This is a technical specification document for Contract No. 524048, an agency-wide paving project administered by the Maryland Port Administration (MPA) at marine terminals in Baltimore, Maryland. The contract encompasses comprehensive pavement work including asphalt and concrete removal, pavement milling, base course installation, asphalt and concrete paving, pavement markings, joint sealing, track installation and removal, traffic maintenance, sediment and erosion control, and site-specific health and safety measures. The scope includes mobilization and demobilization, maintenance of traffic throughout operating marine terminals, handling of chrome-contaminated materials, railroad demolition and removal, and general site work. The contract is structured with multiple line items on a Price Proposal Form, including unit prices for various depths of pavement milling, concrete and asphalt removal, and track work, along with lump sum and allowance items for contingencies such as paving-related unanticipated additional work (Item 1001), test pavements (Item 1006), and ponding-related additional work (Item 1008). The specifications reference Maryland Department of Transportation State Highway Administration standards, American Railway Engineering & Maintenance of Way Association guidelines, and OSHA requirements.

No specific bid due date, award date, or contract term length is provided in this technical specifications exhibit. Compensation is structured through unit prices and lump sum allowances with no separate payment for mobilization, demobilization, or traffic maintenance, which are considered incidental to other contract items. Payment for unanticipated work is negotiated between the contractor and engineer or performed on a Force Account basis per General Provisions GP-9.02. The contract includes provisions for chrome ore processing residue (COPR) contaminated material handling with costs covered under allowance Item 2006, requiring contractor coordination with the MPA's Office of Environmental Quality. A Site-Specific Health and Safety Plan (Item 1009) is required with payment split 50 percent upon approval and the remainder prorated over the contract duration. The contractor must maintain insurance, provide a qualified Health and Safety Officer, and comply with federal, state, and local environmental and safety regulations. The contract allows the MPA to divide the project into separate, independent projects for its own convenience without additional compensation to the contractor for multiple mobilizations.

View the file

Other files

File Type Posted
524048 - Addendum 1.pdf PDF
524048 - AWP - Appendices.pdf PDF
524048 - AWP - Attachments All.pdf PDF
524048 - Agency Wide Paving RFP.pdf PDF
524048 - AWP - Exhibit II Price Proposal Form.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contract No.: 524048

CONTRACT NO. 524048

INDEX TO TECHNICAL SPECIFICATIONS

DIVISION 1 – GENERAL REQUIREMENTS

Section 01500 Mobilization and Demobilization Section 01560 Maintenance of Traffic Section 01700 Paving Related Unanticipated Additional Work Section 01701 Test Pavements Section 01800 Ponding Related Additional Work Section 01900 General Requirements for Track Installation

DIVISION 2 – SITE WORK

Section 02050 Pavement Milling Section 02150 Site Specific Health and Safety Plan Section 02220 Pavement Removal Section 02222 Railroad Demolition and Removal Section 02226 Handling and Hauling Chrome Contaminated Material Section 02230 Pipe and Inlet Removal Section 02300 Excavation and Embankment Section 02340 Soil Stabilization Geotextile Section 02345 Geotextile for Track Work Section 02370 Sediment and Erosion Control Section 02630 Storm Drain System Section 02720 Crushed Aggregate Base Courses Section 02726 Ballast Section 02746 Asphalt Pavements Section 02751 Concrete Pavements Section 02760 Pavement Markings Section 02765 Pavement Marking Removal Section 02770 Hot Mix Asphalt Curb Section 02820 Chain Link Fence Section 02840 Bollards Section 02841 Precast Concrete Traffic Barriers Section 02849 Metal Traffic Barriers Section 02975 Concrete and Asphalt Joint Sealing Section 02976 Pavement Reinforcing Fabric Section 02977 Cape Seal Section 02978 Fog Seal Section 02979 Cold-in-Place Recycling Section 02995 Utility Structures Section 02997 Sinkhole Stabilization and Repair

Contract No.: 524048

DIVISION 3 – CONCRETE

Section 03300 Cast-In-Place Concrete

DIVISION 5 – METALS

Section 05651 Rail Welding Section 05653 Other Track Materials Section 05665 Joints and Joint Bars Section 05671 Ballasted Track Construction Section 05681 Special Trackwork Section 05696 Rail Procurement

DIVISION 6 – WOOD, PLASTICS, AND COMPOSITES

Section 06135 Timber Cross Ties

DIVISION 16 –ELECTRICAL

Section 16010 Electrical Work

Contract No. 524048 01500-1

SECTION 01500

MOBILIZATION AND DEMOBILIZATION

PART 1 - GENERAL

1.1 SCOPE

A. The work covered by this Section includes the furnishing of all materials and equipment and the performing of all labor for the assembling and setting up for the project. This shall include the movement of personnel and equipment to the project site, Contractor’s field offices, trailers, shops, storage areas, sanitary and other facilities required by the Specifications and Special Provisions of the Contract as well as any applicable local or State laws and all other work and operations which must be performed prior to beginning work on compensable items. The cost of required insurance, bonds and any other initial expense required for the start of work on this project shall be included in this item. The adequacy of the Contractor’s facilities, except as noted above, shall be determined by the Contractor.

B. The work further includes the following:

1. Third-party surveys as noted in Paragraph SP-19 of the Special Provisions.

2. Maintenance of all Contractor access and haul roads.

3. Maintenance of all Contractor staging and work areas in a clean and usable condition satisfactory to the Engineer.

4. Demobilization of all equipment, material and personnel upon completion of the project and the clean-up of the project site.

5. Providing utility location services, temporary support and protection for existing utility lines in the project area and temporary utility services.

6. Furnishing all equipment, labor and materials necessary for the preparation, revision, implementation and supervision of a site-specific health and safety plan

(SSHASP).

