580-22-110 DRAWINGS REPAIR WATER LEAK MAIN COMPUTER SERVER ROOM.pdf

PDF 17 MB Posted

Attached to
Z1DA | 580-22-110 | REPAIR WATER LEAK MAIN COMPUTER SERVER ROOM | AMENDMENT 0002
Solicitation number
36C25625R0065
Issued by

About this file

These are architectural and engineering drawings for a federal construction project at the Michael E. DeBakey VA Medical Center in Houston, Texas. The project involves investigating and stopping water infiltration in the main server rooms (Project #580-22-110), with work focused on the building's canteen/CLC inner courtyard. The comprehensive drawing set includes detailed plans for demolition, waterproofing, landscaping, plumbing, electrical, and fire suppression systems, covering both first floor and basement levels. Key project elements include removing existing pavers and soil, installing a new waterproofing membrane, replacing landscaping, and repairing damaged fireproofing on structural steel, with extensive infection control and construction safety protocols outlined throughout the documents. The project is fully sprinklered and designed to be completed without disrupting medical center operations, with an anticipated 420-calendar day performance period.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

PROJECT SITE MAP PROJECT LOCATION MAP

CANTEEN / CLC INNER COURTYARD CANTEEN / CLC INNER COURTYARD GAZEBO

/2

/2

:5

:3

A

M C

U s e rs

\a c a b ra

\D o c u m e n ts \A

-2

-V A

H o u s to n -R e p r S rv r

R m a c a b ra

M U

S

.r v t

G-001

COVER

1 4AC

INVESTIGATE AND STOP

WATER INFILTRATION IN MAIN

SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030 JANUARY 31, 2025

100% BID DOCUMENTS

580-22-11022-228-Q39

INVESTIGATE AND STOP WATER

INFILTRATION IN MAIN SERVER ROOMS

MICHAEL E. DEBAKEY VA MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030

VA PROJECT #: 580-22-110

WVS

N N

PROJECT LOCATION

DRAWING LIST

GENERAL

G-001 COVER 1 4

G-002 CAMPUS MAP AND LOGISTICS PLAN 2 4

G-003 FIRST FLOOR LIFE SAFETY 3 4

G-004 ICRA INFORMATION AND DETAILS 4 4

LANDSCAPE

LP101 COURTYARD LANDSCAPE PLAN 1 2

LP501 COURTYARD LANDSCAPE DETAILS 2 2

ARCHITECTURAL

A-001 ARCHITECTURAL SYMBOLS, ABBREVIATIONS AND NOTES 1 15

A-101 OVERALL FIRST FLOOR PLAN 2 15

A-102 ENLARGED COURTYARD DEMOLITION PLAN 3 15

A-103 ENLARGED COURTYARD SLOPE FIRST FLOOR PLAN 4 15

A-104 ENLARGED COURTYARD FIRST FLOOR PLAN 5 15

A-301 BUILDING SECTIONS 6 15

A-501 PLANTER DETAILS 7 15

A-901 AXONOMETRIC VIEWS 8 15

AB101 OVERALL BASEMENT PLAN 9 15

AB102 PARTIAL ENLARGED BASEMENT PLAN 10 15

AB103 MCR ENLARGED EXISTING CONDITION PLANS 11 15

AB104 MCR ENLARGED PROPOSED SCAFFOLDING PLANS 12 15

AB105 MCR BC-275 ENLARGED REFLECTED CEILING PLANS 13 15

AB106 MCR BC-301 ENLARGED REFLECTED CEILING PLANS 14 15

AB107 STRUCTURAL FRAMING PLAN 15 15

FIRE SUPPRESSION

FX001 FIRE SUPPRESSION GENERAL INFORMATION 1 2

FX101 PARTIAL BASEMENT FIRE SUPPRESSION PLAN 2 2

PLUMBING

P-001 PLUMBING GENERAL INFORMATION, DETAILS, AND SCHEDULES 1 2

P-101 COURTYARD PLUMBING FLOOR PLANS 2 2

ELECTRICAL

E-001 ELECTRICAL GENERAL NOTES, SYMBOL LEGENDS, AND ABBREVIATIONS 1 3

E-101 FIRST FLOOR ELECTRICAL PLAN 2 3

E-102 BASEMENT ELECTRICAL PLANS 3 3

PROJECT LOCATION

W

AL

TE

R DAVID VAN SCOTER

REG. NO. 9953

Docusign Envelope ID: 4F0E9E21-7A0C-4CF7-B642-CCE5C59F0065

1/31/2025

FISHER HOUSE 2

FISHER HOUSE 3

ENTRANCE 71

ENTRANCE 70

ENTRANCE 73

E N

E R

G Y

C E

N T

E R

D R

O

LD

SPAN

ISH

TR

AIL

CAMBRIDGE

LE CAPITAN

C A

T E

T E

R R

A C

E

HO

LCO

M

BE BLVD.

RINGNESS

AVE

ALMEDA

S O

U T

H L

E E

WEST LEE

EAST LEE

MIXON AVE

ENTRANCE (Locked)

ENTRANCE

M

IX

O N

A V

E

SHEEHAN AVE

ENGINEERING

STEAM PLANT

ENERGY CONTROL

CENTER

GROUNDS

E D

U C

A T

IO

N C

T R

WASTE DISPOSAL

HO

LC

OM

BE

R

ET

AI

L C

EN

TE

R

INTR

OGE

N TH

ERA

PEU

TIC

S IN

C

FISHER HOUSE 1

VA

REGIONAL

OFFICE

102 103 104

106 -107

104A

102A

STORAGE

REGIONAL OFFICE

MAIN ENTRANCE

108A

CHP

XXX

CENTERPOINT

ADMIN BLDG

GARAGE

NEW PARKING

INTR

OGE

N TH

ERA

PEU

TIC

S IN

C

H

BUILDING IN SCOPE

PROPOSED CONTRACTOR

PARKING AND STAGING AREA

(LIMITED TO 2 VEHICLES)

CONSTRUCTION MATERIALS

ACCESS ROUTE

AREA OF WORK

Engineers Architects

# KEY NOTES:

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/2

/2

:5

:3

A

M C

U s e rs

\a c a b ra

\D o c u m e n ts \A

-2

-V A

H o u s to n -R e p r S rv r

R m a c a b ra

M U

S

.r v t

G-002

CAMPUS MAP AND LOGISTICS PLAN

2 4AC

INVESTIGATE AND STOP

WATER INFILTRATION IN MAIN

SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030 JANUARY 31, 2025

100% BID DOCUMENTS

580-22-11022-228-Q39

WVS

Scale: 1" = 100'-0"

CAMPUS MAP AND LOGISTICS PLAN

NORTH

0 10050 200

LEGEND

A. LOCATION AND EXTENTS OF STAGING AREA

SHALL BE FULLY COORDINATED WITH THE

VA/COR.

B. BEFORE PROCEEDING WITH ANY WORK, IT

SHALL BE THE RESPONSIBILITY OF THE

CONTRACTOR TO PROVIDE NECESSARY

SAFEGUARDS TO MAINTAIN ALL PARTS OF

THIS PROJECT UNDER THIS CONTRACT IN A

SAFE CONDITION AT ALL TIMES AND PROTECT

FROM DAMAGE THOSE PORTIONS WHICH

ARE TO REMAIN.

C. CONTRACTOR SHALL REPAIR DAMAGES TO

THE EXISTING PAVED AREAS, CURB,

LANDSCAPE/VEGETATION, ETC. CAUSED

BY WORK.

D. PLAZA WORK TO TAKE PLACE DURING

NORMAL WORKING HOURS.

1 CONTRACTOR PARKING, SHUTTLE

AVAILABLE TO MAIN BLDG.

