511.21337.CAK RENOVATE ARMORY - BIG RAPIDS Project Manual CD VOLUME 1b.pdf

PDF 4 MB Posted

Attached to
511/21337. CAK; Big Rapids Armory - Renovate Armory
Solicitation number
RFQ - 171 - 230000000114
Issued by
Mecosta County, Michigan

About this file

This document is a project manual for the Renovate Armory - Big Rapids project, which is for the Michigan Department of Military and Veterans Affairs. The project involves selective demolition and renovation work on the existing armory building in Big Rapids, Michigan. The project includes demolition and removal of selected portions of the building or structure, as well as salvage of existing items to be reused or recycled. Key requirements include protecting individuals and property, controlling dust and noise, and maintaining existing utilities and fire protection during the demolition and renovation work. The project is expected to be completed within a specific timeframe, but the document does not provide details on response due dates, award dates, or contract terms.

The document outlines the requirements for various materials to be used in the renovation, including concrete masonry units, clay face brick, cast stone trim units, mortar and grout, steel reinforcement, masonry accessories, and embedded flashing. It also provides detailed specifications for installation, field quality control, and testing of the masonry and related components. Additionally, the document specifies the use of post-installed concrete anchors, including both mechanical and adhesive anchors, and outlines requirements for their installation and inspection.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NO. 21-502.00 SELECTIVE DEMOLITION

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 1

DEPARTMENT OF MILITARY AND VETERANS AFFAIRS 12/09/2022

[Copyright] 2022 Tower Pinkster Titus Associates - All Rights Reserved

SECTION 02 4119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Demolition and removal of selected portions of building or structure.

2. Demolition and removal of selected site elements.

3. Salvage of existing items to be reused or recycled.

B. Related Requirements:

1. Section 01 1000 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.

2. Section 01 7300 "Execution" for cutting and patching procedures.

3. Section 31 1000 "Site Clearing" for site clearing and removal of above- and below-grade improvements not part of selective demolition.

1.2 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse.

C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

1.3 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 2

1.4 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection , for dust control and , for noise control. Indicate proposed locations and construction of barriers.

B. Statement of Refrigerant Recovery: Signed by refrigerant recovery technician.

1.5 CLOSEOUT SUBMITTALS

A. Inventory of items that have been removed and salvaged.

1.6 QUALITY ASSURANCE

A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.

1.7 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

1. Before selective demolition, Owner will remove the following items:

a. Existing Uniform Storage Lockers

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

1. Hazardous materials will be removed by Owner before start of the Work.

2. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and

Owner. Hazardous materials will be removed by Owner under a separate contract.

E. Storage or sale of removed items or materials on-site is not permitted.

F. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

G. Arrange selective demolition schedule so as not to interfere with Owner's operations.

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 3

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials and using approved contractors so as not to void existing warranties.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting selective demolition operations.

B. Perform an engineering survey of condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective building demolition operations.

C. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

D. Survey of Existing Conditions: Record existing conditions by use of measured drawings, preconstruction photographs or video, and templates as appropriate.

1. Inventory and record the condition of items to be removed and salvaged. Provide photographs or video of conditions that might be misconstrued as damage caused by salvage operations.

2. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.

E. Inventory and record the condition of items to be removed and salvaged.

3.2 PREPARATION

A. Refrigerant: Before starting demolition, remove refrigerant from mechanical equipment according to 40 CFR 82 and regulations of authorities having jurisdiction.

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 4

3.3 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off utility services and mechanical/electrical systems serving areas to be selectively demolished.

1. Arrange to shut off utilities with utility companies.

2. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.

3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.

a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.

b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place.

c. Equipment to Be Removed: Disconnect and cap services and remove equipment.

d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when appropriate, reinstall, reconnect, and make equipment operational.

e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.

f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.

g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.

4. Provide at least 72 hours' notice to Owner if shutdown of service is required during changeover.

3.4 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

B. Temporary Shoring: Design, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.

C. Remove temporary barricades and protections where hazards no longer exist.

3.5 SELECTIVE DEMOLITION

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 5

1. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

2. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

3. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

4. Maintain fire watch during flame-cutting operations.

5. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

6. Dispose of demolished items and materials promptly.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Salvaged Items:

1. Clean salvaged items.

2. Pack or crate items after cleaning. Identify contents of containers.

3. Store items in a secure area until delivery to Owner.

4. Transport items to Owner's storage area designated by Owner.

5. Protect items from damage during transport and storage.

D. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse.

2. Pack or crate items after cleaning and repairing. Identify contents of containers.

3. Protect items from damage during transport and storage.

4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.6 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, and then remove masonry between saw cuts.

C. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.

RENOVATE ARMORY - BIG RAPIDS 02 4119 - 6

D. Resilient Floor Coverings: Remove floor coverings and adhesive according to recommendations in RFCI's "Recommended Work Practices for the Removal of Resilient Floor Coverings." Do not use methods requiring solvent-based adhesive strippers.

E. Roofing: Remove no more existing roofing than what can be covered in one day by new roofing and so that building interior remains watertight and weathertight. See Section 07 5323 “Ethylene-Propylene- Diene-Monomer (EPDM) Roofing” for new roofing requirements.

3.7 CLEANING

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

4. Comply with requirements specified in Section 01 7419 "Construction Waste Management and

Disposal."

B. Burning: Do not burn demolished materials.

C. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 02 4119

PROJECT NO. 21-502.00 CAST-IN-PLACE CONCRETE

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 1

SECTION 03 3000 - CAST-IN-PLACE CONCRETE

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes cast-in-place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes.

B. Related Requirements:

1. Section 32 1313 "Concrete Paving" for concrete pavement and walks.

1.2 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Design Mixtures: For each concrete mixture.

1.3 INFORMATIONAL SUBMITTALS

A. Material test reports.

B. Floor surface flatness and levelness measurements indicating compliance with specified tolerances.

1.4 QUALITY ASSURANCE

A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete Production Facilities."

B. Testing Agency Qualifications: An independent agency, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

1.5 PRECONSTRUCTION TESTING

A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on concrete mixtures.

1.6 FIELD CONDITIONS

A. Cold-Weather Placement: Comply with ACI 306.1.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 2

1. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

B. Hot-Weather Placement: Comply with ACI 301 (ACI 301M).

PART 2 - PRODUCTS

2.1 CONCRETE, GENERAL

A. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:

1. ACI 301 (ACI 301M).

2. ACI 117 (ACI 117M).

2.2 STEEL REINFORCEMENT

A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.

B. Plain-Steel Welded-Wire Reinforcement: ASTM A 1064/A 1064M, plain, fabricated from as-drawn steel wire into flat sheets.

C. Deformed-Steel Welded-Wire Reinforcement: ASTM A 1064/A 1064M, flat sheet.

D. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice."

2.3 CONCRETE MATERIALS

A. Cementitious Materials:

1. Portland Cement: ASTM C 150/C 150M, Type I.

2. Portland Cement: ASTM C 150/C 150M, Type I or Type I/II, gray.

3. Fly Ash: ASTM C 618, Class F or C.

4. Slag Cement: ASTM C 989/C 989M, Grade 100 or 120.

B. Normal-Weight Aggregates: ASTM C 33/C 33M, graded.

1. Maximum Coarse-Aggregate Size: 1-1/2 inches (38 mm) nominal.

2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

3. Combined Aggregate Gradation: Well graded from coarsest to finest with not more than 18 percent and not less than 8 percent retained on an individual sieve, except that less than 8 percent may be retained on coarsest sieve and on No. 50(0.3 mm) sieve, and less than 8 percent may be retained on sieves finer than No. 50(0.3 mm).

C. Air-Entraining Admixture: ASTM C 260/C 260M.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 3

D. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures and that do not contribute water-soluble chloride ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.

1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A.

2. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.

E. Water: ASTM C 94/C 94M and potable.

2.4 VAPOR RETARDERS

A. Sheet Vapor Retarder: ASTM E 1745, Class A, except with maximum water-vapor permeance of 0.02 U.S.

perms, minimum 15 mils(0.38 mm) thick monolithic polyolefin sheet. Include manufacturer's recommended adhesive or pressure-sensitive tape.

1. Products: Subject to compliance with requirements, provide one of the following:

a. Fortifiber Building Systems Group; Moistop Ultra 15.

b. Insulation Solutions, Inc.;Viper VaporCheck II 15-mil.

c. Poly-America, L.P.; Husky Yellow Guard Vapor Barrier 15 Mil ASTM E-1745 Class A.

d. Reef Industries, Inc; Griffolyn 15 mil Green.

e. Stego Industries, LLC; Stego Wrap 15 mil Class A.

2.5 LIQUID FLOOR TREATMENTS

A. Penetrating Liquid Floor Treatment (SC-1): Clear, chemically reactive, waterborne solution of inorganic silicate or siliconate materials and proprietary components; odorless; that penetrates, hardens, and densifies concrete surfaces.