C. The Administration reserves the right to accomplish this project in as many separate and independent projects as it deems necessary, including for its own convenience, during the term of the contract, and in accordance with the conditions set forth under the Special Provisions of these specifications. No additional compensation shall be made to the Contractor for the number of times he/she or its subcontractor(s) have to mobilize, demobilize, and remobilize.

D. At the completion of work all areas used for storage of equipment or materials shall be restored to their original condition as existed prior to commencement of mobilization operations. No additional compensation shall be provided for pavement repairs, and regrading in these areas, or for any restoration activity required by the Engineer. This requirement may apply to each individual “Task” during the life of this Contract.

01500-2

PART 2 - PRODUCTS

2.1 MATERIALS

A. Required materials that are not to be a part of the completed Contract shall be determined by the Contractor.

PART 3 - EXECUTION

3.1 INSTALLATION

A. All work performed in providing the facilities and services shall be done in a safe and workmanlike manner.

PART 4 - COMPENSATION

4.1 MEASUREMENT

A. Mobilization and Demobilization shall not be measured

4.2 PAYMENT

A. No payment shall be made for any work associated with mobilization and demobilization under this Contract. All costs incurred thereby shall be considered incidental to other items specified in the contract documents, including furnishing all supervision, labor, equipment, tools, materials, and any other incidentals necessary to complete this item in accordance with these specifications.

B. No additional payment shall be made for demobilization and remobilization due to shutdowns, suspensions of work, or for any other mobilization activities.

C. Quantity of work or lack thereof; the number of times, instances, intervals and/or duration of each “Task”; or conditions/limitations of each work schedule will not be considered a justification for adjustment to any contract unit prices bid and will not be considered a basis of a claim by the Contractor or his/her subcontractor(s) against the Administration.

END OF SECTION

01560-1 Contract No. 524048

SECTION 01560

MAINTENANCE OF TRAFFIC

PART 1 – GENERAL

A. The work covered by this Section includes the furnishing of all material, equipment and the performing of all labor for the maintenance of traffic within the MPA Marine Terminals throughout the duration of the Contract as shown on the Contract Drawings or as herein specified or directed by the Engineer.

B. This work shall include but is not limited to:

1. The installation, transportation, relocation, continuous maintenance, repair, and replacement of all protective devices required.

2. The immediate repair or replacement of protective devices as may be damaged by weather, vehicular traffic or other causes.

3. Protective devices shall include warning signs, arrow boards, traffic cones, traffic drums, barricades, temporary painted stripe markings, etc.

1.2 RELATED SECTIONS

A. Section 01500 Mobilization and Demobilization

B. Section 01700 Paving Related Unanticipated Additional Work

C. Section 01701 Test Pavements

D. Section 01800 Ponding Related Additional Work

E. Section 02050 Pavement Milling

F. Section 02220 Pavement Removal

F. Section 02746 Asphalt Pavements

G. Section 02751 Concrete Pavements

H. Section 02760 Pavement Markings

I. Section 02765 Pavement Marking Removal

J. Section 02975 Concrete and Asphalt Joint Sealing

01560-2 Contract No. 524048

1.3 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only.

B. The Maryland Department of Transportation State Highway Administration (MDOT

SHA) Book of Standards for Highways, Incidental Structures and Traffic Control Applications, Category 1, with all latest addenda are to be used for this Section, except as modified herein.

C. The Maryland Department of Transportation State Highway Administration (MDOT

SHA) Standard Specifications for Construction and Materials issued 2020 with all latest addenda are to be used for this Section, except as modified herein.

D. Maryland Manual on Uniform Traffic Control Devices (MD-MUTCD).

E. General Provisions Section 7, Paragraph 7.09 and 7.10.

F. Unless otherwise indicated, the most recent edition of the specification, including any

Revisions, shall be used.

1.4 SUBMITTALS

A. Submit the following in accordance with the Special Provisions, SP-16 “Submittals” of these Specifications.

B. The Contractor shall submit a detailed Traffic Control Plan/Work Zone Plan and work schedule, which least interferes with ongoing Terminal operations, for the approval of the Engineer prior to commencing work, using MDOT SHA Book of Standards for Highways, Incidental Structures and Traffic Control Applications and the MD- MUTCD Control Devices as minimum guidelines.

C. The Traffic Control Plan/Work Zone Plan submitted by the Contractor shall indicate the nature and location of the work, any proposed obstructions or other hazards to traffic, the approximate number of men to be engaged, the types and amount of equipment to be employed. The plan shall also include the lengths of time during which it is anticipated the hazards or obstructions to traffic will exist, a signing plan and the means proposed by the Contractor for the protection of the public and his own personnel and equipment. The Plan must adhere to the requirements of MDOT SHA Book of Standards when impacting traffic on local and state roads.

D. All vehicles and construction equipment entering or leaving the project site and work area must follow the traffic flow pattern as established by the Traffic Control Plan.

E. The MDOT SHA Book of Standards for Highways, Incidental Structures and Traffic Control Applications and the MD-MUTCD Control Devices are to be considered as minimum guidelines only and may be adjusted at the discretion of the Engineer as field

01560-3 Contract No. 524048 conditions require.

1.5 RESPONSIBILITY OF CONTRACTOR

A. The work on this Contract is being performed at operating marine terminals with heavy truck, vessel and equipment traffic. The Contractor shall stage, store or park equipment, vehicles and material at the location(s) shown on the Traffic Control Plan/Work Zone Plan or at the locations indicated by the Engineer.

B. Traffic within the Marine Terminals must be maintained and protected at all times.

Precautions must be taken for the protection of terminal personnel as well as the Contractor's personnel and equipment. The Terminal vehicular traffic shall not be interrupted by the Contractor's equipment and construction activities except as noted in the Contract Documents during flagging operations.

