580-22-110 SOW REPAI WATER LEAK INTO MAIN COMPUTER SERVER ROOM.pdf
PDF 168 KB Posted
- Solicitation number
- 36C25625R0065
About this file
This Statement of Work (SOW) details a construction project at the Michael E. DeBakey VA Medical Center in Houston, Texas, focused on repairing water infiltration issues in the main computer server room and canteen dining court atrium. The project (No. 580-22-110) requires comprehensive architectural, electrical, fireproofing, mechanical, plumbing, and demolition work, with critical requirements including minimizing disruptions to server rooms, maintaining power continuity, protecting equipment from dust, and ensuring safe operating temperatures.
Key project specifications include a 420-calendar day performance period, strict safety and security protocols (such as VA-issued identification cards and TB/flu shot requirements for workers), weekly progress meetings, and compliance with numerous federal, VA, and industry standards including VA specifications, OSHA, NFPA, and NEC regulations. The contractor must submit detailed documentation including a submittal schedule, construction schedule, and meeting minutes, with specific milestone deadlines such as providing a submittal schedule within 10 calendar days after Notice to Proceed and completing all shop drawings and product data submissions within 60 calendar days.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MICHAEL E. DEBAKEY VA MEDICAL CENTER
HOUSTON, TEXAS
Project No: 580-22-110 Repair Water Leak into Main Computer Server Room Suite
Statement of Work
1 Foreword
1.1 Contractor shall provide all labor, materials, tools, equipment, expertise, administration, supervision, and transportation as necessary to perform all work in accordance with provided construction specifications, drawings, all documents attached to this contract, all terms and conditions of this contract, and this statement of work.
1.2 This document does not relieve the contractor of their professional responsibility to comply with all local and federal construction codes, environmental guidance, and to perform and complete a fully coordinated job.
2 General Project Description
2.1 Work includes construction labor and supervision for architectural, electrical, fireproofing, mechanical, plumbing, and demolition work as required by the provided construction documents.
2.2 Contractor shall repair the water infiltration issues present in the canteen dining court atrium and prevent the ingress of moisture present in main server room BC-301 and the telecommunication equipment room BC-275 in Building 100.
This work shall be completed while minimizing disruptions to the main server rooms. Power shall not be disconnected at any time during any phase of construction. All equipment in the main server rooms shall be protected from any dust that may result from construction and ensure that safe operating temperatures are maintained for all equipment. This Scope of Work is not considered to be a comprehensive description of work details for this project.
All work shall be completed per the plans/drawings and specifications.
3 General Construction Requirements
3.1 Prior to any mobilization and construction, the contractor shall request and have an approved Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety Measures Certification from the COR and CO.
Project/construction schedule, schedule of values/prices and construction phases must be provided and approved by the COR and CO.
3.2 Contractor shall completely prepare site, furnish labor, equipment, and materials to perform work for this specific project as required by construction documents.
3.3 The entire project’s associated construction and temporary works shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and regulations.
3.4 The following milestone dates shall be incorporated into the contractor’s schedule.
3.4.1 Submittal Schedule and log shall be provided within ten (10) calendar days after Notice to Proceed. The contractor shall provide it to the Contracting Officer’s Representative (COR) for approval and shall include the dates for submission of Shop Drawings, Product Data, and Samples.
3.4.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the VA within sixty (60) calendar days after Notice to Proceed. The VA will provide the Contractor with written comments within 15 business days after receiving each submittal.
3.4.3 The Contractor shall submit a construction schedule within seven (7) calendar days after Notice to Proceed. The construction schedule shall be prepared in terms of calendar days (not working days). Once the construction schedule is submitted by the Contractor and approved by the CO, no lateness in the schedule shall be tolerated without the CO’s approval.
3.4.4 A pre-construction meeting shall be held within ten (10) calendar days after award of Contract. During the construction, the Contractor shall attend all weekly construction progress meetings. The meeting schedule and place will be discussed in the pre-construction meeting.
4 General Contract Requirement
4.1 VA’s Normal Working Hours are 7:00 am to 4:30 p.m., Monday through Friday.
Contractor may work earlier or later in the day, after business hours, on weekends or on Federal Holidays with prior approval from the Contracting Officer’s Representative at no additional cost to the VA.
4.2 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. If required by the Contracting Officer, Contractor shall, at no additional cost to the VA, coordinate with other VA’s activities including but not limited to construction activities near the job site to ensure the construction work under this project will be in harmony with those activities.
This coordination shall include but not limited to the careful scheduling of work commencement, equipment mobilization etc.
4.3 The following legal holidays are observed by this Government Agency:
New Year's Day January 1st Martin Luther King's Birthday Third Monday in January Presidents Day Third Monday in February Memorial Day Last Monday in May Juneteenth Independence Day June 19th Independence Day July 4th Labor Day First Monday in September Columbus Day Second Monday in October Veterans Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th and any day declared by the federal government as holiday.
5 Project Meetings
5.1 Each week the contractor shall hold a progress meeting to review progress to date and to resolve all questions for the upcoming week. The progress meeting shall include at a minimum, the Project Manager and the Superintendent representing the Contractor, the COR and the CO representing the Government.
Technical supervisor (foreman), sub-contractors, suppliers, etc. shall attend when requested by the Contracting Officer. The meeting shall be same day, time, and place each week.
5.2 Meeting Minutes - The contractor shall take minutes of all meetings held relative to this project. The format must be acceptable to the Contracting Officer (CO). Minutes must include the meeting date and time; agenda; meeting location; list of participants with their affiliations, and telephone numbers; be fully descriptive of issues, problems and decisions made; and action items with names of responsible parties and deadlines. In addition, the minutes must include, as attachments, all exhibits and references distributed as handout materials, unless the materials are part of a formal submission. The contractor shall provide, via e-mail, complete copies of all minutes to all attendees within 72 hours of the meeting. All challenges to the minutes will be reflected in a revised version prepared by the contractor and CO along with the contractor and COR shall sign/initial the minutes. In the event of any disputes or challenges that can’t be resolved, the Contracting Officer shall render a final decision. Copies of updated minutes shall be distributed to all attendees within 48 hours after change notice.
6 Safety and Security
6.1 Contract workers under this project may require a VA issued identification card before the start of construction work at the MEDVAMC. There is no charge for the badges; however, multiple trips to MEDVAMC facility maybe required.
6.2 Contract employees, including all subcontractor employees, must be TB tested and receive a flu shot (each year under the contract performance) if they will work within the MEDVAMC Building 100. A letter from the prime contractor shall be submitted to the CO prior to work commencing that all staff members are TB negative and the flu shot was received.
6.3 All contract personnel are subject to inspection of personal effects when entering or leaving the project site.
6.4 Parking is strictly controlled throughout MEDVAMC. Contractor parking is only allowed in authorized areas. Contractor shall abide by all police requirements. Parking in designated patient parking areas is strictly prohibited. Parking for unloading equipment necessary to perform the work shall be approved in advance by the COR.
--- End---
| 1 Foreword |
| 2 General Project Description |
| 3 General Construction Requirements |
| 4 General Contract Requirement |
| 5 Project Meetings |
| 6 Safety and Security |