1. Products: Subject to compliance with requirements, provide one of the following:

a. ChemMasters, Inc; Chemisil Plus.

b. Curecrete Distribution Inc.; Ashford Formula.

c. Dayton Superior; Sure Hard Densifier J17.

d. Euclid Chemical Company (The); an RPM company; Euco Diamond Hard.

e. L&M Construction Chemicals, Inc; Seal Hard.

f. PROSOCO, Inc; Consolideck LS by PROSOCO.

2.6 CURING MATERIALS

A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

1. Products: Subject to compliance with requirements, provide one of the following:

a. ChemMasters, Inc; Spray-Film.

b. Dayton Superior; AquaFilm Concentrate J74.

c. Euclid Chemical Company (The); an RPM company; Eucobar.

d. L&M Construction Chemicals, Inc; E-CON.

B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m) when dry.

http://www.specagent.com/Lookup?ulid=1166 http://www.specagent.com/Lookup?uid=123456976082 http://www.specagent.com/Lookup?uid=123456976085 http://www.specagent.com/Lookup?uid=123456976087 http://www.specagent.com/Lookup?uid=123456976079 http://www.specagent.com/Lookup?uid=123456976080 http://www.specagent.com/Lookup?ulid=11023 http://www.specagent.com/Lookup?uid=123456975878 http://www.specagent.com/Lookup?uid=123456975893 http://www.specagent.com/Lookup?uid=123456975880 http://www.specagent.com/Lookup?uid=123456975883 http://www.specagent.com/Lookup?uid=123456975885 http://www.specagent.com/Lookup?uid=123456975892 http://www.specagent.com/Lookup?ulid=11025 http://www.specagent.com/Lookup?uid=123456975991 http://www.specagent.com/Lookup?uid=123456975992 http://www.specagent.com/Lookup?uid=123456975995 http://www.specagent.com/Lookup?uid=123456975997

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 4

C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

D. Water: Potable.

E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating.

1. Products: Subject to compliance with requirements, provide one of the following:

a. ChemMasters, Inc; Safe-Cure Clear DR.

b. Dayton Superior; Clear Resin Cure J11W.

c. Euclid Chemical Company (The); an RPM company; Kurez DR VOX.

d. Kaufman Products, Inc; Thinfilm 420.

e. L&M Construction Chemicals, Inc; L&M CURE R.

f. Lambert Corporation; AQUA KURE - CLEAR.

g. Nox-Crete Products Group; Resin Cure E.

h. Right Pointe; Clear Water Resin.

i. SpecChem; PaveCure Rez.

j. TK Products; TK-2519 DC WB.

k. Vexcon Chemicals Inc.; Certi-Vex Enviocure 100.

l. W.R. Meadows, Inc; 1100-CLEAR SERIES.

2.7 RELATED MATERIALS

A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.

B. Bonding Agent: ASTM C 1059/C 1059M, Type II, nonredispersible, acrylic emulsion or styrene butadiene.

2.8 CONCRETE MIXTURES, GENERAL

A. Prepare design mixtures for each type and strength of concrete, proportioned on the basis of laboratory trial mixture or field test data, or both, according to ACI 301 (ACI 301M).

B. Cementitious Materials: Limit percentage, by weight, of cementitious materials other than portland cement in concrete as follows:

1. 20 percent fly ash or 30 percent ground blast furnace slag.

C. Limit water-soluble, chloride-ion content in hardened concrete to 0.15 percent by weight of cement.

D. Admixtures: Use admixtures according to manufacturer's written instructions.

2.9 CONCRETE MIXTURES FOR BUILDING ELEMENTS

A. Slabs-on-Grade: Normal-weight concrete.

1. Minimum Compressive Strength: 4000 psi (27.6 MPa) at 28 days.

2. Maximum W/C Ratio: 0.45.

3. Minimum Cementitious Materials Content: 470 lb/cu. yd. (279 kg/cu. m).

4. Slump Limit: 5 inches (125 mm), plus or minus 1 inch (25 mm).

5. Air Content: Do not allow air content of trowel-finished floors to exceed 3 percent.

http://www.specagent.com/Lookup?ulid=11026 http://www.specagent.com/Lookup?uid=123456975895 http://www.specagent.com/Lookup?uid=123456975896 http://www.specagent.com/Lookup?uid=123456975899 http://www.specagent.com/Lookup?uid=123456975900 http://www.specagent.com/Lookup?uid=123456975901 http://www.specagent.com/Lookup?uid=123456975902 http://www.specagent.com/Lookup?uid=123456975904 http://www.specagent.com/Lookup?uid=123456975910 http://www.specagent.com/Lookup?uid=123456975905 http://www.specagent.com/Lookup?uid=123456975907 http://www.specagent.com/Lookup?uid=123456975908 http://www.specagent.com/Lookup?uid=123456975903

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 5

B. Normal-Weight Concrete:

1. Minimum Compressive Strength: 4000 psi (27.6 MPa) at 28 days.

2. Maximum W/C Ratio: 0.45.

3. Slump Limit: 8 inches (200 mm) for concrete with verified slump of 2 to 4 inches (50 to 100 mm) before adding high-range water-reducing admixture or plasticizing admixture, plus or minus 1 inch (25 mm).