W

AL

FD FD

FD

FD

FD FD

FD FDFD

FD

FD

CSWK 52

FHVEC

T6A

4" CONC PAD

THA01

(VV)

GMA031GMA031

TD

GP35

GP35

GP35

GP26

Z1G04

Z1G03

Z1G05

STAIR

OFFICE

STUD WRKM

NUR INST

STORAGE

CORR

CORR

VEST

SOC WK

BATH

KIT

CORR

PVA SECY

PVA OFF

BR

LIV/DIN

CORR

TWO BR

T

TWO BR

ELEVATOR ELEVATOR

STAIR

CORR

PT EDUCATION

CORR

NON-FOOD STOR HAC

KITCHEN

LC

EQ STOR

TWO BR

T

TC

TWO BR

TWO BR

T

TWO BR

TWO BR

T

TWO BR

TWO BR

TWO BR

TWO BR

TWO BR

TWO BR

PVA OFF

T

T

T

PVA SECY

CORR

LIV/DIN KIT SOC WK

BR

SOC WK

CLO

BATH FAC

T

BREAK RM EX/TMT

DIN/RECREATION

NURSE EXECUTIVE

WAITING/RECEPTIONIST/WORK AREA

NUR STA

CORR

CORR

CORR

STF T

COPY/WORK ROOM

CONFERENCE ROOM

SUPERVISORS OFFICEOFFICEOFFICE

CORRIDOR

OFFICE

MED

ELEVATOR ELEVATOR

STORAGE

CORR

PT EDUCATION

HACHAC

VENDING

DINING

ELEVATOR

ELEVATOR

P ELEV. LOBBY

ELEVATORFUT ELEVATOR

MECHANICAL BAY-6

STAIR

ELEVATORELEVATOR ELEVATOR

CORR

MAIL CHUTE

EXAM

T

OFFICE

OFFICE

MEDS/

SUPPLY

TLT

HAC

ELEVATOR

ELEVATOR

STAIR

ELEVATOR

STAFF

CORRIDOR

VEST

STAIR

CORR

HAC

ATS

STO

OFFICE OFFICE

OFFICE

TUB ROOM

1B-160

1B-172

1B-170

C1B-111

C1B-112

ST-3

1A-590

1B-168

1C-158D

1C-158A

C1B-108

1B-164

1C-158B

1C-158

C1C-108

1C-154

1C-152A

1C-152

1C-125

1C-126A

1C-122A

1C-143A

1C-129

1C-143

1C-144A

1C-148A

1C-116

1C-112

1C-118A

1C-114

1C-111C

1C-160

1C-152A

1B-164A

1C-158E

1C-160F

CIC-102

1C-108

CIC-102

1C-111B 1C-111A

1C-111

1C-109

1C-118

1C-120

1C-122

1C-124

1C-126 1C-146

1C-148

1C-150

1C-152

1C-154

1B-164

C1C-108

1C-158 1C-158A 1B-166

1C-158B

1B-168

1C-127

CIC-106

C1C-107

C1C-105

C1C-104

ST-4

P-12P-11

1C-109D

1C-109C1C-109B1C-109A

CIC-103

1C-204

1C-206

1C-160B

1C-160A

1C-160C1C-160D1C-160E

CIC-160

1C-206

1C-204

1C-110

1C-108

1A-660A

1A-660

1A-660B 1A-632

P-6

C1C-100

P-10 P-9

P-7 P-8

1A-640

ST-9

CIA-600

T-4

T-3

1C-327A

1C-325

1C-321

1C-109C1C-109B1C-109A

1C-109 1C-109D

1C-327A

1A-660B

P-6

ST-9

1C-204

1C-323 C1A-601

1A-590

ST-8

C1C-112

1A-632

1C-204A

1C-111

1C-143B

S S

S S

S S

S S

S

S

S

?CAPACITYCLR

EXIT

PASSAGEWAY

42" 210

CAPACITYCLR

EXIT

PASSAGEWAY

44" 220

A ?B

?C

CANTEEN

COURTYARD

BC-403

EGRESS PATH

EGRESS PATH TAG

EGRESS IDENTIFICATION

FIRE EXTINGUISHER CABINET

XXX

FEC

CAPACITYCLR

EXTERIOR

EXIT

XX" ###

EXIT

IDENTIFICATION

EGRESS CLEAR

WIDTH

EGRESS CAPACITY

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/2

/2

:5

:3

A

M C

U s e rs

\a c a b ra

\D o c u m e n ts \A

-2

-V A

H o u s to n -R e p r S rv r

R m a c a b ra

M U

S

.r v t

G-003

FIRST FLOOR LIFE SAFETY

3 4AC

INVESTIGATE AND STOP

WATER INFILTRATION IN MAIN

SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030 JANUARY 31, 2025

100% BID DOCUMENTS

580-22-11022-228-Q39

WVS

Scale: 1/8" = 1'-0"

FIRST FLOOR PLAN LIFE SAFETY

LIFE SAFETY LEGEND

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

N O R

TH

0 4 8 16

PROJECT NAME: INVESTIGATE AND STOP

WATER INFILTRATION IN MAIN

SERVER ROOMS

PROJECT ADDRESS: MICHAEL E. DEBAKEY

VA MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030

PROPOSED USE: HEALTHCARE

OWNED BY: FEDERAL GOVERNMENT

AUTHORITY HAVING JURISDICTION: US DEPARTMENT OF VETERAN AFFAIRS

PROJECT DESCRIPTION:

REMOVE THE SOIL LOCATED IN THE PLANTERS AND SIDE AREA AND ALL THE PAVERS AT

HARD SURFACES AND INSTALL A NEW WATERPROOFING MEMBRANE AT THE ENTIRE

CANTEEN/CLC COURTYARD AND REPAIR DAMAGED FIREPROOFING TO STEEL BELOW.

(APPROX. 8,500 S.F.)

APPLICABLE CODES:

2021 NFPA 101 LIFE SAFETY CODE

2021 NFPA 220 STANDARDS ON TYPES OF BUILDING CONSTRUCTION

2021 INTERNATIONAL BUILDING CODE

2010 AMERICANS WITH DISABILITIES ACT (ADA) STANDARDS

2017 PG-18-13 VA BARRIER FREE DESIGN STANDARD

GENERAL CODE INFORMATION:

CONSTRUCTION TYPE: I (332) PER

NFPA 220

PRIMARY OCCUPANCY: HEALTHCARE

CONSTRUCTION SCOPE: RENOVATION

SPRINKLERS: FULLY

SPRINKLERED

ALLOWABLE STORIES ABOVE GRADE: UNLIMITED (2021 IBC, T504.4)

ACTUAL STORIES: 6

ALLOWABLE HEIGHT: UNLIMITED

(2021 IBC, T504.3)

ACTUAL HEIGHT: 116'-0"

ALLOWABLE AREA:

UNLIMITED (2021 IBC, T506.2)

FIRE RESISTANCE RATING REQUIREMENTS (NFPA 220 TABLE 4.1.1):

COLUMNS:

3 HR

BEAMS, GIRDERS, TRUSSES, AND ARCHES: 3 HR

FLOOR/CEILING ASSEMBLIES: 2 HR

LIFE SAFETY SYSTEMS:

EMERGENCY LIGHTING: YES

EXIT SIGNS: YES

FIRE ALARM: YES

SMOKE DETECTION: YES

BUILDING AREA PER LEVEL EXISTING (SF)

BASEMENT 220,624

FIRST 294,739

SECOND 268,195

THIRD 207,081

FOURTH 189,652

FIFTH 186,199

SIXTH 121,579

CODE SUMMARY

CODE STANDARDS AND EXECUTIVE

ORDERS (PG-18-3 TOPIC 1)

GENERAL: VA HAS ADOPTED THE LATEST EDITION OF THE FOLLOWING CODES AND

STANDARDS AS A MINIMUM FOR ALL PROJECTS PERFORMED IN THE

MODERNIZATION, ALTERATION, ADDITION, OR IMPROVEMENT OF ITS REAL

PROPERTY AND THE CONSTRUCTION OF NEW STRUCTURES. VA DESIGN MANUALS

AND MASTER SPECIFICATIONS SPECIFY OTHER CODES AND STANDARDS THAT VA

FOLLOWS ON ITS PROJECTS:

• VA DIRECTIVES, DESIGN MANUALS, MASTER SPECIFICATIONS, VA NATIONAL CAD

STANDARD APPLICATION GUIDE, AND OTHER GUIDANCE ON THE TECHNICAL

INFORMATION LIBRARY (TIL) (HTTP://WWW.CFM.VA.GOV/TIL/).

• INTERNATIONAL BUILDING CODE (IBC) 2021 (ONLY WHEN SPECIFICALLY

REFERENCED IN VA DESIGN DOCUMENTS, SEE NOTES BELOW)

• NFPA 101 LIFE SAFETY CODE 2021 (SEE NOTES BELOW)

• NFPA NATIONAL FIRE CODES WITH THE EXCEPTION OF NFPA 5000 AND NFPA 900

• OCCUPATIONAL, SAFETY AND HEALTH ADMINISTRATION (OSHA) STANDARDS.