C. Traffic within MPA Marine Terminals is under the control of the Maryland Transportation Authority Police.

D. Compliance with all prescribed safety precautions contained herein shall not relieve the Contractor of his primary responsibility to take all necessary measures to protect and safeguard the work, nor relieve him of any responsibilities prescribed by GP Section 7.

All provisions herein are in addition to the requirements of the Traffic Control Manual.

E. Parking for the Contractor’s employees’ private vehicles shall either be within the designated staging areas or at the designated remote parking area as directed by the Engineer. The Contractor is responsible for providing any shuttle service between the parking area and the jobsite.

F. Maintenance of Traffic shall be continuously inspected. Contractor to respond to reports of problems within thirty minutes of notice.

PART 2 – PRODUCTS

2.1 TRAFFIC CONTROL DEVICES

A. Traffic control devices shall be in accordance with the MSHA Standard Specifications and the MD-MUTCD.

PART 3 – EXECUTION

3.1 SITE ACCESSIBILITY

A. The Contractor shall note that the marine terminal will be in operation throughout the duration of this Contract. In addition, construction of Terminal facilities by other Contractors may be in progress. Uninterrupted access to the marine terminal must be maintained.

01560-4 Contract No. 524048

B. All construction operations within 30 feet of the traveled roadway edge shall be performed in the normal direction of traffic flow unless prior written permission is obtained from the Engineer. Work performed and equipment moving against the normal traffic flow pattern, other than during one-lane flagging operations, is strictly prohibited unless a written exception is granted by the Engineer.

C. Parking of the Contractors employees' vehicles, and storage of equipment and material will be as directed by the Engineer.

3.2 MAINTENANCE OF PROTECTIVE DEVICES

A. The warning signs, traffic cones, drums, pavement markings, arrow panels and other protective devices and equipment required by this contract for the maintenance and protection of traffic during construction operations shall remain the property of the Contractor. They shall be moved and relocated as often as necessary to conform to the limits of construction and keep the restrictions to traffic flow at a minimum. Failure to heed this provision shall be sufficient cause for discontinuation of construction operations until remedial action has been taken to the satisfaction of the Engineer.

When no longer needed, these devices, etc., shall be removed from the site to the satisfaction of the Engineer.

PART 4 – COMPENSATION

A. Maintenance of Traffic, including all temporary traffic control devices, pavement markings, arrow panels, flaggers and drums, shall not be measured, except for Temporary Concrete Jersey Barriers when requested by the Administration.

4.2 PAYMENT

A. No payment will be made for any work associated with “Maintenance of Traffic” under this contract. All costs incurred thereby shall be considered incidental to other items specified in the contract documents, including furnishing all supervision, labor, mobilization and demobilization, equipment, tools, materials, and any other incidentals necessary to complete this item in accordance with these specifications.

B. Payment for “Temporary Concrete Jersey Barriers,” complete in place, shall be made from the allowance amount under Item No. 1007 on the Price Proposal Form. When Temporary Concrete Jersey Barriers are requested by the Administration, payment will be made per third party invoicing. The Contractor shall provide proof of purchase for reimbursement.

C. The above price shall include all the work described in this Section and shown on the

Contract Drawings including all labor, materials, services and equipment necessary to complete the work in every respect to the satisfaction of the engineer.

01700-1

SECTION 01700

PAVING RELATED UNANTICIPATED ADDITIONAL WORK

A. The work covered by this Section includes the furnishing of all materials, equipment and the performing of all labor to complete any paving related unanticipated additional work as directed by the Engineer.

B. This work shall include but is not limited to: paving related additional work not included in the scope of any other unit price or lump sum item on the Price Proposal Form. This shall include hidden or unforeseen site conditions and approved extra work required by the Engineer after award of the Contract that was not intentionally withheld prior to contract advertisement.

C. This contingency allowance is for the exclusive use of the Maryland Port

Administration and is to be distributed at its sole discretion.

D. Any work to be performed under this Section shall be approved in writing and shall be authorized at the discretion of the Engineer.

E. Any paving related authorized additional work shall not include any extension of time to complete the contract, except as separately approved in writing by the Engineer.

A. Section 01560 Maintenance of Traffic

B. Section 01701 Test Pavements

C. Section 02050 Pavement Milling

D. Section 02220 Pavement Removal

E. Section 02300 Excavation and Embankment

F. Section 02720 Crushed Aggregate Base Courses

G. Section 02746 Asphalt Pavements

H. Section 02751 Concrete Pavements

I. Section 02770 Hot Mix Asphalt Curb

01700-2

J. Section 02975 Concrete and Asphalt Joint Sealing

1.3 REFERENCES

A. The Maryland Department of Transportation State Highway Administration (MDOT SHA) “Standard Specifications for Construction and Materials” and Maryland Standard Method of Tests (MSMT) with all latest addenda are to be used for this Section, except as modified herein.

PART 2 - PRODUCTS

2.1 MATERIAL

A. Any material to be used under this Section shall be approved by the Engineer before purchase.

B. Any equipment to be used under this Section shall be approved by the Engineer before its use.

3.1 GENERAL

A. The Contractor’s methods and techniques that he proposes to utilize in performing the work shall be subject to the approval of the Engineer.