4. Air Content: 5.5 percent, plus or minus 1.5 percent at point of delivery for 1-1/2-inch (38-mm) nominal maximum aggregate size.

2.10 FABRICATING REINFORCEMENT

A. Fabricate steel reinforcement according to CRSI's "Manual of Standard Practice."

2.11 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M and ASTM C 1116/C 1116M, and furnish batch ticket information.

1. When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 deg C), reduce mixing and delivery time to 60 minutes.

PART 3 - EXECUTION

3.1 FORMWORK INSTALLATION

A. Design, erect, shore, brace, and maintain formwork, according to ACI 301 (ACI 301M), to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Construct formwork so concrete members and structures are of size, shape, alignment, elevation, and position indicated, within tolerance limits of ACI 117 (ACI 117M).

3.2 EMBEDDED ITEM INSTALLATION

A. Place and secure anchorage devices and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.3 VAPOR-RETARDER INSTALLATION

A. Sheet Vapor Retarders: Place, protect, and repair sheet vapor retarder according to ASTM E 1643 and manufacturer's written instructions.

1. Lap joints 6 inches (150 mm) and seal with manufacturer's recommended tape.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 6

3.4 STEEL REINFORCEMENT INSTALLATION

A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

3.5 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Architect.

C. Contraction Joints in Slabs-on-Grade: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of concrete thickness as follows:

1. Sawed Joints: Form contraction joints with power saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut 1/8-inch- (3.2-mm-) wide joints into concrete when cutting action does not tear, abrade, or otherwise damage surface and before concrete develops random contraction cracks.

D. Isolation Joints in Slabs-on-Grade: After removing formwork, install joint-filler strips at slab junctions with vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

3.6 CONCRETE PLACEMENT

A. Before placing concrete, verify that installation of formwork, reinforcement, and embedded items is complete and that required inspections are completed.

B. Deposit concrete continuously in one layer or in horizontal layers of such thickness that no new concrete is placed on concrete that has hardened enough to cause seams or planes of weakness. If a section cannot be placed continuously, provide construction joints as indicated. Deposit concrete to avoid segregation.

1. Consolidate placed concrete with mechanical vibrating equipment according to ACI 301 (ACI 301M).

3.7 FINISHING FORMED SURFACES

A. Rough-Formed Finish: As-cast concrete texture imparted by form-facing material with tie holes and defects repaired and patched. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces not exposed to public view.

a. Locations include walls and, ceiling within the Vault, and walls that are exposed to public view on the exterior side of the Vault walls.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 7

B. Smooth-Formed Finish: As-cast concrete texture imparted by form-facing material, arranged in an orderly and symmetrical manner with a minimum of seams. Repair and patch tie holes and defects. Remove fins and other projections that exceed specified limits on formed-surface irregularities.

1. Apply to concrete surfaces exposed to public view, or to be covered with a coating or covering material applied directly to concrete .

a. Locations include walls and, ceiling within the Vault, and walls that are exposed to public view on the exterior side of the Vault walls.

C. Rubbed Finish: Apply the following to smooth-formed-finished as-cast concrete where indicated:

1. Grout-Cleaned Finish: Wet concrete surfaces and apply grout of a consistency of thick paint to coat surfaces and fill small holes. Mix 1 part portland cement to 1-1/2 parts fine sand with a 1:1 mixture of bonding admixture and water. Add white portland cement in amounts determined by trial patches, so color of dry grout matches adjacent surfaces. Scrub grout into voids and remove excess grout. When grout whitens, rub surface with clean burlap and keep surface damp by fog spray for at least 36 hours.

D. Related Unformed Surfaces: At tops of walls, horizontal offsets, and similar unformed surfaces adjacent to formed surfaces, strike off smooth and finish with a texture matching adjacent formed surfaces. Continue final surface treatment of formed surfaces uniformly across adjacent unformed surfaces unless otherwise indicated.

3.8 FINISHING FLOORS AND SLABS

A. General: Comply with ACI 302.1R recommendations for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Scratch Finish: While still plastic, texture concrete surface that has been screeded and bull-floated or darbied. Use stiff brushes, brooms, or rakes to produce a profile amplitude of 1/4 inch (6 mm) in one direction.