• VA SEISMIC DESIGN REQUIREMENTS, H-18-8

• NATIONAL ELECTRICAL CODE (NEC)

• INTERNATIONAL PLUMBING CODE (IPC) 2021

• SAFETY CODE FOR ELEVATORS AND ESCALATORS, AMERICAN SOCIETY OF

MECHANICAL ENGINEERS (ASME) A 17.1.

• ASME BOILER AND PRESSURE VESSEL CODE

• ASME CODE FOR PRESSURE PIPING

• ARCHITECTURAL BARRIERS ACT ACCESSIBILITY STANDARDS (ABAAS) INCLUDING

VA SUPPLEMENT, BARRIER FREE DESIGN STANDARD (PG-18-13)

• BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE, AMERICAN

CONCRETE INSTITUTE AND COMMENTARY (ACI 318)

• MANUAL OF STEEL CONSTRUCTION, LOAD AND RESISTANCE FACTOR DESIGN

SPECIFICATIONS FOR STRUCTURAL STEEL BUILDINGS, AMERICAN INSTITUTE OF

STEEL CONSTRUCTION (AISC)

• ENERGY POLICY ACT OF 2005 (EPACT)

• DOE INTERIM FINAL RULE: ENERGY CONSERVATION STANDARDS FOR NEW

FEDERAL, COMMERCIAL AND MULTI-FAMILY HIGH-RISE RESIDENTIAL BUILDINGS

AND NEW LOW-RISE RESIDENTIAL BUILDINGS, 10 CFR PARTS 433, 434 AND 435.

• FEDERAL LEADERSHIP IN HIGH PERFORMANCE AND SUSTAINABLE BUILDINGS:

MEMORANDUM OF UNDERSTANDING (MOU)

• THE PROVISIONS FOR CONSTRUCTION AND SAFETY SIGNS. STATED IN THE

GENERAL REQUIREMENTS SECTION 01010 OF THE VA MASTER CONSTRUCTION

SPECIFICATION.

• VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY – ASHRAE STANDARD 62.1-

2022.

• SAFETY STANDARD FOR REFRIGERATION SYSTEMS – ASHRAE STANDARD 15 –

2022.

NOTES:

1. NFPA 101 PRIMARILY ADDRESSES LIFE SAFETY AND FIRE PROTECTION FEATURES

WHILE THE IBC ADDRESSES A WIDE RANGE OF CONSIDERATIONS, INCLUDING, BUT

NOT LIMITED TO, STRUCTURAL STRENGTH, SEISMIC STABILITY, SANITATION,

ADEQUATE LIGHT AND VENTILATION, AND ENERGY CONSERVATION. VA BUILDINGS

MUST MEET THE REQUIREMENTS OF NFPA 101 AND DOCUMENTS REFERENCED BY

NFPA 101 IN ORDER TO COMPLY WITH THE ACCREDITATION REQUIREMENTS OF

THE JOINT COMMISSION. DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR

DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS

OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE ADDRESSED ABOVE IN

THIS PROGRAM GUIDE. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH

THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE

REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101

SHALL BE USED EXCLUSIVELY.

2. CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA

REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND

VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT

SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE

CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO

ENSURE A CONSISTENCY SYSTEM WIDE.

EGRESS PATH "A"

TOTAL PATH LENGTH: 125' - 6"

EGRESS PATH "B"

TOTAL PATH LENGTH: 245' - 0"

EGRESS PATH "C"

TOTAL PATH LENGTH: 172' - 6"

A. SEE SHEET AB102 FOR ICRA MEASURES AT

BASEMENT AREA.

W

AL

INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX OF

PRECAUTIONS FOR CONSTRUCTION AND RENOVATION

INFECTION CONTROL RISK MITIGATION RECOMMENDATIONS MATRIX OF

PRECAUTIONS FOR CONSTRUCTION AND RENOVATION

EXISTING CEILING SYSTEM

BASE - TO MATCH

EXISTING AREA

EXISTING FLOOR

UNDERSIDE OF EXISTING

DECK

C E

IL

IN

G H

E

IG

H T

V A

R

IE

S F

IE

L D

V E

R

IF

Y

W A

L L

H E

IG

H

T V

A R

IE

S

F

IE

L D

V E

R

IF

Y EXISTING CEILING SYSTEM

EXISTING FLOOR

FIRE RESISTANT

SEALANT, BOTH SIDES TO

WALL ABOVE OPENING

FIRE RESISTANT SEALANT,

BOTH SIDES

1-HR RATED

U.L. DESIGN NO. U419

1-HR RATED

U.L. DESIGN NO. U419

TEMPORARY PREFABRICATED

ICRA WALL SYSTEM. BASIS OF

DESIGN: STARC WALL OR

EDGEGUARD OR EQUAL.

EXISTING CEILING

SYSTEM TO HAVE

INTEGRATED CEILING

SEAL.

EXISTING PARTITION WALL

O P

E N

IN

G

A.F.F.

9'-0"

CORRIDOR

CBC300

FIELD DETERMINED

TELEPHONE

ROOM

BC275

MAIN

COMPUTER

ROOM

BC301

EXISTING CEILING SYSTEM

EXISTING FLOOR

FIRE RESISTANT

SEALANT, BOTH SIDES TO

WALL ABOVE OPENING

2-HR RATED

U.L. DESIGN NO. U419

EXISTING CMU WALL

D O

O R

O P

E N

IN

G

H E

IG

H

T

A.F.F.

9'-0"

TOP OF TEMPORARY DOOR

OPENING

DEMO CMU WALL

FOR DOOR TD03

INSTALLATION

FIELD DETERMINED

VEHICLE

TUNNEL

DEMO PORTION OF CEILING

FOR 2 HR RATED TEMPORARY

HARD BARRIER COVER

ILSM TEMPORARY BARRIER TAG

PROJECT:

PRIME CONTRACTOR:

SUB CONTRACTOR:

EMERGENCY CONTACT NO.:

BARRIER INSTALLATION DATE:

BARRIER EXPIRATION DATE:

ILSM SIGNAGE

INTERIM LIFE SAFETY MEASURES IN EFFECT

[INVESTIGATE AND STOP WATER

INFILTRATION IN MAIN BC-275 AND BC-301]

THIS EXIT IS CLOSED AND LEADS TO A

CONSTRUCTION AREA.

PLEASE USE ALL ALTERNATE EXITS AS MARKED.

1' - 5"

1/2"1/2"

/2

/2

/2

/2

/2

/2

EQ.EQ.

DUST CONTROL PLAN NOTES

1. THE VAMC INFECTION CONTROL GROUP HAS CONFIRMED THE DESIGNATION FOR THIS

PROJECT IS LEVEL IV FOR THE CLASS OF PRECAUTIONS OR LEVEL OF INFECTION CONTROL

ACTIVITIES. HARD SURFACE BARRIERS SHALL BE USED EXCEPT IN THE AREA INDICATED ON

THE PHASING PLAN WITH PLASTIC BARRIERS (MINIMUM 4MIL) TO SEAL AREA FROM NON-WORK

AREA AS LONG AS THE SPRINKLER SYSTEM IS INTACT AND ACTIVE.

2. THIS PROJECT NEEDS AN ENTRY VESTIBULE FOR CLOTHING CHANGES (PROVIDE AND LOCATE

A STAGING AREA FOR HAZMAT SUITS NEAR THE PLASTIC BARRIER ENTRANCE SPACES -

CONSTRUCTION ANTEROOM. THEY SHALL BE USED WHEN GOING INTO CONSTRUCTION AREA

AND LEAVING THE CONSTRUCTION AREA) AND TOOL STORAGE AND TIGHT SEALS SHALL BE

MAINTAINED AT THE FULL PERIMETER OF WALLS AND WALL PENETRATIONS. ANY DUST SHALL

BE IMMEDIATELY CLEANED IF TRACKED OUTSIDE OF THE CONSTRUCTION BARRIER. UPON

COMPLETION OF THE CONSTRUCTION PHASE, DUST BARRIERS SHALL BE REMOVED

CAREFULLY TO MINIMIZE SPREADING OF DUST AND THE CONTRACTOR SHALL HAVE

TEMPORARY DUST PROTECTION IN PLACE BEFORE REMOVAL OF A PERMANENT BARRIER.

