized and existing under the laws of Pennsylvania, and so is authorized to do business in Pennsylvania by the Pennsylvania Business Corporation Law of 1988, as amended.

The Bidder is a Foreign Corporation, LP, LLP, or LLC (circle one), organized and existing under the laws of the state of (enter the name of the state), and has or has not (circle one) been granted a certificate of authority, or is or is not (circle one) registered, to do business in Pennsylvania as required by the Pennsylvania Business Corporation Law of 1988, as amended.

The Bidder is an Individual, Proprietorship, Partnership, or other (circle one), trading under a fictitious or assumed name, and has or has not (circle one) registered under the Pennsylvania Fictitious Names Act of 1982, as amended.

RESIDENCY (complete one of the two options below)

Does your firm have a street address in Pennsylvania at which it was transacting business when the Notice to Contractors for this contract was issued?

If "Yes", insert the address, or insert "same as address on page 1."

If "No," insert the address of the office responsible for this bid, or insert "same as address on page 1."

(In either case, provide a street address in lieu of a post office box.)

BID SIGNATURE PAGE

CERTIFICATIONS

The person(s) signing below certifies that:

· he/she(they) is(are) authorized to represent the Bidder and bind the Bidder to this bid,

· and, the information contained in or with this bid is true and correct, and that this information is material and important and will be relied upon by the System in awarding the contract for which this bid is submitted.

If the Bidder is an Individual, Proprietorship, or Partnership:

(one signature and one witness signature required)

(Signature) (Witness)

(Date)

If the Bidder is a Corporation, LP, LLP, or LLC:

(two signatures required)

(President/Vice President) (Secretary/Treasurer)

(Date)

(CORPORATE SEAL)

Solicitation for Work Order Contract for Construction 2018K112Bid Form
Solicitation # CWU-L-2027/1.1Page 9 of 9

File details come from the government source that posted it. Updated .