This pre-solicitation announcement describes an upcoming Invitation for Bid for an electrical upgrade project. The Department of Veterans Affairs will replace the existing 4800V primary distribution system at the Ann Arbor VA Medical Center with a new 13.2kV system, reusing the existing 4800V cabling. A Firm Fixed Price contract valued between $2-5 million will be awarded within 120 days of bid receipt to furnish all labor, materials, equipment, permits and supervision necessary to upgrade the switchgear and distribution. Interested contractors must register at beta.SAM.gov and the solicitation containing specifications, forms and drawings will be available there on or around July 6th, with the bid due date specified in those documents. All work must comply with privacy training requirements and be completed within 570 days.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 36C25020B0057 0001.docx | DOCX document | |
| Pre-Bid Attendance 506-18-102.pdf | ||
| 506-18-102 - RFIs answers.docx | DOCX document | |
| Covid Instructions.docx | DOCX document | |
| RFI Form 506 18 102.docx | DOCX document | |
| 506-18-102 Specs Vol 1 - Ann Arbor VA Upgrade Switchgear.pdf | ||
| 36C25020B0057_3.docx | DOCX document | |
| 506-18-102 Specs Vol 2 - Ann Arbor VA Upgrade Switchgear.pdf | ||
| _WD MI20200100 7-24-20.pdf | ||
| 506-18-102 Contractor EMR Certification Form 2020.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
T
E
O
F M
I
C
H
I
G
A
N
L I C
E
N
S
D
P
R
O
F
E
SS
I O
N
A
L
N
G
I
N
E
E R
GI000
COVER SHEET
PROJECT SITE
AREA MAP
VICINITY MAP
SHEET
NUMBER SHEET NAME
GENERAL
GI000 COVER SHEET
DEPARTMENT OF VETERANS AFFAIRS
ANN ARBOR VA MEDICAL CENTER
ANN ARBOR, MICHIGAN
UPGRADE ELECTRICAL SWITCHGEAR
AND DISTRIBUTION
Contact:
GHAFARI ASSOCIATES
ELECTRICAL
ENGINEER
GUIDON DESIGN INC.
CIVIL
ENGINEER
ANN ARBOR VA MEDICAL CENTER
Jeff Means Project COR
2215 Fuller Road Ann Arbor, MI 48105 p: 735.222.4345 e: Jeff.Means@va.gov
OWNER
17101 Michigan Avenue Dearborn, MI 48126 p:313.441.3000
1221 N. Pennsylvania Avenue Suite 200 Indianapolis, IN 46202 p: 317.800.6388
100% CONSTRUCTION DOCUMENTS
SHEET LIST
GI001 GENERAL NOTES SHEET
OVERALL SITE PLAN
SWITCHGEAR DEMOLITION PLAN
SWITCHGEAR SITE DEVELOPMENT PLAN
BUILDING 22 TRANSFORMER DEMOLITION AND SITE PLAN
BUILDING 28 TRANSFORMER DEMOLITION AND SITE PLAN
LINAC BUILDING TRANSFORMER DEMOLITION AND SITE PLAN
DETAIL SHEET
DETAIL SHEET
GRADING PLAN
CIVIL
CC001
CD101
CS101
CS102
CS103
CS104
CS501
CS502
CG101
ELECTRICAL SYMBOLS LIST
ELECTRICAL GENERAL NOTES AND ABBREVIATIONS
ELECTRICAL COMPOSITE SITE PLAN - DEMOLITION
ELECTRICAL ENLARGED PLAN BUILDING 1 - WEST
ELECTRICAL ONE LINE DIAGRAM - DEMOLITION
ELECTRICAL COMPOSITE SITE PLAN
ELECTRICAL ENLARGED PLAN BUILDING 1 - WEST
ELECTRICAL ENLARGED PLAN BUILDING 22
ELECTRICAL ENLARGED PLAN BUILDING 28
ELECTRICAL ENLARGED PLAN LINEAR ACCELERATOR
ELECTRICAL DETAILS
ELECTRICAL ONE LINE DIAGRAM MV POWER DISTRIBUTION
ELECTRICAL ONE LINE DIAGRAM SWITCHBOARDS 1-A & 1-B
ELECTRICAL ONE LINE DIAGRAM SWITCHBOARDS 2-A & 2-B
ELECTRICAL ONE LINE DIAGRAM SWITCHBOARDS 3-A & 3-B
ELECTRICAL
EE001
EE002
ED101
ED401
ED601
ES101
ES401
ES402
ES403
ES404
ES501
EP601
EP602
EP603
EP604
Contact:
Stacey Paul Project Manager
Contact:
Jeff Pedersen
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
GI001
GENERAL NOTES SHEET
BLDG. 1-W
BLDG. 22
BLDG. 1-W
BLDG. 28
AMBULANCE
ENTRANCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 8040
CC001
OVERALL SITE PLAN
AMBULANCE
ENTRANCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 105
CD101
SWITCHGEAR DEMOLITION PLAN
ENTRANCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 105
CS101
SWITCHGEAR SITE DEVELOPMENT
PLAN
BLDG. 22
BLDG. 22
BLDG. 1-W
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 105
BUILDING 22 TRANSFORMER
DEMOLITION AND SITE PLAN
CS102
0 105
BLDG. 28
BLDG. 28
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 105
N
0 105
CS103
BUILDING 28 TRANSFORMER
DEMOLITION AND SITE PLAN
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N 0 105
N
0 105
CS104
LINAC BUILDING TRANSFORMER
DEMOLITION AND SITE PLAN
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
CS501
DETAIL SHEET
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
CS502
DETAIL SHEET
ENTRANCE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
100% CONSTRUCTION
DOCUMENTS
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVANIA STREET
INDIANAPOLIS, IN 46204
317.800.6388
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
313.331.3000
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
11/19/19 SLP DSMRevisions: Date:
SUITE 200
S
T
A
M
I
C
H
I
G
A
N
L I C
E
N
S
O
F
E
SS
I O
N
G
I
N
E
E R
N
0 105
GRADING PLAN
CG101
EE001
ELECTRICAL SYMBOLS LIST
M.