[AFTER EACH PHASE, PERFORM TASKS STATED IN CONTAMINATION OF PATIENT ROOMS,

SUPPLIES, EQUIPMENT AND RELATED AREAS NOTE 2.

3. PROVIDE STICKY MATS AND BLANKET AT THE PLASTIC BARRIER ENTRANCE SPACES

(CONSTRUCTION ANTEROOM) AND CHANGE DAILY OR MORE OFTEN AS NEEDED TO PREVENT

THE SPREAD OF DUST AND DEBRIS INTO ADJACENT CLEAN SPACE.

INTERNAL DEMOLITION AND CONSTRUCTION ACTIVITIES DUST AND DEBRIS CONTROL

1. USE CORRIDORS AS PRIMARY CONSTRUCTION ACCESS.

2. TRAFFIC CONTROL: DESIGNATED ENTRY AND EXIT PROCEDURES SHALL BE DEFINED. EGRESS

PATHS SHALL BE FREE OF DEBRIS; DESIGNATED ELEVATORS SHALL BE USED DURING

SCHEDULED TIMES; AND ONLY AUTHORIZED PERSONNEL SHALL BE ALLOWED TO ENTER

THE CONSTRUCTION ZONE. SIGNAGE SHALL DIRECT PEDESTRIAN TRAFFIC AWAY FROM THE

CONSTRUCTION AREA AND MATERIALS.

3. CONTRACTOR SHALL USE TWO CARTS TO TRANSFER CONSTRUCTION MATERIAL IN AND OUT

OF THE PROJECT - A CLEAN CART SHALL BE USED; THE NOT-SO-CLEAN CART SHALL BE USED

BETWEEN THE MAIN ENTRY AND THE CONSTRUCTION STAGING/PREP AREA.

4. DEMOLITION DEBRIS: DEBRIS SHALL BE REMOVED IN CARTS WITH TIGHTLY FITTED COVERS, USING DESIGNATED TRAFFIC ROUTES. EFFORTS SHALL BE MADE TO MINIMIZE USE OF

ELEVATORS WITH AN EMPHASIS ON TRANSPORT DURING THE LOWEST PERIOD OF ACTIVITY.

DEBRIS SHALL BE REMOVED DAILY AND AT TIMES SPECIFIED BY THE VAMC. IF CHUTES ARE

USED TO DIRECT DEBRIS OUTSIDE, HIGH EFFICIENCY PARTICULATE AIR (HEPA) FILTERED

NEGATIVE AIR MACHINES SHALL BE USED, AND THE CHUTE OPENING SHALL BE SEALED WHEN

NOT IN USE. FILTERS SHALL BE BAGGED AND SEALED BEFORE BEING TRANSPORTED OUT OF

THE CONSTRUCTION AREA. THE CONTRACTOR SHALL NOT HAUL DEBRIS THROUGH PATIENT-

CARE AREAS WITHOUT PRIOR APPROVAL OF THE COR.

5. EXTERIOR WINDOWS: WINDOWS SHALL BE SEALED TO MINIMIZE INFILTRATION FROM ANY

ADJACENT EXCAVATION DEBRIS.

6. ALL EQUIPMENT REMAIN IN THE ORs AND ASSOCIATED ROOMS SHALL BE COVERED AND

PROTECTED PRIOR STARTING EACH CONSTRUCTION PHASE.

VENTILATION AND ENVIRONMENTAL CONTROLS

1. AIR SYSTEM FLOW: THE COR VERIFY AND ACKNOWLEDGE CONTRACTOR WHETHER THE

CONSTRUCTION AREA USES FRESH/OUTSIDE OR RE-CIRCULATED AIR; FILTERS SHALL BE

ADDED OR RETURN VENTS COVERED AS NEEDED WITH FILTER MATERIAL OR PLASTIC. AIR

MUST FLOW FROM CLEAN TO DIRTY AREAS.

2. NEGATIVE AIR PRESSURE: THE AIR WITHIN THE CONSTRUCTION AREA SHALL BE NEGATIVE

WITH RESPECT TO SURROUNDING AREAS AND WITH NO DISRUPTION OF AIR SYSTEMS OF

ADJACENT AREAS. USE OF THE NEGATIVE AIR PRESSURE SYSTEM WITHIN THE ENCLOSURE

TO REMOVE DUST SHALL PASS AIR THROUGH AN INDUSTRIAL GRADE, PORTABLE HEPA FILTER

CAPABLE OF FILTRATION RATES OF 300-800 CUBIC FEET PER MINUTE (FT3/MIN), OR EXHAUST AIR DIRECTLY TO THE OUTSIDE IF APPROVED BY VAMC. IF EXHAUST SHALL BE TIED INTO A RE-

CIRCULATED AIR SYSTEM, A PRE-FILTER AND HEPA FILTER SHALL BE USED BEFORE EXHAUST

TO PREVENT CONTAMINATION OF THE DUCTS.

3. FOR EXHAUST DUCT ROUTING THRU CORRIDOR: INSTALL HARD DUCT WITH NON-FLANGE

HANGER HUNG FROM CEILING ABOVE, BOTTOM OF DUCT SHALL BE A MINIMUM OF 7'-2" A.F.F.

4. ADJACENT AREAS: THE STATUS OF SEALED PENETRATIONS AND INTACT CEILING SHALL BE

VERIFIED DAILY.

5. AIR EXCHANGE RATES AND PRESSURE RELATIONSHIPS: VAMC AND CONTRACTOR SHALL

VERIFY AND MAINTAIN PROPER RATES IN CRITICAL AREAS NEAR CONSTRUCTION ACTIVITY

AND ENSURE AIR IS NOT BEING RE-CIRCULATED WITHOUT FILTRATION FROM THE

CONSTRUCTION AREA ELSEWHERE. PROVIDE AIR PRESSURE TESTING THROUGHOUT THE

PROJECT IN THE FREQUENCY AS IDENTIFIED BY THE COR.

CONTAMINATION OF PATIENT ROOMS, SUPPLIES, EQUIPMENT AND RELATED AREAS

1. WORKSITE CLOTHING: CONTRACTOR PERSONNEL CLOTHING SHALL BE FREE OF LOOSE SOIL

AND DEBRIS BEFORE LEAVING THE CONSTRUCTION AREA. IF PROTECTIVE APPAREL IS NOT

WORN (E.G., COVERALLS, FOOTGEAR AND HEADGEAR) A HEPA-FILTERED VACUUM SHALL BE

USED TO REMOVE DUST FROM CLOTHING BEFORE LEAVING THE BARRICADE. IF PROTECTIVE

APPAREL IS UTILIZED, THE CONTRACTOR SHALL CONSTRUCT A SPACE OR ANTEROOM FOR

CHANGING CLOTHING AND STORING EQUIPMENT (DESIGNATED AREA. ALL EQUIPMENT,

TOOLS, TOOL CARTS, AND MATERIALS TRANSPORTED THROUGH OCCUPIED AREAS SHALL BE

MADE FREE FROM DUST AND MOISTURE BY VACUUMING AND WET WIPING BEFORE THEIR

REMOVAL FROM THE CONSTRUCTION ZONE OR WORK AREA.

2. POST CONSTRUCTION: DO NOT REMOVE BARRIERS AND KEEP ALL HVAC ISOLATION UNTIL

CONTRACTOR HAS CLEANED CONSTRUCTION SITE, VA EMS STAFF HAS DONE A TERMINAL

CLEANING, AND VA INFECTIOUS DISEASE CONTROL HAS INSPECTED AND APPROVED THE

CLEANING.

ICRA NOTES

IIILOW Risk Group 1

Class III

Note: Infection Control approval will be required when the Construction Activity and Risk Level indicate that

It is the Contractor's Responsibility to provide the following Infection Control Precautions depending upon the Area Class Designation

I

I

III

MEDIUM Risk Group 2

HIGH Risk Group 3

HIGHEST Risk Group 4 V

V

IV

V

IV

III

IV

II

III

Patient Risk Group Table

Infection Control Matrix - Class of Precautions: Construction Project by Patient Risk

TYPE A

Construction Project Type

Major demolition and construction projects Includes, but is not limited to:

• Removal or replacement of building system component(s).