4.1 GENERAL

A. After receiving the request for paving related unanticipated additional work from the Engineer, which will outline the scope of work to be done, the Contractor shall submit a price proposal to the Engineer. This price proposal shall include estimated quantities, unit prices and lump sum prices for those items not already included in the Price Proposal Form. If the Contractor and the Engineer cannot successfully negotiate the cost for the unanticipated additional work, then the Engineer may direct the Contractor to perform the work on a Force Account basis as set forth in Paragraph GP-9.02 Force Account Work of the General Provisions. All paving and non-paving related to unanticipated work shall still be performed in accordance with the respective specification(s) included in the Contract when possible. If the work differs and is not defined under any of the specifications included in the Contract, the Engineer will collaborate with the Contractor to develop the specific details and specifications.

B. For paving related to unanticipated work, test pavement shall be measured as indicated in Section 01701, Test Pavement.

4.2 MEASUREMENT

A. Unanticipated additional work shall be measured as stated in Paragraph 4.1 above.

01700-3

4.3 PAYMENT

A. Payment for “Paving Related Unanticipated Additional Work,” complete in place, shall be made from the allowance amount under Item No. 1001 on the Price Proposal Form.

B. The above price shall include all work described in this Section and approved by the Procurement Officer and the Engineer including mobilization, demobilization, maintenance of traffic, all labor, services, equipment and materials necessary to complete the work in every respect to the satisfaction of the Engineer.

Contract No 524048 01701-1

SECTION 01701

TEST PAVEMENTS

A. The work covered by this Section includes the furnishing of all materials, equipment and the performing of all labor to complete any new test sections of unspecified pavements not otherwise called for within the scope of this Contract because of the use of different types of paving materials or equipment.

B. This work shall include but is not limited to: test sections of unspecified pavements not included in the scope of any other unit price or lump sum item on the Price Proposal Form. This shall include furnishing and placing pavements not otherwise specified within this contract for testing by the Administration.

C. The allowance is for the exclusive use of the Maryland Port Administration and is to be distributed at its sole discretion.

D. Any work to be performed under this Section shall be approved in writing and shall be authorized at the discretion of the Engineer.

E. Any authorized work under this section shall not include any extension of time to complete the contract, except as separately approved in writing by the Engineer.

B. Section 01700 Paving Related Unanticipated Additional Work

D. Section 02220 Pavement Removal

E. Section 02300 Excavation and Embankment

F. Section 02720 Crushed Aggregate Base Courses

G. Section 02746 Asphalt Pavements

H. Section 02751 Concrete Pavements

I. Section 02975 Concrete and Asphalt Joint Sealing

01701-2

1.1 REFERENCES

A. The publications listed below form a part of this specification to the extent referenced.

The publications are referred to in the text by the basic designation only.

B. Unless otherwise indicated the most recent edition of the publication, including any revisions, shall be used.

C. The Maryland Department of Transportation State Highway Administration (MDOT

SHA) “Standard Specifications for Construction and Materials” and Maryland Standard Method of Tests (MSMT) with all latest addenda are to be used for this Section, except as modified herein.

A. After receiving the request for test pavements from the Engineer, which will outline the scope of work to be done, the Contractor shall submit a price proposal to the Engineer. This price proposal shall include estimated quantities, unit prices and lump sum prices for those items not already included in the Price Proposal Form. If the Contractor and the Engineer cannot successfully negotiate the cost for the work, then the Engineer may direct the Contractor to perform the work on a Force Account basis as set forth in Paragraph GP-9.02 Force Account Work of the General Provisions.

A. Test Pavements shall be measured as stated in Paragraph 4. 1 above.

01701-3

4.3 PAYMENT

A. Payment for “Test Pavements,” complete in place, shall be made from the allowance amount under Item No. 1006 on the Price Proposal Form.

Engineer including all labor, services, mobilization, demobilization, maintenance of traffic, equipment and materials necessary to complete the work in every respect to the satisfaction of the Engineer.

01800-1

SECTION 01800

PONDING RELATED ADDITIONAL WORK

A. The work covered by this Section includes the furnishing of all materials, equipment and the performing of all labor to complete any ponding related additional work as directed by the Engineer.

B. This work shall include but is not limited to: topographic land surveying, engineering, and preparation of associated plans such as grading, drainage, and erosion and sediment control plans.

C. This contingency allowance is for the exclusive use of the Maryland Port

Administration and is to be distributed at its sole discretion.

D. Any work to be performed under this Section shall be approved in writing and shall be authorized at the discretion of the Engineer.

E. Any ponding related authorized additional work shall not include any extension of time to complete the contract, except as separately approved in writing by the Engineer.

B. Section 01701 Test Pavements

D. Section 02220 Pavement Removal

E. Section 02300 Excavation and Embankment

F. Section 02720 Crushed Aggregate Base Courses

G. Section 02746 Asphalt Pavements

H. Section 02770 Hot Mix Asphalt Curb

I. Section 02975 Concrete and Asphalt Joint Sealing

J. Section 02997 Sinkhole Stabilization and Repair

01800-2

1.3 REFERENCES

A. The Maryland Department of Transportation State Highway Administration (MDOT

SHA) Book of Standards for Highways, Incidental Structures and Traffic Control Applications, May 2020.

B. The Maryland Department of Transportation State Highway Administration (MDOT SHA) “Standard Specifications for Construction and Materials,” Book of Standards for and Maryland Standard Method of Tests (MSMT) with all latest addenda are to be used for this Section, except as modified herein.

1.4 SUBMITTALS

A. General: Submit the following in accordance with the Special Provisions, SP-16 "Submittals", of these Specifications:

1. The Contractor shall provide a work proposal to the Engineer for approval prior to commencing work.

B. The Contractor shall employ and pay for the services of a competent registered professional engineer and/or registered land surveyor, to be approved by the Engineer, who shall furnish all lines and grades required by these Specifications.

C. The Contractor shall be responsible for all necessary field surveys required for the project, which shall conform to the Maryland Grid System NAD 83/91 and NAVD88 Survey Control System.