SABAPATHY
F. KHAN11/18/19
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
J J
PANEL;CIRCUIT
SINGLE RECEPTACLE - WALL, CEILING, FLOOR
RECEPTACLE, 220V, 3 PHASE - SINGLE, DUPLEX
CONDUIT UP
GROUND ROD
CONDUIT HOME RUN TO PANEL
CONDUIT RUN
UNDERGROUND GROUND WIRE
UNDERGROUND TELECOMMUNICATIONS CONDUIT / DUCT BANK
UNDERGROUND ELECTRICAL CONDUIT / DUCT BANK
JUNCTION BOX
DUPLEX RECEPTACLE - WALL, CEILING, FLOOR
DOUBLE DUPLEX RECEPTACLE - WALL, CEILING, FLOOR
RECEPTACLE, 240/208V, 3 PHASE - WALL, FLOOR
RECEPTACLE, 480V, 3 PHASE - WALL, FLOOR
PULL BOX
GROUND TEST WELL
CADWELD CABLE CONNECTION
GROUND BUS
PB
GROUNDING SYMBOL LIST (ALL MAY NOT APPLY)
WIRING SYMBOL LIST (ALL MAY NOT APPLY)
POWER SYMBOL LIST (ALL MAY NOT APPLY)
G
T
E
GFR
CAPACITOR
VALUE AS
INDICATED
ON
DRAWINGS
V
G
A
MOUNTING HEIGHTS (ALL MAY NOT APPLY)
SINGLE LINE DIAGRAM SYMBOL LIST
(ALL MAY NOT APPLY)
TOGGLE SWITCHES - GENERAL 4'-0" AFF
RECEPTACLES - FINISHED AREAS 1'-6" AFF
RECEPTACLES - NON FINISHED AREAS 4'-0" AFF
PUSHBUTTONS 4'-6" AFF
DISCONNECT SWITCHES 5'-6" AFF
MOTOR STARTERS 5'-6" AFF
PANELS & CABINETS 6'-0" TO TOP
INDIVIDUAL CIRCUIT BREAKERS 5'-6" TO TOP
MOUNTING HEIGHT NOTES:
1. ALL ELEVATIONS ARE TO CENTER LINE OF DEVICE
UNLESS NOTED OTHERWISE.
2. PENDANT LIGHTING FIXTURE MOUNTING HEIGHTS ARE TO THE
BOTTOM OF THE FIXTURE UNLESS NOTED OTHERWISE.
3. CEILING SURFACE LIGHTING FIXTURE MOUNTING HEIGHTS ARE TO
THE TOP OF THE FIXTURE UNLESS NOTED OTHERWISE.
4. WALL LIGHTING FIXTURE MOUNTING HEIGHTS ARE TO THE BOTTOM
OF THE FIXTURE UNLESS NOTED OTHERWISE.