1. Apply scratch finish to surfaces to receive concrete floor toppings.

C. Float Finish: Consolidate surface with power-driven floats or by hand floating if area is small or inaccessible to power-driven floats. Restraighten, cut down high spots, and fill low spots. Repeat float passes and restraightening until surface is left with a uniform, smooth, granular texture.

1. Apply float finish to surfaces to be covered with fluid-applied or sheet waterproofing, built-up or membrane roofing, or sand-bed terrazzo.

D. Trowel Finish: After applying float finish, apply first troweling and consolidate concrete by hand or power-driven trowel. Continue troweling passes and restraighten until surface is free of trowel marks and uniform in texture and appearance. Grind smooth any surface defects that would telegraph through applied coatings or floor coverings.

1. Apply a trowel finish to surfaces to be covered with resilient flooring, carpet, ceramic or quarry tile set over a cleavage membrane, paint, or another thin-film-finish coating system.

E. Broom Finish: Apply a broom finish to exterior concrete platforms, steps, ramps, and elsewhere as indicated.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 8

1. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Coordinate required final finish with Architect before application.

3.9 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

Comply with ACI 306.1 for cold-weather protection and ACI 301 (ACI 301M) for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to unformed concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h) before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Cure concrete according to ACI 308.1, by one or a combination of the following methods:

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days.

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches (300 mm), and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period, using cover material and waterproof tape.

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period.

a. Removal: After curing period has elapsed, remove curing compound without damaging concrete surfaces by method recommended by curing compound manufacturer unless manufacturer certifies curing compound does not interfere with bonding of floor covering used on Project.

3.10 FIELD QUALITY CONTROL

A. Special Inspections: Owner will engage a special inspector to perform field tests and inspections and prepare testing and inspection reports.

B. Testing Agency: Owner will engage a qualified testing and inspecting agency to perform tests and inspections and to submit reports.

1. Testing agency shall be responsible for providing curing container for composite samples on Site and verifying that field-cured composite samples are cured in accordance with ASTM C31/C31M.

2. Testing agency shall immediately report to Architect, Contractor, and concrete manufacturer any failure of Work to comply with Contract Documents.

3. Testing agency shall report results of tests and inspections, in writing, to Owner, Architect, Contractor, and concrete manufacturer within 48 hours of inspections and tests.

a. Test reports shall include reporting requirements of ASTM C31/C31M, ASTM C39/C39M, and ACI 301, including the following as applicable to each test and inspection:

1) Project name.

2) Name of testing agency.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 9

3) Names and certification numbers of field and laboratory technicians performing inspections and testing.

4) Name of concrete manufacturer.

5) Date and time of inspection, sampling, and field testing.

6) Date and time of concrete placement.

7) Location in Work of concrete represented by samples.

8) Date and time sample was obtained.

9) Truck and batch ticket numbers.

10) Design compressive strength at 28 days.

11) Concrete mixture designation, proportions, and materials.

12) Field test results.

13) Information on storage and curing of samples before testing, including curing method and maximum and minimum temperatures during initial curing period.

14) Type of fracture and compressive break strengths at seven days and 28 days.

C. Batch Tickets: For each load delivered, submit three copies of batch delivery ticket to testing agency, indicating quantity, mix identification, admixtures, design strength, aggregate size, design air content, design slump at time of batching, and amount of water that can be added at Project site.

D. Inspections:

1. Headed bolts and studs.

2. Verification of use of required design mixture.

3. Concrete placement, including conveying and depositing.

4. Curing procedures and maintenance of curing temperature.

5. Verification of concrete strength before removal of shores and forms from beams and slabs.

6. Batch Plant Inspections: On a random basis, as determined by Architect.

E. Concrete Tests: Testing of composite samples of fresh concrete obtained in accordance with ASTM C 172/C 172M shall be performed in accordance with the following requirements:

1. Testing Frequency: Obtain one composite sample for each day's pour of each concrete mixture exceeding 5 cu. yd. (4 cu. m), but less than 25 cu. yd. (19 cu. m), plus one set for each additional 50 cu. yd. (38 cu. m) or fraction thereof.

a. When frequency of testing provides fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.

2. Slump: ASTM C143/C143M:

a. One test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture.

b. Perform additional tests when concrete consistency appears to change.

3. Slump Flow: ASTM C1611/C1611M:

a. One test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture.

b. Perform additional tests when concrete consistency appears to change.

4. Air Content: ASTM C231/C231M pressure method, for normal-weight concrete;.

a. One test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 10

5. Concrete Temperature: ASTM C1064/C1064M:

a. One test hourly when air temperature is 40 deg F (4.4 deg C) and below or 80 deg F (27 deg C) and above, and one test for each composite sample.