D. The Contractor shall utilize Microstation files, including data collector survey and photogrammetry in their design and drafting. The Contractor shall utilize the Microstation drafting software packages Version V8 or later. All Microstation files

01800-3 shall conform to current MPA CAD Standards and shall be provided to MPA prior to the start of any related construction work.

E. The Contractor shall provide a licensed Professional Engineer or Land Surveyor in the

State of Maryland with experience in drainage design and construction to ensure all pavement areas are in conformance with line, grade and cross slope.

F. The Contractor shall construct a pavement surface that matches the line, grade and cross slope shown on the Contractor’s Release for Construction Plans within the following tolerances:

1. Ensure an approved 10 ft straightedge is available at all times. The surface of each pavement course shall be true to the established line and grade after final compaction of each course. The surface shall also be sufficiently smooth so that the surface does not deviate more than 1/8 in. when the straightedge is placed parallel to the centerline. The transverse slope of the finished surface of each course shall not deviate more than 3/16 in. when the straightedge is placed perpendicular to the centerline.

2. Check transverse joints using the straightedge immediately after the initial rolling.

When the surface of each course varies more than 1/8 in. from true, make immediate corrections so the finished joint surface is within tolerance.

G. The following items shall be included in the design plan documents as applicable to the work proposed:

1. Storm Drain Plans as necessary.

2. Pipe profiles and structure schedules for all storm drain systems.

a. Profiles shall be at a scale of 1 in. = 50 ft. horizontal and 1 in. = 5 ft. vertical.

The 10-year hydraulic gradient and existing and proposed ground, proposed pipe, existing and proposed utilities, proposed outlet protection, and existing structures shall be shown on all storm drain profiles.

3. Details for all non-standard drainage structures as necessary.

4. Hazardous material spill containment plans as necessary.

5. The Contractor shall develop ESC Plans that include the following:

a. Plans for both initial and final phases of the construction are required. Plans for interim phases may also be required by MPA to ensure adequate controls throughout project duration. These interim phase plans shall be coordinated with traffic control stages. The plans require one-foot contouring for all phases at the same scale as the roadway plans.

01800-4

b. The initial phase plan shall detail the implementation of erosion and sediment control measures necessary to complete the clearing and grubbing and the initial stages of the Traffic Control Plan (TCP).

c. The final phase shall detail the control measures required to move to final grade and accommodate interim traffic control phases.

d. Plans shall provide a detailed description of the Limit of Disturbance (LOD).

Maintenance of stream flow and maintenance of storm drain flow plans as required. This plan will be coordinated with the MDE Non-Tidal Wetland and Waterways Division to ensure compliance with ESC measures in areas subject to waterway construction permits. The Contractor shall be responsible for all revisions due to MDE review and comment.

e. The plans shall be sealed and signed by a Maryland Registered Professional

Engineer.

H. Design and construct all roadways to meet the following performance requirements:

1. Meet or exceed all MDOT SHA roadway design and safety guidelines as referenced above, outlined in these specifications, and in accordance with sound engineering principles.

2. All Roadway components shall be constructed within the defined right of way and easements.

I. The Contractor shall design and construct all roadway geometrics including horizontal alignment, vertical alignment, cross slopes, lane widths, turning radii for intersections, sidewalk widths, medians, pedestrian ramps, driveway entrances, and alley entrances in accordance with the requirements of this section and the Guidelines for roadway design.

J. Design criteria:

1. Positive drainage away from all structures towards inlets for captured runoff or berth fascia for direct runoff.

2. On wharf areas:

a. Minimum pavement slope = 1%

b. Maximum pavement slope = 2%

01800-5

3. Landside of wharf areas:

a. Minimum pavement slope = 1%

b. Maximum pavement slope = 4%.

A. After receiving the request for ponding related additional work from the Engineer, which will outline the scope of work to be done, including instances for Sinkhole Stabilization and Repair per Section 02997, the Contractor shall submit a price proposal to the Engineer. This price proposal shall include estimated quantities, unit prices and lump sum prices for those items not already included in the Proposal Form. If the Contractor and the Engineer cannot successfully negotiate the cost for the ponding related additional work, then the Engineer may direct the Contractor to perform the work on a Force Account basis as set forth in Paragraph GP-9.02 Force Account Work of the General Provisions. All work shall still be performed in accordance with the respective specification(s) included in the Contract when possible. If the work differs and is not defined under any of the specifications included in the Contract, the Engineer will collaborate with the Contractor to develop the specific details and specifications.

B. For paving related to additional work, test pavement shall be measured as indicated in Section 01701, Test Pavement.

A. Ponding related additional work shall be measured as stated in Paragraph 4.1 above.

4.3 PAYMENT

A. Payment for “Ponding Related Additional Work,” complete in place, shall be made from the allowance amount under Item No. 1008 on the Proposal Form.

Procurement Officer and the Engineer including mobilization, demobilization, maintenance of traffic, all labor, services, equipment and materials necessary to complete the work in every respect to the satisfaction of the Engineer.

01900 - 1

SECTION 01900

GENERAL REQUIREMENTS FOR TRACK INSTALLATION

A. The work covered by this Section includes providing information for the general requirements for track installation as shown on the Contract Drawings and as herein specified or directed by the Engineer.

B. This information shall include but is not limited to the installation of new track.

A. Section 02222 Railroad Demolition and Removal Work

A. Pertinent provisions of the following listed standards and publications shall apply to the Work, except as they may be modified herein, and are hereby made part of these Specifications to the extent required.

1. American Railway Engineering & Maintenance of Way Association (AREMA), Manual for Railway Engineering, herein referred to as the AREMA Manual.

2. American Railway Engineering & Maintenance of Way Association (AREMA), Portfolio of Trackwork Plans, herein referred to as the AREMA Portfolio.

