Updated Attachment A 598-19-127 Bldg 104 Renovations SOW Construction.docx
DOCX document 238 KB Posted
- Attached to
- Y1DZ--598-19-127 Bldg 104 Renovations
- Solicitation number
- 598-19-127
About this file
This document is a Statement of Work (SOW) for Building 104 Renovations at the Eugene J. Towbin Healthcare Center in North Little Rock, AR, issued by the Department of Veterans Affairs Veterans Health Administration. The project involves comprehensive renovation of a 9,167 square foot historic building used by the Law Enforcement Training Center (LETC), including interior and exterior upgrades, mechanical systems replacement, structural improvements, and ADA accessibility modifications.
Key project details include a 300-day performance period, requirements for complete site preparation, adherence to multiple regulatory standards (VA, EPA, OSHA, NFPA, NEC), and specific contractor responsibilities such as developing quality control procedures, maintaining project record drawings, and submitting detailed construction schedules. The solicitation requires contractors to coordinate closely with VA personnel, comply with security protocols, and attend safety training. Contractors must submit shop drawings, product data, and samples within 20 calendar days after Notice to Proceed, with the VA providing review comments within 10 business days.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING 104 RENOVATIONS
Project Number 598-19-127
Engineering Planning and Design Office Central Arkansas Veterans Healthcare System 2200 Fort Roots Drive Building 1
North Little Rock, AR 72114
Building 104 Renovations Project No. 598-19-127
THE SCOPE OF WORK
1.1 The project “Building 104 Renovations”, is located at the Eugene J. Towbin Healthcare Center, North Little Rock, AR, Building 104.
1.2 The Law Enforcement Training Center (LETC) provides training to VA and DOD law enforcement/ security personnel to enhance the safety of veterans, guests and employees. LETC has experienced a growth in student attendance and anticipates an expansion of students in support of the Secretaries shared services reorganization. Building 104 is used by LETC for classroom and training purposes. Building 104 requires renovations to meet LETC specific training space requirements and new mechanical systems.
Work Overview
1.3 General project scope is proved below. See the attached Design Drawings, Design narrative, and specifications for detailed scope of work which supersedes the below overview.
1.4 Building 104 (approximately 9,167 SF total) is a historic building consisting of a basement, first floor, second floor and attic level. The scope includes renovation of both interior and exterior elements including building restrooms and shower room upgrades to conform to ADA/ABA accessibility requirements, interior room demo and remodeling; structural work to correct inadequate floor capacity, limited new finishes and comprehensive replacement of all mechanical systems to meet modern standards, replacement of an electrical panel and the replacement of exterior fire escapes and access ramp.
1.5 If design documents do not clearly specify, emergency battery pack/LED drivers are to be equipped with self-test/diagnostics.
1.6 Period of Performance is 300 days after the notice to proceed.
General Contractor Services
1.7 Contractor shall provide all labor, materials, tools, equipment, storage, expertise, administration, supervision and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.
1.8 Location is in building 104. Building should be unoccupied during renovations. Contractor is responsible for complying with ICRA standards and policies.
1.9 The Contractor is responsible for verifying dimensions, existing utilities and other information presented in this document. The Contractor’s price shall include all direct (Bare Cost) and indirect costs (Coefficient) including labor, materials, equipment, transportation, incidentals, and taxes.
1.10 Quality Control (QC). The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The plan shall be submitted to the COR for review/acceptance prior to starting any work.
1.11 Quality Assurance (QA). The CAVHS Engineers will monitor and inspect the Contractor's performance under this contract using the quality assurance procedures in the Federal Acquisition Regulation (FAR) clause 52.246-12, “Inspection of Construction”.
1.12 The Contracting Officer’s Representative monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract; perform inspections necessary in connection with contract performance; maintain written and oral communications with the Contractor concerning technical aspects of the contract; issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. The COR is not authorized to change any of the terms and conditions of the Contract.
1.13 All employees of general contractor and subcontractors shall comply with the VA security management program, be identified by through project and employer badges, and restricted from areas of unauthorized access.
1.14 General Contractor’s employees shall not enter the project site without appropriate badging/identification. They may also be subject to inspection of their personal effects when entering or leaving the project site.
1.15 Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
1.16 No photography of VA premises is allowed without written permission of the Contracting Officer. The Contractor and workforce personnel shall not post or discuss government facility activities on unauthorized public media.
1.17 VA reserves the right to close/shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
1.18 When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
1.19 General Contractor’s employees are subject to rules of CAVHS Medical Center applicable to their conduct.
1.20 Execute work to interfere as little as possible with normal functioning of CAVHS Medical Center, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required.
1.21 Do not store materials and equipment in other than assigned areas.
1.22 Scheduling of material deliveries is required. Due to space restrictions, material deliveries should not be more than what can be installed within five working days unless written authorization is given for additional storage in a designated area.
1.23 No utility service such as water, gas, steam, HVAC, sewers, electricity, or fire protection systems and communications systems may be interrupted without prior approval of the CAVHS Chief Engineer. If services must be interrupted to other services outside of the immediate work area of this scope, a minimum of 21 days written notice must be submitted for approval. This outage request must identify the affected buildings, areas, rooms, date, duration, outage description, and the procedure of the intended work.