• Removal/installation of drywall partitions.

• Invasive large-scale new building construction.

• Renovation work in two or more rooms.

Work that generates a moderate to high level of dust or requires demolition or removal of any fixed building components or assemblies Includes, but is not limited to:

• Removal of preexisting floor covering, walls, casework or other building components.

• New drywall placement.

• Renovation work in a single room.

• Nonexisting cable pathway or invasive electrical work above ceilings.

• The removal of drywall where a moderate amount of dust and debris is created.

• Dry sanding where a moderate amount of dust and debris is created.

• Work creating significant vibration and/or noise.

• Any activity that cannot be completed in a single work shift.

Small scale, short duration activities which create minimal dust Includes, but is not limited to:

• Work conducted above the ceiling (e.g., prolonged inspection or repair of firewalls and barriers, installation of conduit and/or cabling, and access to mechanical and/or electrical chase spaces).

• Fan shutdown/startup.

• Installation of electrical devices or new flooring that produces minimal dust and debris.

• The removal of drywall where minimal dust and debris is created.

• Controlled sanding activities (e.g., wet or dry sanding) that produce minimal dust and debris.

Inspection and Non-Invasive Activities Includes, but is not limited to:

• Removal of ceiling tile for visual inspection-limited to 1 tile per 50 square feet with limited exposure time.

• Limited building system maintenance (e.g., pneumatic tube station, HVAC system, fire suppression system, electrical and carpentry work to include painting without sanding) that does not create dust or debris.

• Clean plumbing activity limited in nature.

Type of Construction / Project Activity Table

Group 2 Medium Risk

Group 1 Low Risk

• Physical Therapy

• Radiology departments

• All patient waiting rooms

• All outpatient clinics

• Research Areas

• Respiratory Therapy

• Office areas (non-clinical)

• FES/EMS areas

I

Patient Risk Group

TYPE D

TYPE C

TYPE B

TYPE A

Group 4 Highest Risk

Group 3 High Risk

• Emergency Room

• Clinical Laboratories (specimen)

• Same Day Surgery

• Pharmacy

• Nutrition and Food

Service/Canteen

• Procedural Areas (GI)

• Inpatient Mental Health

• Any area caring for immunocompromised patients

• Cardiac Cath Lab/IR

• Central Sterile Supply

• Sterile Processing Service

• Intensive Care Units

IIII

TYPE DTYPE CTYPE B

Class IV or control procedures are necessary.

C

LA

S S

IV

During Construction Project Upon Completion of Project

1. Includes all activities required by Class III

2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities Management

Maintenance and Engineering department before construction begins.

3. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.

4. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to ground and ceiling and secure from movement or damage. Apply tape that will not leave a residue to seal gaps between barriers, ceiling or floor.

5. Seal all penetrations in containment barriers, including floors and ceiling, using approved materials (UL schedule firestop if applicable for barrier type).

6. Containment units or environmental containment units (ECUs) approved for Class IV precautions in small areas totally contained by the unit and that has HEPA-filtered exhaust air.

7. Remove or isolate return air diffusers to avoid dust entering the HVAC system.

8. Remove or isolate the supply air diffusers to avoid positive pressurization of the space.

9. Negative airflow pattern must be maintained from the entry point to the anteroom and into the construction area. The airflow must cascade from outside to inside the construction area. The entire construction area must remain negatively pressurized.

10. Maintain negative pressurization of the entire workspace by use of HEPA exhaust air systems directed outdoors. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows does not require HEPA-filtered air.

11. If exhaust is directed indoors, then the system must be HEPA filtered. Prior to start of work, HEPA filtration must be verified by particulate measurement as no less than 99.97% efficiency and must not alter or change airflow/pressure relationships in other areas.

12. Exhaust into shared or recirculating HVAC systems, or other shared exhaust systems (e.g., bathroom exhaust) is not acceptable.

13. Install device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.

14. Contain all trash and debris in the work area.

15. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.

16. Worker clothing must be clean and free of visible dust before leaving the work area.

HEPA vacuuming of clothing or use of cover suites is acceptable.

17. Workers must wear shoe covers prior to entry into the work area. Shoe covers must be changed prior to exiting the anteroom to the occupied space (non-work area). Damaged shoe covers must be immediately changed.

18. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.

19. Consider collection of particulate data during work to monitor and ensure that contaminates do not enter the occupied spaces. Routine collection of particulate samples may be used to verify HEPA filtration efficiencies.

• Medical/Surgical Units

• Negative pressure isolation rooms

• Outpatient Chemotherapy

Areas

• Operating rooms

• Post Anesthesia Care Unit

• Dialysis

• Dental

C

LA

S S

V

1. Includes all activities required by Class IV

2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities Management

Maintenance and Engineering department before construction begins.

3. Construct and complete critical barriers meeting NFPA 241 requirements. Barriers must extend to the ceiling or if ceiling tile is removed, to the deck above.

4. All (plastic or hard) barrier construction activities must be completed in a manner that prevents dust release. Plastic barriers must be effectively affixed to ground and ceiling and secure from movement or damage. Apply tape that will not leave a residue to seal gaps between barriers, ceiling or floor.

5. Seal all penetrations in containment barriers, anteroom barriers, including floors and ceiling using approved materials (UL schedule firestop if applicable for barrier type).

6. Construct anteroom large enough for equipment staging, cart cleaning, workers. The anteroom must be constructed adjacent to entrance of construction work area.

7. Personnel will be required to wear coveralls at all times during Class V work activities.

Coveralls must be removed before leaving the anteroom.

8. Remove or isolate return air diffusers to avoid dust entering the HVAC system.

9. Remove or isolate the supply air diffusers to avoid positive pressurization of the space.

10. Negative airflow pattern must be maintained from the entry point to the anteroom and into the construction area. The airflow must cascade from outside to inside the construction area. The entire construction area must remain negatively pressurized.

11. Maintain negative pressurization of the entire workspace using HEPA exhaust air systems directed outdoors. Exhaust discharged directly to the outdoors that is 25 feet or greater from entrances, air intakes and windows does not require HEPA-filtered air.

12. If exhaust is directed indoors, then the system must be HEPA filtered. Prior to start of work, HEPA filtration must be verified by particulate measurement as no less than 99.97% efficiency and must not alter or change airflow/pressure relationships in other areas.

13. Exhaust into shared or recirculating HVAC systems, or other shared exhaust systems (bathroom exhaust) is not acceptable.

14. Install device (e.g., magnehelic, manometer, or digital monitoring) on exterior of work containment to continually monitor negative pressurization. The “ball in the wall” or similar apparatus are not acceptable.

15. Contain all trash and debris in the work area.

16. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.

17. Worker clothing must be clean and free of visible dust before leaving the work area anteroom.

18. Workers must wear shoe covers prior to entry into the work area. Shoe covers must be changed prior to exiting the anteroom to the occupied space (non-work area).

Damaged shoe covers must be immediately changed.

19. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.

20. Consider collection of particulate data during work to monitor and ensure that contaminates do not enter the occupied spaces. Routine collection of particulate samples may be used to verify HEPA filtration efficiencies.

Construction areas must be inspected by an infection preventionist or designee and engineering representative for discontinuation or downgrading of ICRA precautions.

Work Area Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

Removal of Critical Barriers:

1. Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed.

2. All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:

1. Carefully remove screws and painter tape.

2. If dust will be generated during screw removal, use hand-held HEPA vacuum.

3. Drywall cutting is prohibited during removal process.

4. Clean all stud tracks with HEPA vacuum before removing outer hard barrier.

5. Use a plastic barrier to enclose area if dust could be generated.

Negative Air Requirements:

1. The use of negative air must be designed to remove contaminates from the work area.

2. Negative air devices must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.

HVAC systems:

1. Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed.

2. Verify that HVAC systems are clean and operational.

3. Verify the HVAC systems meets original airflow and air exchange design specifications.

It is the Contractor's Responsibility to provide the following Infection Control Precautions depending upon the Area Class Designation

During Construction Project

C

LA

S S

I

Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

HVAC Systems:

1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.

2. Verify the HVAC systems meet original airflow and air exchange design specifications.

Upon Completion of Project

1. Execute work by methods to minimize raising dust from construction operations.

2. Perform noninvasive work activity as to not block or interrupt patient care.

3. Perform noninvasive work activities in areas that are not directly occupied with patients.

4. Perform noninvasive work activity in a manner that does not create dust.

5. Immediately replace any displaced ceiling tile before leaving the area and/or at end of noninvasive work activity.

C

LA

S S

II

Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

HVAC Systems:

1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.