3. Specifications required by the relevant Rail Authority.

1.4 DEFINITIONS

A. The use of the following terms in these Specifications shall be interpreted as specified herein:

1. Ballast - An integral part of the track structure, generally composed of graded crushed stone, in which ties are embedded.

2. Cross level is the difference in elevation of the tops of heads of opposite rails measured at right angles to the track alignment.

3. Grade Crossing - The crossing of a railway track and a vehicular roadway at the same elevation.

4. Joint Bar - Device used to join the abutting ends of contiguous rails of the same cross section.

5. Joint Bar, Compromise - A joint bar used to connect contiguous rails of different cross sections.

6. Joint Bar, Insulated - Joint bar used to arrest the flow of electric current between contiguous rails. Standard types are bonded and non-bonded.

7. Outside Rails - On curved track, the rail farthest from the curve center; the rail with the longer radius. Also referred to as the "high rail."

8. Premium Rail (High Strength Rail) - Rail having greater hardness than standard rail for use at locations of high track wear. Premium rail shall be fully heat-

01900 - 2 treated.

9. Profile Grade Line (PGL) - The datum line which defines the vertical alignment of the track, applied at the top of the rails on tangent and the top of the inside (low) rail on curves.

10. Rail Anchor - A device which clamps to the base of a rail and bears against the side of a cross tie to restrain longitudinal movement of the rail.

11. Rail, Tee - The common class of steel rail design symmetrical about the vertical axis and which approximately resembles an inverted letter "T."

12. Running Rails - The rails of a track on which the tread of the rail vehicle wheels ride.

13. Spikes, Cut or Hair Pin Spring Type - Component of ballasted track construction which fastens rails and tie plates to timber cross ties.

14. Spiral - A curve of varying radius used to connect circular curves with tangents or contiguous circular curves of different radius for the purpose of reducing the sudden lateral force associated with a change in horizontal direction.

15. Sub-Ballast - A material superior in composition to the subgrade material which provides a semi-impervious layer between the track ballast and the subgrade to provide better drainage and distribution of loads to the subgrade.

16. Subgrade - The finished ground below the level of sub-ballast.

17. Superelevation - In curved track, the amount in inches that the outside rail is raised above the inside rail. The inside rail elevation is maintained at the PGL top of rail profile.

18. Top of Rail (T/R) - That portion of the running rail that follows the PGL.

19. Track, Ballasted - Track constructed of rails, crossties, tie plates, and rail fastenings set in ballast.

20. Track Foot - Unit of measurement for all types of track construction; measured along the centerline of track.

21. Track Profile - The running surface along the top of the grade rail. On curves, the grade rail is the inside rail.

22. Track Surface - The relationship of opposite rails to each other in profile and cross level.

23. Trackway - The foundation on which the track structure is constructed.

1.5 SYSTEM DESCRIPTION

(NOT USED)

1.6 SUBMITTALS:

A. General: Submit the following in accordance with Special Provision SP-14

“Submittals” of the Special Provisions.

B. Contractor shall submit Certificates of Compliance as may be required by the following:

1. Regulations, standards and recommended practices for all materials, tools, labor, equipment, procedures including hauling, shipping, handling, unloading, stockpiling, and installing, and incidental work:

a. Codes and regulations of the jurisdictional authorities.

b. AREMA Manual for Railway Engineering.

01900 - 3

C. Submit the method of handling, shipping, unloading, and stacking of rail for review and acceptance at least four weeks prior to shipping of the rail.

D. Submit the following lists of equipment to be used at least 30 days prior to their use in the work:

1. Construction equipment to be used during the trackwork construction

2. On-track equipment proposed for use

1.7 QUALITY ASSURANCE

A. Contractor shall perform all measures necessary to assure quality of the Work. This shall include source quality control and field quality control requirements specified in these Specifications.

1.8 DELIVERY, STORAGE AND HANDLING

A. Delivery, storage and handling of crossing panels shall be in accordance with the manufacturer’s recommendations.

B. Storage and handling of existing rails to be reused in the finished work shall be in a manner that will not damage the rails by impact or bending.

1.9 PROJECT CONDITIONS

A. The Contractor is advised that a staging area has been designated for materials storage. These areas are shown on the erosion and sediment control drawings of the Contract Drawings.

1.10 INSURANCE

A. The Contractor shall acquire a railroad protective liability insurance policy naming the Maryland Port Administration (Administration) as the insured, and the amounts and limits as specified by the Administration, for any work that takes place within 50' of any rail line.

PART 2 - PRODUCTS

NOT USED

3.1 CONSTRUCTION EQUIPMENT

A. The Contractor shall prepare a list of construction equipment to be used during the trackwork construction. The list shall be submitted for review 30 days before such equipment shall be used in the Work. Acceptance by the Engineer indicates general acceptability of the type of equipment for the work planned.

B. Clearance for the Contractor's on-track equipment shall conform to AREMA criteria and COMAR. Exceptions to this will not be allowed unless agreed to by the Administration. A complete description of any on-track equipment proposed for use by the Contractor shall be submitted. The submittal shall include a drawing showing

01900 - 4 the outline of the proposed equipment superimposed on a track cross section.

C. The Contractor's equipment shall not exceed Cooper E-80 loading. The Contractor shall verify that proposed equipment meets these requirements.

3.2 TRACK GEOMETRY

A. Track shall be installed to conform to the alignment and profile criteria as specified herein, and in conformance with the Contract Drawings.

B. Track gauge, guard rail gauge, flangeway width, curve radii, rail sections and special trackwork components shall be in accordance with AREMA Manual and AREMA Portfolio, except as may be modified in these Specifications.