1.24 The Contractor shall maintain the work site in a neat, orderly, and safe condition at all times. The Contractor shall remove debris on a daily basis. The Contractor shall repair any damage to the existing grounds, facilities, or property incurred during the course of construction to its original pre-existing conditions. The Contractor shall remove all tools, supplies, equipment, and debris upon completion of the contract.
1.25 The general contractor shall field verify all dimensions and submit shop drawings for approval by contracting officer. Coordinate site visits with the COR.
1.26 Final clean up and finishes. At the completion of the work, all fixtures, equipment, and materials shall be cleaned. The Contractor shall do a final cleaning to include disposal of debris resulting from construction as well as dispose of containers for the materials used during the performance of the work. Contractor shall provide weight tickets for all recyclable items and debris disposal to the COR.
1.27 Warranty. Contractor shall warrant its work against faulty workmanship for a period of not less than one year from the date of Government acceptance of the work provided under this contract. Under this warranty, contractor shall be prepared to return to the work site within one working day after notification without charge to make any necessary repairs.
1.28 The design of new work shall include all changes to existing facilities, utility systems, and site improvements required to provide for satisfactory connection between the old and new work to make the facility completely operable for its intended use.
1.29 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the VAMC. Also, project/construction schedule, schedule of values/prices and construction phases must be provided and approved by the Contracting Officer.
1.30 Contractor shall completely prepare site, prior to the installation of the equipment, and furnish labor, equipment and materials to perform work for this specific project as required by construction documents.
1.31 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, ICRA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.
1.32 Project Record Drawings: The Contractor will maintain a set of Record Drawings. The Contractor will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process. The project record drawings will be available for review by the VA Project Manager at all times.
1.33 After the award of contract, the Contractor shall prepare a detailed schedule (aka milestone chart) using “Microsoft Project” software. The schedule shall indicate detailed activities for the projected life of the project. The schedule shall consist of detailed activities and their restraining relationships. It will also detail manpower usage throughout the project. This schedule shall be updated every 2 weeks.
1.34 Submittals will be submitted and approved through submittal exchange, Procore or similar program as long as the program is accessible by the VA at the contractor’s expense.
1.35 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within twenty (20) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 10 business days after receiving each submittal.
1.36 The Contractor shall submit a construction schedule within ten (10) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no delays in the schedule shall be tolerated without the CO’s approval.
1.37 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.
1.38 The Contactor and subcontractors shall attend a Safety training provided by Central Arkansas Veterans Hospital before any work begins. This training includes Infection Control.
4. General Contract Requirement
4.1 Work as described under this contract shall be accomplished during Normal Working Hours, which are defined as 7:00 am to 5:00 p.m., Monday through Friday. Contractor may work earlier or later in the day and on weekends or federal holidays with the COR’s approval at no additional cost to the VA. Noise disturbances and utility shutdowns/tie-ins shall be coordinated with the COR and not interfere with VA daily operations
4.2 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. If required by the Contracting Officer, Contractor shall, at no additional cost to the VA, coordinate with other VA’s activities including but not limited to construction activities near the job site to ensure the construction work under this project will be in harmony with those activities. This coordination shall include but not limited to the careful scheduling of work commencement, equipment mobilization etc.
4.3 The following legal holidays are observed by this Government Agency:
New Year's Day January 1st Martin Luther King's Birthday Third Monday in January
| Presidents Day | Third Monday in February | |
| Memorial Day | Last Monday in May | |
| Juneteenth | June 19th | |
| Independence Day | July 4th |
Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th and any day declared by the federal government as holiday.
5. Project Meetings
5.1 Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government. Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.
5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer Representative (COR). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and email addresses; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to the all attendees within 48 hours after change notice.
6. ID Badge Requirement
6.1 Contract workers under this project will require an identification badge from the VA before the start of construction work at the Central Arkansas VAMC. There is no charge for these badges; however, it may be required for each contract employee to make multiple trips to the Human Resources office located on campus
7. Privacy and Information Security
7.1 Information Systems Officer, Information Protection:
7.1.1 The contractor will not have access to VA Desktop computers nor will they have access to online resources belonging to the government while conducting services. If removal of equipment from the VA is required, any memory storage devices, such as hard drives, solid state drives and non-volatile memory units will remain in VA control and will not be removed from VA custody.
7.2 Privacy Officer:
7.2.1 The contractor will not have access to protected Patient Health Information (PHI) and nor will they have the capability of accessing patient information during the services provided to the VA and if removal of equipment from the VA is required, any memory storage devices, such as hard drives, solid state drives and non-volatile memory units will remain in VA control and will not be removed from VA custody. All research data available for Contractor analyses is de-identified.
7.3 Records Manager:
7.3.1 Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
7.3.2 Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
7.3.3 Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
7.3.4 Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
7.3.5 Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
7.3.6 The Government Agency owns the rights to all data/records produced as part of this contract.
7.3.7 The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
7.3.8 The Certification and Accreditation (C&A) requirements do not apply, and a Security Accreditation Package is not required.
8. Deduct Alternates
8.1 Deduct Alternates are listed in the 598-19-127 Construction Documents Narrative in Chapter 01 Executive Summary. Three deduct alternates are listed.
9. Attachments
9.1 598-19-127 Construction Documents Submission Drawings 03-17-2025
9.2 598-19-127 Construction Documents Narrative 03-17-2025
9.3 598-19-127 Documents Submission Specs 03-17-2025 image1.png image2.png