2. Verify the HVAC systems meet original airflow and air exchange design specifications.

1. Includes all activities required by Class I

2. Perform only limited dust work and/or activities designed for basic facilities and engineering work.

3. Perform limited dust and invasive work following standing precautions procedures approved by the organization.

4. This Class of Precautions must never be used for construction or renovation activities.

5. Provide active means to prevent airborne dust from dispersing into atmosphere.

6. Water mist work surfaces to control dust while cutting.

7. Seal unused doors with duct tape.

8. Block off and seal air vents.

9. Replace adhesive walk-off mats at entrance and exit of work area. Replace used mats in accordance with manufacturer's recommendations.

10. Remove or isolate HVAC system in area where work is being done to prevent contamination of duct system.

Construction areas must be inspected by an infection preventionist or designee and engineering representative for discontinuation or downgrading of ICRA precautions.

Work Area Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

Removal of Critical Barriers:

1. Critical barriers must remain in place during all work involving drywall removal, creation of dust and activities beyond simple touch-up work. The barrier may NOT be removed until a work area cleaning has been performed.

2. All (plastic or hard) barrier removal activities must be completed in a manner that prevents dust release. Use the following precautions when removing hard barriers:

1. Carefully remove screws and painter tape.

2. If dust will be generated during screw removal, use hand-held HEPA vacuum.

3. Drywall cutting is prohibited during removal process.

4. Clean all stud tracks with HEPA vacuum before removing outer hard barrier.

5. Use a plastic barrier to enclose area if dust could be generated.

Negative Air Requirements:

1. The use of negative air must be designed to remove contaminates from the work area.

2. Negative air devices must remain operational at all times and in place for a period after completion of dust creating activities to remove contaminants from the work area and before removal of critical barriers.

HVAC systems:

1. Upon removal of critical barriers, remove isolation of HVAC system in areas where work is being performed.

2. Verify that HVAC systems are clean and operational.

3. Verify the HVAC systems meets original airflow and air exchange design specifications.

CONSTRUCTION ACTIVITIES SHALL BE CLASSIFIED AS FOLLOWS UNLESS NOTED OTHERWISE:

1. INSTALLATION OF CABLE TRAY IN CORRIDOR CEILINGS SHALL BE CONSIDERED CONSTRUCITON ACTIVITY TYPE B.

2. ALL CONDUIT SPECIFIED TO BE INSTALLED IN WALL SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE C.

3. CONSTRUCTION OF NEW ROOMS SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE D.

4. INSTALLATION OF NEW DOORS TO OR FROM EXISTING SPACES SHALL BE CONSIDERED CONSTRUCTION ACTIVITY TYPE C.

C

LA

S S

II

I

1. Includes all activities required by Class II

2. Obtain Infection Control Permit from Hospital Safety Officer or Facilities

Management Maintenance and Engineering department before construction begins.

3. Provide active means to prevent airborne dust dispersion into the occupied areas.

4. Means for controlling minimal dust dispersion may include hand-held HEPA vacuum devices, polyethylene plastic containment, or isolation of work area by closing room door.

5. Remove or isolate return air diffusers to avoid dust from entering the HVAC system.

6. Remove or isolate the supply air diffusers to avoid positive pressurization of the space,

7. If work area is contained, then it must be neutrally to negatively pressurized at all times.

8. Seal all doors with tape that will not leave residue.

9. Contain all trash and debris in the work area.

10. Nonporous/smooth and cleanable containers (with a hard lid) must be used to transport trash and debris from the construction areas. These containers must be damp-wiped cleaned and free of visible dust/debris before leaving the contained work area.

11. Install a sticky (dust collection) mat at entrance of contained work area based on facility policy. Sticky mats must be changed routinely and when visibly soiled.

12. Maintain clean surroundings when area is not contained by damp mopping or HEPA vacuuming surfaces.

13. Clean construction area at the end of each shift by damp mopping or HEPA Vacuum.

For Type C activities, follow procedures for Class IV.

Cleaning:

1. Clean work areas including all environmental surfaces, high horizontal surfaces and flooring materials.

2. Check all supply and return air registers for dust accumulation on upper surfaces as well as air diffuser surfaces.

HVAC Systems:

1. Remove isolation of HVAC system in areas where work is being performed. Verify that HVAC systems are clean and operational.

2. Verify the HVAC systems meet original airflow and air exchange design specifications.

A

.F .F

A P

P R

O X

SUSPENDED

PLASTIC ZIPPER

WALL CURTAIN

BARRIER

POST ICRA, ILSM, FIRE

INSPECTION SHEETS

VISIBLE TO PUBLIC

HEPA NEGATIVE

AIR UNIT

FINISHED FLOORING TO BE KEPT

CLEAN. FLOORS NOT BEING REPLACED

MUST BE PROTECTED. COVER WITH

ROSIN PAPER / FIRE RATED PLYWOOD.

REMOVE CMU AT EXTERIOR

WALL FOR EXHAUST. SEAL

ALL AROUND. SECURE

OPENING WITH 3/4" PLYWOOD

AT EACH END OF SHIFT

COORDINATE LOCATION AND

HEIGHT WITH COR.

V .I

.F

E X

IS

T

IN

G

W A

L L

FLOOR SLAB ABOVE

CEILING

PLASTIC

WINDOW

SWIVEL CASTERS

WITH TWO

LOCKING BRAKES

MOBILE CART

A D

J U

S T

A B

L E

H

E

IG

H T

HEPA NEGATIVE

AIR UNIT

EXISTING

WALL

EXISTING

CEILING

FLEX DUCT

Engineers Architects

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

/2

/2

:5

:3

A

M C

U s e rs

\a c a b ra

\D o c u m e n ts \A

-2

-V A

H o u s to n -R e p r S rv r

R m a c a b ra

M U

S

.r v t

G-004

ICRA INFORMATION AND DETAILS

4 4AC

INVESTIGATE AND STOP

WATER INFILTRATION IN MAIN

SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030 JANUARY 31, 2025

100% BID DOCUMENTS

580-22-11022-228-Q39

WVS

Scale: 3/4" = 1'-0"

ICRA BARRIER WALL TYPE

Scale: 3" = 1'-0"

ILSM CONSTRUCTION EGRESS SIGNAGE

Scale: 1/4" = 1'-0"

PLASTIC BARRIER ENCLOSURE ELEVATION

Scale: 1/4" = 1'-0"

CROSS SECTION "A"

Scale: 1/4" = 1'-0"

ICRA MOBILE CONTAINMENT CART

W

AL

CORRIDOR

CIA-600

CLC

COURTYARD

DINING

1A-660

MECHANICAL

BAY - 6

1A-640

BR

1C-158B

LIV/DIN

1C-158

KITCHEN

1C-158A

BATH

1C-158D

CORRIDOR

1C-108

PVA SECY

1B-164

WAITING/RECEPTIONIST/WORK

AREA

1C-160

SUPERVISORS

OFFICE

1C-160C

NURSE

EXECUTIVE

1C-160F

CORRIDOR

1C-105

DIN/RECREATION

1C-111C

KITCHEN

1C-111

OFFICE

1C-109D

OFFICE

1C-109C

ELEVATOR

P-9

ELEVATOR

LOBBY

C1C-100

ELEVATOR

P-8

OFFICE

1C-160E

OFFICE

1C-160D

CANTEEN

COURTYARD

BC-403

MEXICAN FEATHER GRASS

AUTUMN CORAL® ENCORE® AZALEA

BLUE BOY DWARF ROSEMARY

ANNUAL FLOWERS

BLUE BOY DWARF ROSEMARY

NEW 6' HEIGHT WOOD

FENCE

VEGETABLE GARDEN (TYP.)

COMMON YARROW (YELLOW)

ENDLESS SUMMER® THE ORIGINAL HYDRANGEA

GARDEN SAGE

BUTTERFLY MILKWEED

MEXICAN FEATHER GRASS

AUTUMN CORAL® ENCORE® AZALEA

RED YUCCA

ANNUAL FLOWERS

ENDLESS SUMMER® THE ORIGINAL HYDRANGEA

COMMON YARROW (YELLOW)

SPIKE SPEEDWELL

BIG BLUE LILYTURF

HEAVY METAL SWITCH GRASS

1" = 5'

SCALE IN FEET

5 2.5 5 10

Foresite Group, LLC 3740 Davinci Ct.