6. Unit Weight: ASTM C567/C567M fresh unit weight of structural lightweight concrete.

a. One test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

7. Compression Test Specimens: ASTM C31/C31M:

a. Cast and laboratory cure two sets of two 6-inch (150 mm) by 12-inch (300 mm) or 4-inch

(100 mm) by 8-inch (200 mm) cylinder specimens for each composite sample.

b. Cast, initial cure, and field cure two sets of two standard cylinder specimens for each composite sample.

8. Compressive-Strength Tests: ASTM C39/C39M.

a. Test one set of two laboratory-cured specimens at seven days and one set of two specimens at 28 days.

b. Test one set of two field-cured specimens at seven days and one set of two specimens at

28 days.

c. A compressive-strength test shall be the average compressive strength from a set of two specimens obtained from same composite sample and tested at age indicated.

9. When strength of field-cured cylinders is less than 85 percent of companion laboratory-cured cylinders, Contractor shall evaluate operations and provide corrective procedures for protecting and curing in-place concrete.

10. Strength of each concrete mixture will be satisfactory if every average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength, and no compressive-strength test value falls below specified compressive strength by more than 500 psi (3.4 MPa) if specified compressive strength is 5000 psi (34.5 MPa), or no compressive strength test value is less than 10 percent of specified compressive strength if specified compressive strength is greater than 5000 psi (34.5 MPa).

11. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.

12. Additional Tests:

a. Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect.

b. Testing and inspecting agency may conduct tests to determine adequacy of concrete by cored cylinders complying with ASTM C42/C42M or by other methods as directed by Architect.

1) Acceptance criteria for concrete strength shall be in accordance with ACI 301

(ACI 301M), section 1.6.6.3.

13. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

14. Correct deficiencies in the Work that test reports and inspections indicate do not comply with the Contract Documents.

F. Measure floor and slab flatness and levelness in accordance with ASTM E1155 (ASTM E1155M) within 48 hours of completion of floor finishing and promptly report test results to Architect.

RENOVATE ARMORY - BIG RAPIDS 03 3000 - 11

END OF SECTION 03 3000

This page intentionally left blank.

PROJECT NO. 21-502.00 POST INSTALLED ANCHORS

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 1

SECTION 03 6000 - POST INSTALLED ANCHORS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes post installed concrete anchors requirements for the following:

1. Mechanical Anchors.

2. Adhesive Anchors.

B. Related Sections:

1. Division 03 Section "Cast-In-Place Concrete".

2. Division 04 Section "Unit Masonry”.

3. Division 05 Section "Structural Steel Framing".

1.2 DEFINITION

A. Post Installed Anchors: Anchors installed into hardened concrete or fully constructed hollow or grouted masonry.

1.3 REFERENCE MATERIAL

A. ACI 318 – Building Code Requirements for Structural Concrete

B. ACI 355.2 – Standard for Evaluating the Performance of Post-Installed Mechanical Anchors in Concrete

C. ASTM A36 – Standard Specification for Carbon Structural Steel

D. ASTM A153 – Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware

E. ASTM A193 – Standard Specification for Alloy-Steel and Stainless Steel Bolting Materials for High- Temperature Service

F. ASTM C881 – Standard Specification Epoxy-Resin-Based Bonding Systems for Concrete

G. ASTM E488 – Standard Test Methods for Strength of Anchors in Concrete and Masonry Elements

H. ASTM E1512 – Standard Test Methods for Testing Bond Performance of Bonded Anchors

I. ASTM F593 – Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and Studs

J. ICC-ES AC01 – Acceptance Criteria for Expansion Anchors in Masonry Elements

K. ICC-ES AC58 – Acceptance Criteria for Adhesive Anchors in Masonry Elements

L. ICC-ES AC60 – Acceptance Criteria for Anchors in Unreinforced Masonry Elements

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 2

M. ICC-ES AC106 – Acceptance Criteria for Predrilled Fasteners (Screw Anchors) in Concrete or Masonry Elements

N. ICC-ES AC193 – Acceptance Criteria for Mechanical Anchors in Concrete Elements

O. ICC-ES AC308 – Acceptance Criteria for Post-Installed Adhesive Anchors in Concrete Elements

1.4 SUBMITTAL

A. General: Submit in accordance with Conditions of the Contract and Division 1 Submittal Procedures Section.

1. Product specifications with recommended design values and physical characteristics for epoxy dowels, expansion and undercut anchors.

1.5 Quality Assurance Submittals:

a. Test Reports: Certified test reports showing compliance with specified performance characteristics and physical properties.

b. Certificates

1) ICC ES Evaluation Reports

B. Manufacturer’s installation instructions.

C. Installer Qualifications & Procedures: Submit installer qualifications to special inspector for approval prior to commencement of work.