C. For tangent track, the alignment is to be based on each centerline of track, equidistant between the gauge sides of the running rails as measured 5/8-inch below the top of the rail.

D. For curved track, the alignment is to be based on the centerline of track with the outside rail located 2 feet 4-1/4 inches radially from the centerline measured in the plane of the rails.

E. Track gauge shall be as follows:

1. Track gauge shall be measured between points 5/8 inch below the top of, and from inside face to inside face of, the running rails.

2. Tangent ballasted primary track gauge shall be 4'-8 1/2”.

3. Curved ballasted primary track gauge shall be 4'-8 1/2”.

F. Rail Cant:

1. Ballasted track shall be constructed with rail cant at 40 to 1 inward inclination of the rails.

01900 - 5

3.3 TRACK INSTALLATION TOLERANCES

The track installation tolerances shall be as specified in Table 1 below:

TABLE 1

TRACK INSTALLATION TOLERANCES

VERTICAL TRACK

ALIGNMENT

HORIZONTAL TRACK

ALIGNMENT

CONCRETE AT-

GRADE ALIGNMENT

Type of Class of Track

Gauge

Variation

Cross Level and Superelevation (Note 2)

Total Deviation (Note 1)

Middle Ordinate in 62' Chord

(Note 3)

(Note 1)

Middle Ordinate in 62' Chord

(Note 3)

(Note 1)

Middle Ordinate in 62' Chord

(Note 3) Ballasted Primary

+1/8" -0"

+/-1/8" +/-1/4" +/-1/8" +/-1/4" +/-1/8" +/-1/8" +/-1/8" (Note 1)

Concrete Grade Crossing

+1/8" -0"

+/-1/8" +/-1/4" +/-1/8" +/-1/4" +/-1/8" +/-1/8" +/-1/8"

(Note 1)

Asphalt Grade Crossing

+1/8" -0"

+/-1/8" +/-1/4" +/-1/8" +/-1/4" +/-1/8" +/-1/8" +/-1/8"

(Note 1)

NOTES:

1. Total deviation is measured between theoretical and actual alignments at any point in the track.

2. Rate of change variations from theoretical gauge, cross level and superelevation shall not exceed 1/8- inch per 31 feet of track.

3. Chord measurements may be taken at the mid-point between any two points 62 feet apart.

3.4 TYPES OF RAIL

A. All rails must be saw-cut. No torch-cut rails will be permitted for this project.

B. The rail section to be installed shall be noted on the Contract Drawings. Contractor shall conduct field survey to determine the horizontal alignment and profile grade of existing track at the points where the proposed track will connect to the existing track as shown on the Contract Drawings. Alignment of proposed track shall conform to the existing alignment, as shown on the Contract Drawings.

3.5 REMOVAL OF EXISITNG RAILS AND OTHER TRACK MATERIAL (OTM)

A. Contractor shall remove existing rail joints and/or saw cut, remove, store and/or dispose of the rail and OTM as specified in Section 02222, “Railroad Demolition and

01900 - 6

Removal Work”, at the locations shown on the Contract Drawings and as approved by the Engineer.

3.6 STORAGE AND INSTALLATION OF RAIL

A. Shop Drawings for track work shall be submitted for approval in accordance with Special Provision, SP-16, of this Specification.

B. Rails shall be handled carefully to avoid damage. Sufficient blocking and dunnage shall be used to prevent damage to rail during storage.

C. Store rails to minimize rust and corrosion. Store for easy handling and maintain cleanliness for visual inspection.

D. Storing of rail shall be done in such a way as to prevent sagging.

E. Rail shall be protected from the elements to prevent excessive corrosion during storage and protect rail ends from physical damage.

3.7 FINAL TRACK INSPECTION

A. In order to determine the acceptability of the new primary trackage for line and grade the Contractor will perform a track survey making and recording measurements of track gauge, cross level and alignment at least once every 31 feet of track centerline length. The purpose of this survey will be to detect instances where the track geometry does not meet the tolerances outlined in these specifications. The survey results and a written narrative will be submitted to the Engineer with all deviations from proposed line and grade highlighted and the amount of deviation clearly marked. The Engineer will be the sole judge of acceptability of the as-built track geometry for the Administration. Rail seat areas, tie plates and ties shall be checked to ensure that the rail is properly seated and that the base has full bearing on the surface.

B. The relevant Rail Authority will also perform a track inspection to verify that the track is safe for their operation. At the completion of work Contractor shall notify the Rail Authority to request a final inspection.

A. General Requirements for Track Installation will not be measured.

01900 - 7

A. Payment for General Requirements for Track Installation complete in place shall be taken to be included in and covered by the lump sum or unit prices for the respective items requiring General Requirements for Track Installation.

02050-1

SECTION 02050

PAVEMENT MILLING

A. This item shall consist of the variable depth, width, and length milling and cleaning of asphalt surfaces. If required by the Engineer, milling may also be required to remove contaminated asphalt surfaces, to remove surface irregularities, or to prepare surfaces for other work. The work shall be accomplished in accordance with these specifications, at locations and in close conformity to the details provided by the Engineer.

1.2 GENERAL CONDITIONS

A. It is the intent of this item to effect the complete removal and disposal of pavement material within the limits delineated and at locations required by the Engineer. All materials of other nature which would be an obstruction to the completion of the work, shall be removed and reset or disposed of, as directed by the Engineer, as if they were specifically enumerated herein, and shall be considered incidental to this item.

1.3 RELATED SECTIONS

B. Section 02746 Asphalt Pavements

C. Section 02751 Concrete Pavements

1.4 REFERENCES

A. The Maryland Department of Transportation State Highway Administration, Standard

Specifications for Construction and Materials, and all current supplements, unless specified otherwise by the Engineer.