Suite 100 Peachtree Corners, GA 30092 o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net

1) CONTRACTOR SHALL NOTIFY DESIGN PROFESSIONAL OF ANY

DISCREPANCIES BETWEEN THE EXISTING CONDITIONS IN THE

FIELD AND THE SURVEY SHOWN ON THE PLANS BEFORE

PROCEEDING WITH ANY NEW CONSTRUCTION.

2) THERE MAY BE ADDITIONAL UTILITIES NOT SHOWN ON THESE

PLANS. IT SHALL BE THE RESPONSIBILITY OF THE

CONTRACTOR TO FIELD VERIFY THE LOCATIONS OF ALL

UTILITIES WITHIN THE LIMITS OF CONSTRUCTION AND NOTIFY

THE ENGINEER AND COR IN CASE OF DISCREPANCIES THAT

AFFECT THE CONSTRUCTION PROJECT.

3) THE CONTRACTOR SHALL NOT DEVIATE FROM THESE PLANS

AND SPECIFICATIONS WITHOUT THE PRIOR WRITTEN

CONSENT OF THE VA COR.

4) ALL BUFFERS, TREE SAVE AREAS, AND UNDISTURBED AREAS

SHALL BE CLEARLY IDENTIFIED BY FLAGGING AND/OR

FENCING PRIOR TO COMMENCEMENT OF ANY LAND

DISTURBANCE.

5) NO OUTSIDE STORAGE BEYOND THE WORK AREA IS

PROPOSED. THIS INCLUDES SUPPLIES, VEHICLE, EQUIPMENT,

PRODUCTS, ETC.

6) ALL EROSION, SEDIMENT CONTROL AND TREE PROTECTION

MEASURES SHALL BE INSTALLED PRIOR TO ANY WORK

INCLUDING DEMOLITION.

7) CONTRACTOR SHALL BE RESPONSIBLE FOR CONSTRUCTION

AND MAINTENANCE OF EROSION AND SEDIMENTATION

CONTROLS DURING CONSTRUCTION UNTIL PERMANENT

GROUNDCOVER IS ESTABLISHED IN ALL DISTURBED AREAS.

8) SEE LP501 AND SPECIFICATIONS SECTIONS 32900 FOR ALL

LANDSCAPE PLANT MATERIAL REQUIREMENTS.

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

Engineers Architects

100% BID DOCUMENTS

22-228-Q39

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

INVESTIGATE AND STOP

WATER INFILTRATION INTO

MAIN SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030

580-22-110

LP101

1 2YHJANUARY 31, 2025 PT

COURTYARD LANDSCAPE PLAN

Revisions: Date

Drawing Title

Approved

Project Title

Location

VA PROJECT NUMBER

Building Number

Drawing Number

Dwg of

VA FORM 08-6231

Office of Construction and Facilities Management

CONSULTANTS: PROJECT MANAGER

SHEET NOTES:

Date Checked Drawn

FULLY SPRINKLERED

ACG Project Number

Headquarters:

Apogee Consulting Group, P.A.

1151 Kildaire Farm Road, Suite 120 Cary, North Carolina 27511 www.acg-pa.com 919-858-7420 U.S. Department of Veterans Affairs# © COPYRIGHT Apogee Consulting Group, P.A.

Engineers Architects

100% BID DOCUMENTS

22-228-Q39

N

AREA OF WORK

KEY PLAN

SCALE: NO SCALE

INVESTIGATE AND STOP

WATER INFILTRATION INTO

MAIN SERVER ROOMS

MICHAEL E. DEBAKEY VA

MEDICAL CENTER

2002 HOLCOMBE BLVD

HOUSTON, TX 77030

580-22-110

1) CONTRACTOR SHALL NOTIFY DESIGN PROFESSIONAL OF ANY

DISCREPANCIES BETWEEN THE EXISTING CONDITIONS IN THE

FIELD AND THE SURVEY SHOWN ON THE PLANS BEFORE

PROCEEDING WITH ANY NEW CONSTRUCTION.

2) THERE MAY BE ADDITIONAL UTILITIES NOT SHOWN ON THESE

PLANS. IT SHALL BE THE RESPONSIBILITY OF THE

CONTRACTOR TO FIELD VERIFY THE LOCATIONS OF ALL

UTILITIES WITHIN THE LIMITS OF CONSTRUCTION AND NOTIFY

THE ENGINEER AND COR IN CASE OF DISCREPANCIES THAT

AFFECT THE CONSTRUCTION PROJECT.

3) THE CONTRACTOR SHALL NOT DEVIATE FROM THESE PLANS

AND SPECIFICATIONS WITHOUT THE PRIOR WRITTEN

CONSENT OF THE VA COR.

4) ALL BUFFERS, TREE SAVE AREAS, AND UNDISTURBED AREAS

SHALL BE CLEARLY IDENTIFIED BY FLAGGING AND/OR

FENCING PRIOR TO COMMENCEMENT OF ANY LAND

DISTURBANCE.

5) NO OUTSIDE STORAGE BEYOND WORK LIMITS IS PROPOSED.

THIS INCLUDES SUPPLIES, VEHICLE, EQUIPMENT, PRODUCTS,

ETC.

6) ALL EROSION, SEDIMENT CONTROL AND TREE PROTECTION

MEASURES SHALL BE INSTALLED PRIOR TO ANY WORK

INCLUDING DEMOLITION.

7) CONTRACTOR SHALL BE RESPONSIBLE FOR CONSTRUCTION

AND MAINTENANCE OF EROSION AND SEDIMENTATION

CONTROLS DURING CONSTRUCTION UNTIL PERMANENT

GROUNDCOVER IS ESTABLISHED IN ALL DISTURBED AREAS.

8) SEE LP501 AND SPECIFICATIONS SECTIONS 32900 FOR ALL

LANDSCAPE PLANT MATERIAL REQUIREMENTS.

9) COORDINATE LANDSCAPE PLANS WITH EROSION CONTROL

FINAL STABILIZATION MEASURES.

10) REFER TO SHEET LP101 FOR OVERALL LANDSCAPE PLAN .

Foresite Group, LLC 3740 Davinci Ct.

Suite 100 Peachtree Corners, GA 30092 o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net o | 770.368.1399 f | 770.368.1944 w | www.foresitegroup.net

SHRUB PLANTING

3/4" = 1'-0"

NOTES:

1- SHRUBS SHALL BE OF SPECIMEN QUALITY.

2- SEE SPECIFICATIONS FOR FURTHER REQUIREMENTS RELATED TO THIS DETAIL.

LOOSEN ALL HARDPAN.

USE 50/50 PLANTING

MIX WITH NATIVE SOIL.

3x's widest dimension of root ball.

ROOTBALL.

4" HIGH X 8" WIDE ROUND -

TOPPED SOIL BERM ABOVE

ROOT BALL SURFACE SHALL BE

CONSTRUCTED AROUND THE

ROOT BALL. BERM SHALL BEGIN

AT ROOT BALL PERIPHERY.

PRIOR TO MULCHING, LIGHTLY

TAMP SOIL AROUND THE ROOT

BALL IN 6" LIFTS TO BRACE

SHRUB. DO NOT OVER

COMPACT. WHEN THE

PLANTING HOLE HAS BEEN

BACKFILLED, POUR WATER

AROUND THE ROOT BALL TO

SETTLE THE SOIL.

3" LAYER OF MULCH.

NO MORE THAN 1" OF

MULCH ON TOP OF ROOT

BALL. (SEE NOTES ON

LANDSCAPE PLAN FOR

TYPE OF MULCH).

ROOT BALL RESTS

ON EXISTING OR

RECOMPACTED

SOIL.

SLOPE SIDES OF

LOOSENED SOIL.

EXISTING SOIL.

FINISHED GRADE.

SHRUB.

SECTION VIEW

URBAN TREE FOUNDATION © 2014

OPEN SOURCE FREE TO USE

0001-01

GROUNDCOVER

3/4" = 1'-0"

EQ.EQ.

NOTES:

1- SEE PLANTING LEGEND FOR GROUNDCOVER SPECIES, SIZE, AND SPACING DIMENSION.