1.6 QUALITY ASSURANCE

A. Installer(s) Training:

1. Product Manufacturer’s certificate for each installer certifying they have been trained on the means and methods for installing the particular anchor.

B. For horizontal and upwardly inclined adhesive installations, the installer shall be certified by an ACI/CRSI Adhesive Anchor Installing Certification Program or equivalent.

C. Certifications: Unless otherwise authorized by the Engineer, anchors shall have one of the following certifications.

1. ICC ES Evaluation Report indicating conformance with current applicable ICC ES Acceptance Criteria.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Deliver products to job site in manufacturer’s or distributor’s packaging undamaged, complete with installation instructions.

B. General: Comply with Division 1 Section−Product Storage and Handling Requirements

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 3

1. Store anchors in accordance with manufacturer’s recommendations.

PART 2 - PRODUCTS

1.8 MANUFACTURER

A. All products are based on Hilti Corporation.

B. Substitution:

1. Upon approval by the engineer, the installer may substitute a product by a different manufacturer, provided that the manufacturer submits calculations signed and sealed by an engineer registered in the state of the project’s location.

a. These calculations must show that the strength of the substituted anchor meets or exceeds the strength of the specified anchor at each application in the project where a substituted anchor is proposed, with consideration for combined stress and any applicable reduction factors.

C. The substitution request and submittal shall be made a minimum of 2 weeks prior to planned installation of the anchors.

D. The finish of the anchor shall remain the same as specified.

1.9 MECHANICAL ANCHORS

A. Torque Controlled (TC) Anchors. Hilti Kwik Bolt TZ is a torque controlled expansion anchor suited to seismic and cracked concrete applications.

1. Size: As indicated on drawings

2. Finish: Plain carbon steel or stainless steel type 304 (316) as indicated on drawings.

B. Screw Anchors: Hilti Kwik HUS-EZ anchors are comprised of a body with hex washer head.

1. Size: As indicated on drawings

2. Finish: As indicated on drawings

C. Sleeve Anchors: Hilti HLC Sleeve Anchor are mechanical expansion anchors consisting of an externally threaded stud with an expanding sleeve for use in concrete and hollow and solid masonry base material.

1. Size: As indicated on drawings

2. Finish: As indicated on drawings

1.10 ADHESIVE ANCHORS

A. In contract documents adhesive anchors may be generically referred to as epoxy anchors. Where this is the case the word adhesive should be substituted for epoxy.

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 4

B. Adhesive anchors used in concrete under a tension condition cannot be installed until after the concrete has cured for a minimum 21 days in accordance with ACI 17.4.5.2.

C. Concrete Anchor

1. Hilti HIT-RE 500-V3 is a high strength, two part epoxy adhesive.

a. Base material temperature range: 23 degrees up to 120 degrees Fahrenheit.

b. Size: As indicated on drawings, up to 1.25” diameter maximum.

c. Finish: As indicated on drawings

d. Anchor material: HAS Threaded Rod Standard ISO 898 Class 5.8, and Deformed

Reinforcing Bars.

e.

2. Hilti HIT HY 200 is a two-component hybrid adhesive.

a. Base material temperature range: 14 degrees up to 104 degrees Fahrenheit.

b. Size: As indicated on drawings, up to 1” diameter maximum.

c. Finish: As indicated on drawings

d. Anchor material: HY200 HAS Threaded Rod Standard ISO 898 Class 5.8, and Deformed

Reinforcing Bars.

3. Hilti HIT HY 200 Safeset is a two-component hybrid adhesive.

a. Base material temperature range: 14 degrees up to 104 degrees Fahrenheit.

b. Size: As indicated on drawings, up to 1” diameter maximum.

c. Finish: As indicated on drawings

d. Anchor material based on cleaning:

1) No cleaning of hole:

a) HIT-Z, HIT-Z-R Threaded Rods

2) Automatic cleaning of hole:

a) HY200 HAS Threaded Rod Standard ISO 898 Class 5.8, and Deformed

Reinforcing Bars.

D. Masonry Anchor:

1. Hilti HIT HY-70 System is a hybrid adhesive consisting of a dual cylinder adhesive refill pack, a mixing nozzle, a screen tube, and either a threaded rod or rebar.

a. Size: As indicated on drawings

b. Finish: As indicated on drawings

c. Anchor Rod: HAS-E Standard ISO 898 Class 5.8.

d. Use: Hollow brick, hollow concrete masonry block, or grouted solid concrete masonry block.