A. The pavement surface shall be removed to the depth, width, length, grade, and cross section as directed by the Engineer. The existing cross slope gradient and longitudinal gradient shall be maintained unless noted otherwise.

02050-2

B. The construction operation shall be scheduled and proceed in a manner that produces a uniform finished milled surface with a neat uniform right angle cut at the sides and ends of the milled section. Milling will be accomplished in a manner that while provide positive lateral drainage by maintaining a constant cross-slope between milling extremities.

C. The entire area designated by the Engineer shall be milled until the pavement surfaces result in a surface that conforms to the typical section and cross section requirements directed or specified. The milling process shall produce a pavement surface that is true to grade with uniform texture. Fill all depressions, potholes, and other irregularities using an approved, compatible asphalt mix after the milling is complete as directed by the Engineer.

D. Pavement planning operations shall be referenced from the existing pavement surface or an independent grade control in all areas designated for milling. If independent grade control is required (at the direction of the Engineer), the independent grade control shall be established and maintained by the Contractor in a manner acceptable to the Engineer, and the final position of same shall be acceptable to the Engineer.

E. For each repair area that requires milling a test section of an area determined by the

Engineer will be required prior to the Engineer's authorization for full production.

Should the milling equipment fail such test sections, the machine shall be immediately removed and replaced with another machine. All interfaces of milled areas with existing pavement to be retained shall be vertical (including stop and start points). At interface areas of manholes where the pavement cannot be removed a method approved by the Engineer shall be employed.

F. The transverse and longitudinal slope of the pavement shall be uniform to a degree that no depressions or misalignment of slope greater than 5/8-inch in 10 feet are present when tested with a 10 feet straightedge.

G. The Contractor shall establish positive means for removal of milled residue. Solid residue shall be removed from pavement surfaces immediately. Residue shall not be permitted to flow into drainage facilities. The Contractor shall protect all inlets and similar structures from pollution by an approved method at his/her expense.

H. Exposed interface of milled areas with existing pavement that are to be opened to traffic or when directed by the Engineer, shall be protected by construction of bituminous asphalt transition surfaces by a method approved and acceptable to the Engineer at no cost to the Owner.

3.2 CLEANING OPERATIONS

A. Equipment for use in the pavement cleaning operation shall consist of a rotary pick-up sweeper, a construction sweeper and a water tanker.

02050-3

B. Immediately after the pavement surface has been milled to the depth directed or shown on the plans, and the milling debris has been removed, the pavement surface shall be cleaned of all dust and debris. The milled area shall first be swept with the rotary pick-up sweeper, followed by the construction sweeper. Next, the tanker shall place water at the pavement's crown. Then the construction sweeper shall move the water and dust to the edge of the pavement. Each piece of equipment shall make as many passes as necessary to clean the pavement to a dust and particle free condition, to the satisfaction of the Engineer.

C. In the event milling is to be followed by paving, immediately prior to placing any pavement material over the milled areas, the pavement shall be swept with the construction sweeper.

D. Debris removed by the pick-up sweeper and all other excess material shall be properly disposed of off Administration property.

E. Cleaning operation shall be conducted in such a manner as not to blow dust and debris towards buildings, cargo, vessels, public, or other working personnel. Damage inflicted on any property as a result of the Contractor's operations shall be repaired to the Administration’s satisfaction. Upon the Contractor's failure to meet the cleaning operations and repair of damages, the work shall be done by others at the Contractor's full expense.

3.3 EQUIPMENT

A. Rotary Pick-Up Sweeper:

A. Rotary pick-up sweeper shall be a power driven, self-propelled machine that is specifically designed to sweep and pick up debris. The vehicular mounted sweeper shall combine rotating brooms with conveyors or vacuums to pick up loosened material and transport the material into a storage hopper. Sweeper shall be equipped to wet down the loosened material to prevent dust.

B. Construction Sweeper:

A. Construction sweeper shall be a sweeper with stiff bristles, towed/pushed by a tractor or similar machine. Towed/pushed sweeper shall have a 3-point hitch and a constant velocity driveshaft.

C. Air Compressor:

A. Air compressor with wands shall be a self-propelled or towed air compressor, to which wands are attached. Nozzle of the wands shall be capable of blowing dust and other debris off the pavement surface and away from the cleaning operation.

D. Water Tanker:

A. Water tanker shall be a tank mounted on or towed behind a truck. Tanker shall be equipped with an outflow pipe.

E. Measuring Device:

02050-4

A. An approved 10 ft. straightedge for testing the transverse and longitudinal surface during and after milling.

F. Milling Equipment:

A. Milling equipment shall be power driven, self-propelled machine that is specifically designed to smooth and texture pavements.

B. Equipment shall be of a size that will cut or plane the width required by the Engineer. Equipment shall be capable of milling the surface without causing spalls at cracks, joints, or other locations.

C. Milling machine shall be equipped with automatic controls capable of controlling the elevation of the milling cutter by reference from either the existing pavement or from an independent grade control and a positive means of controlling the cross slope gradient elevations within a tolerance of 1/8 inch. The bits of the milling cutter shall be so shaped and mounted as to produce the texture uniformly over a minimum width specified per machine pass. The equipment shall have a floating mold-board and conveyor as an effective means of removing the pavement debris and for preventing dust from escaping into the air. The reclaimer system shall be equipped with a collector and discharge conveyor system that allows for simultaneous pavement removal and debris discharge into dump trucks. The entire cutting area shall be enclosed and utilize a pressure fog spray system to control the debris particulate emission. The machine shall be equipped with front headlights and a minimum of four (4) flood lights to allow for operation during darkness.

D. Conventional equipment such as motor graders, scarifiers, loaders, dozers, or heater-planers will not be…