2- SMALL ROOTS (14" OR LESS) THAT GROW AROUND, UP, OR DOWN THE ROOT BALL PERIPHERY ARE CONSIDERED A NORMAL CONDITION IN CONTAINER PRODUCTION AND ARE ACCEPTABLE HOWEVER THEY SHOULD BE ELIMINATED AT THE TIME OF PLANTING. ROOTS ON THE PERIPERHY CAN BE REMOVED AT THE TIME OF PLANTING. (SEE ROOT BALL SHAVING CONTAINER DETAIL).

3- SETTLE SOIL AROUND ROOT BALL OF EACH GROUNDCOVER PRIOR TO MULCHING.

PLAN

SECTION VIEW

PAVEMENT.

SHREDDED HARDWOOD MULCH.

GROUNDCOVER PLANTS TO BE

TRIANGULARLY SPACED.

EXISTING SOIL.

8" OF MODIFIED SOIL TILLED WITH 50/50 MIX OF

4" PLANTING SOIL AND 4" NATIVE SOIL.

2 - 3" THICK LAYER OF

SHREDDED HARDWOOD MULCH.

FINISHED GRADE.

6" m in

URBAN TREE FOUNDATION © 2014

OPEN SOURCE FREE TO USE1

0003-01

SYMBOL QTY BOTANICAL / COMMON NAME CONT SPACING

SHRUBS

61 ASCLEPIAS TUBEROSA / BUTTERFLY MILKWEED 3 GAL 24" o.c.

27 HESPERALOE PARVIFLORA / RED YUCCA 3 GAL 30" o.c.

40 HYDRANGEA MACROPHYLLA `BAILMER` / ENDLESS SUMMER® THE ORIGINAL HYDRANGEA 3 GAL 42" o.c.

63 RHODODENDRON X `CONLED` / AUTUMN CORAL® ENCORE® AZALEA 3 GAL 30" o.c.

22 SALVIA ROSMARINUS `BLUE BOY` / BLUE BOY DWARF ROSEMARY 3 GAL 24" o.c.

GROUND COVERS

83 ACHILLEA MILLEFOLIUM / COMMON YARROW (YELLOW) 1 GAL 12" o.c.

47 SF ANNUAL FLOWERS 4"POT

191 SF LIRIOPE MUSCARI 'BIG BLUE' / BIG BLUE LILYTURF 4"POT

204 NASSELLA TENUISSIMA / MEXICAN FEATHER GRASS 1 GAL 18" o.c.

39 PANICUM VIRGATUM `HEAVY METAL` / HEAVY METAL SWITCH GRASS 1 GAL 30" o.c.

113 SALVIA OFFICINALIS / GARDEN SAGE 1 GAL 12" o.c.

19 VERONICA SPICATA / SPIKE SPEEDWELL 1 GAL 24" o.c.

PLANT SCHEDULE

LP501

2 2YHJANUARY 31, 2025 PT

COURTYARD LANDSCAPE DETAILS

S SS

AFF ABOVE FINISHED FLOOR

ACP/APC ACOUSTIC CEILING PANEL/

ACOUSTIC PANEL CEILING

ACT ACOUSTIC(AL) TILE

ADJ ADJUSTABLE

ADT'L ADDITIONAL

AGG AGGREGATE

ALT ALTERNATE

AL ALUMINUM

APPROX APPROXIMATE(LY)

ASPH ASPHALT

AUTO AUTOMATIC

B/O BOTTOM OF

BD BOARD

BLDG BUILDING

BLKG BLOCKING

BOT BOTTOM

BRG BEARING

CENTERLINE

C/C CENTER TO CENTER

CJ CONTROL JOINT

CLL CONTRACT LIMIT LINE

CEM CEMENT(ITIOUS)

CMU CONCRETE MASONRY UNIT

CLG CEILING

CLR CLEAR

COL COLUMN

CONC CONCRETE

CONST CONSTRUCTION

CONT CONTINUOUS

CPT CARPET

CT CERAMIC TILE

CTR CENTER(ED)

DF DRINKING FOUNTAIN

DS DOWNSPOUT

DBL DOUBLE

DEG DEGREE

DEMO DEMOLITION

DET/DTL DETAIL

DIA DIAMETER

DIM DIMENSION

DN DOWN

DWG(S) DRAWING(S)

E EAST

EC ELECTRICAL CONTRACTOR

EHO ELECTRICAL HOLD OPEN

EJ EXPANSION JOINT

EW EACH WAY

EA EACH

EIFS EXTERIOR INSULATION

FINISH SYSTEM

EL ELEVATION

ELEC ELECTRIC(AL)

ELEV ELEVATOR

EMER EMERGENCY

EQ EQUAL

EQUIP EQUIPMENT

EXIST EXISTING

EXT EXTERIOR

EWC ELECTRIC WATER COOLER

FD FLOOR DRAIN

FE FIRE EXTINGUISHER

FFE FINISH FLOOR ELEVATION

FV FIELD VERIFY

FEC FIRE EXTINGUISHER CABINET

FDN FOUNDATION

FIN FINISH

FLSHG FLASHING

FLR FLOOR

FRMG FRAMING

FT FOOT/FEET

FTG FOOTING

GC GENERAL CONTRACTOR

GA GAUGE

GALV GALVANIZED

GEN GENERAL

GYP GYPSUM

HM HOLLOW METAL

HDWR HARDWARE

HOL HOLLOW

HOR HORIZONTAL

HT HEIGHT

HVAC HEATING/VENTILATION/AIR

CONDITIONING

ID INSIDE DIAMETER

IN INCH

INCL INCLUDING

INSUL INSULATION

INT INTERIOR

JAN JANITOR

JT JOINT

LAV LAVATORY

LB(S) POUND(S)

L/S LANDSCAPE

LT LIGHT

MO MASONRY OPENING

MAS MASONRY

MAT'L MATERIAL

MAX MAXIMUM

MECH MECHANICAL

MFR MANUFACTURER

MIN MINIMUM

MISC MISCELLANEOUS

MTD MOUNTED

MTL METAL

N NORTH

NIC NOT IN CONTRACT

NTS NOT TO SCALE

NOM NOMINAL

OC ON CENTER

OD OUTSIDE DIAMETER

O TO O OUT TO OUT

OPNG OPENING

OPP OPPOSITE

OVHD OVERHEAD

PEB PRE-ENGINEERED BUILDING

PJF PREFORMED JOINT FILLER

PT PRESSURE TREATED

PERIM PERIMETER

PL PLATE

PLAM PLASTIC LAMINATE

PLBG PLUMBING

PLYWD PLYWOOD

PNT PAINT

PR PAIR

PTD PAINTED

PWR POWER

RB RUBBER BASE

RD ROOF DRAIN

RO ROUGH OPENING

RAD RADIUS

REC RECESSED

REINF REINFORCED

REQ'D REQUIRED

REV REVISED (REVISION)

RM ROOM

S SOUTH

SB SPLASH BLOCK

SF SQUARE FEET

SS STAINLESS STEEL

SIM SIMILAR

SPEC SPECIFICATIONS

SQ SQUARE

STD STANDARD

STL STEEL

STOR STORAGE

STRUCT STRUCTURAL

SUSP SUSPENDED

T&G TONGUE AND GROOVE

T/O TOP OF

TELE TELEPHONE

TRTD TREATED

TS TUBE STEEL

TYP TYPICAL

UNFIN UNFINISHED

UNO UNLESS NOTED OTHERWISE

VCT VINYL COMPOSITION TILE

VIF VERIFY IN FIELD

VERT VERTICAL

W WEST

W/ WITH

W/O WITHOUT

WC WATER CLOSET

WWF WELDED WIRE FABRIC

WD WOOD

WH WATER HEATER

WT WEIGHT

CL

DEMOLITION KEYNOTE WINDOW TYPE

DOOR NUMBER

TYPICAL KEYNOTE CEILING/ SOFFIT

HEIGHT

MATL

1'-0"

1. INDICATIONS OF PROJECT LIMITS OR LINES OF DEMARCATION ARE SHOWN FOR GENERAL SCOPE DEFINITION AND REFLECT THE UNDERSTANDING OF THE DESIGNER AS TO THE LIMITATIONS OF THE WORK AREA IN AN OCCUPIED AREA.