2. Hilti HIT HY 200 is a two-component hybrid adhesive.

a. Base material temperature range: 14 degrees up to 104 degrees Fahrenheit.

b. Size: As indicated on drawings, up to 1” diameter maximum.

c. Finish: As indicated on drawings

d. Anchor material: HY200 HAS Threaded Rod Standard ISO 898 Class 5.8, and Deformed

Reinforcing Bars.

e. Use: Solid or grouted solid masonry only.

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 5

PART 3 - EXECUTION

1.11 POST INSTALLED ANCHORS

A. All installation shall be done in accordance with manufacturer’s ICC-ES report.

B. Drilling:

1. Drill holes with rotary impact hammer drills. Drill bits shall be of diameters as specified by the anchor manufacturer. Unless otherwise shown on the Drawings, all holes shall be drilled perpendicular to the concrete surface.

2. Embedded Items: Identify position of reinforcing steel and other embedded items prior to drilling holes for anchors. Exercise care in coring or drilling to avoid damaging existing reinforcing or embedded items. Notify the Engineer if reinforcing steel or other embedded items are encountered during drilling. Take precautions as necessary to avoid damaging prestressing tendons, electrical and telecommunications conduit, and gas lines.

3. Base Material Strength: Unless otherwise specified, do not drill holes in concrete or masonry until concrete, mortar, or grout has met Manufacturer’s specifications.

C. Torque Controlled Anchors and Sleeve Anchors: Protect threads from damage during anchor installation.

Set anchors to manufacturer’s recommended torque, using a torque wrench. Following attainment of 10% of the specified torque, 100% of the specified torque shall be reached within 7 or fewer complete turns of the nut. If the specified torque is not achieved within the required number of turns, the anchor shall be removed and replaced unless otherwise directed by the Engineer.

D. Screw Anchors: Install screw anchors to a snug tight condition unless noted otherwise.

E. Adhesive Anchors: Clean all holes per manufacturer instructions to remove loose material and drilling dust prior to installation of adhesive. Inject adhesive into holes proceeding from the bottom of the hole and progressing toward the surface in such a manner as to avoid introduction of air pockets in the adhesive.

Follow manufacturer recommendations to ensure proper mixing of adhesive components. Sufficient adhesive shall be injected in the hole to ensure that the annular gap is filled to the surface. Remove excess adhesive from the surface. Shim anchors with suitable device to center the anchor in the hole. Do not disturb or load anchors before manufacturer specified cure time has elapsed.

1.12 FIELD QUALITY CONTROL

A. Testing and Inspecting: Engage a special inspector and qualified testing and inspecting agency to perform field tests and inspections and prepare test reports.

B. Continuous special Inspection of post-installed anchors shall be provided as required by ICC-ES evaluation reports. This service shall be performed by personnel independent of the Manufacturer or Contractor so as to prevent a conflict of interest.

C. The Engineer or Architect of Record may require pullout or shear tests, in addition to Special Inspection, to determine the adequacy of anchors. A field testing program shall be established by the independent testing and inspecting agency and/or Engineer of Record and performed in accordance with appropriate ASTM test standards. Field tests shall be non-destructive whenever possible.

RENOVATE ARMORY - BIG RAPIDS 03 6000 - 6

END OF SECTION 03 6000

PROJECT NO. 21-502.00 MASONRY CLEANING

RENOVATE ARMORY - BIG RAPIDS 04 0110 - 1

SECTION 04 0110 - MASONRY CLEANING

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes cleaning the following:

1. Unit masonry surfaces.

1.2 DEFINITIONS

A. Medium-Pressure Spray: 400 to 800 psi (2750 to 5510 kPa); 4 to 6 gpm (0.25 to 0.4 L/s).

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product.

1.5 QUALITY ASSURANCE

A. Mockups: Prepare mockups of cleaning on existing surfaces to demonstrate aesthetic effects and to set quality standards for materials and execution.

1. Cleaning: Clean an area approximately 25 sq. ft. (2.3 sq. m) for each type of masonry and surface condition.

a. Test cleaners and methods on samples of adjacent materials for possible adverse reactions. Do not test cleaners and methods known to have deleterious effect.

b. Allow a waiting period of not less than seven days after completion of sample cleaning to permit a study of sample panels for negative reactions.

1.6 FIELD CONDITIONS

A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit masonry-cleaning work to be performed according to product manufacturers' written instructions and specified requirements.

B. Clean masonry surfaces only when air temperature is 40 deg F (4 deg C) and above and is predicted to remain so for at least seven days after completion of cleaning.

RENOVATE ARMORY - BIG RAPIDS 04 0110…

This is the start of the file's text. The full file is on GovTribe.