CONTACTOR - NORMALLY OPEN
CONTACTOR - NORMALLY CLOSED
LINE TERMINATOR
ELECTRICAL CONNECTOR
GROUND
FUSE
DISCONNECT SWITCH
TRANSFORMER
JAGGED RESISTOR
VOLTAGE REGULATOR
3-PHASE MOTOR
WYE CONNECTION
SERVICE WEATHERHEAD
METER
CONTROL TRANSFORMER
POTENTIAL TRANSFORMER
CURRENT TRANSFORMER
CABLE POT HEAD
CIRCUIT BREAKER
DELTA CONNECTION
BATTERY
SURGE ARRESTOR
DRAW OUT, LOW VOLTAGE CIRCUIT BREAKER
GROUND FAULT RELAY
AUTOMATIC TRANSFER SWITCH
H.R.C FUSE RATING AS INDICATED ON DRAWING
RATINGS AS INDICATED ON DRAWING
H.R.C FUSED CUT-OUT
SURGE PROTECTION DEVICE
LIGHTNING ARRESTOR
POWER FACTOR CORRECTION CAPACITOR BANK
POTENTIAL TRANSFORMER WITH PRIMARY
AND SECONDARY FUSES
FULL VOLTAGE NON-REVERSIBLE MOTOR
STARTER AND OVERLOAD RELAY,
MOUNTED IN MOTOR CONTROL CENTER
REDUCED VOLTAGE (STAR/DELTA) NON-REVERSIBLE
MOTOR STARTER AND OVERLOAD RELAY, MOUNTED
IN MOTOR CONTROL CENTER
OVERLOAD RELAY
KEY INTERLOCK
AMMETER, VOLTMETER
AMMETER, VOLTMETER SELECTOR SWITCH
INDICATOR LAMP
STAND-BY DIESEL GENERATOR SET
POWER METER
ADDRESSABLE ELECTRONIC MODULE
DRAW OUT, MEDIUM VOLTAGE VACUUM
CIRCUIT BREAKER (VCB)
M
SPD
ASS VSS
K
AEM
PP
CP
VFD
M
DCP
POWER POLE
ELECTRICAL EQUIPMENT (TYPE OF EQUIPMENT AS INDICATED ON DRAWINGS)
RECESSED ELECTRICAL PANEL
SURFACE MOUNTED ELECTRICAL PANEL
CONTROL PANEL
DOOR CONTROL PANEL
COMBINATION DISCONNECT SWITCH / MOTOR STARTER
FUSED DISCONNECT SWITCH
NON-FUSED DISCONNECT SWITCH
SINGLE-PHASE MOTOR
THREE-PHASE MOTOR
MOTOR STARTER
VARIABLE FREQUENCY DRIVE
PUSHBUTTON - 2 BUTTON, W/ PILOT LIGHT
PUSHBUTTON - 3 BUTTON, W/ PILOT LIGHT
PUSHBUTTON - EMERGENCY OFF
ELECTRICAL BUS DUCT WITH FUSIBLE BUS PLUGS
UTILITY METER
PUSHBUTTON - 1 BUTTON, W/ PILOT LIGHT
RECEPTACLE, 240/208V, 3 PHASE, W/DISCONNECT - FUSED,
W/DISCONNECT - NON-FUSED - WALL
RECEPTACLE, 480V, 3 PHASE, W/DISCONNECT - FUSED,
W/DISCONNECT - NON-FUSED - WALL
MANUAL MOTOR STARTER
HOT
CONDUCTOR
GROUND
CONDUCTOR
NEUTRAL
CONDUCTOR
RECEPTACLE IDENTIFIERS:
"A" ABOVE COUNTER
"GFCI" GROUND FAULT CIRCUIT INTERRUPTER
"IG" ISOLATED GROUND
"PT" POKE THRU
"WP" WEATHERPROOF
"XP" EXPLOSION PROOF
SHUNT TRIP
ST
PM
1-PHASE MOTOR
EXISTING
NEW
LINETYPE LEGEND (ALL MAY NOT APPLY)
INSTANTANEOUS OVER CURRENT
OR DEFINITE TIME RELAY
INVERSE TIME OVER CURRENT RELAY
GROUND INSTANTANEOUS AND TIME
OVER CURRENT RELAY
50G/51G
ANSI RELAY DESIGNATIONS (ALL MAY NOT APPLY)
POWER FACTOR RELAY55
UNDERVOLTAGE RELAY27
OVERVOLTAGE PROTECTION RELAY59
FREQUENCY PROTECTION RELAY
74TC
LOCKOUT RELAY
DIFFERENTIAL PROTECTION RELAY87
DEMOLITION
CONDUIT DOWN
FIXED CAPACITOR
UNDERGROUND ELECTRICAL CONDUIT
CABLE TRAY (TYPE AND SIZE INDICATED ON DRAWINGS)
CABLE TRAY UP OR DOWN OR SECTION CUT
CR CORD REEL RECEPTACLE
COMBINATION FUSED DISCONNECT SWITCH / MOTOR STARTER
TB TEST BLOCK
TRIP CIRCUIT SUPERVISION
CIRCUIT BREAKER FAILURE PROTECTION
50BF
SENSITIVE GROUND CURRENT PROTECTION
50NS
CIRCUIT METER AND MONITORCMM
100% CONSTRUCTION
DOCUMENTS SUBMISSION
G
DATA OUTLET - WALL / FLOOR MOUNTED
AUXILIARY SYSTEMS SYMBOL LIST (ALL MAY NOT APPLY)
EWHITMAN
Image
EE002
ELECTRICAL GENERAL NOTES
AND ABBREVIATIONS
M.
SABAPATHY
F. KHAN
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
GENERAL NOTES:
ABBREVIATIONS
A
AFF
AFG
AHJ
AL
ATS
C
COMM
CP
CTRL
CU
DPM
ECC
EF
E.O
ER
ERR
FTV
G
GB
GFCI
HP
Hz
I.C
KA
KVA
LSIG
M
MAX
MCB
MIN
MLO
NC
NIC
NB
NO
P
PH
POS
PWR
RECEP
RGS
TR
TRU
UNO
V
W
WP
WAP
XP
AMPERES
ABOVE FINISHED FLOOR
ABOVE FINISHED GRADE
AUTHORITY HAVING JURISDICTION
ALUMINUM
AUTOMATIC TRANSFER SWITCH
CONDUIT
COMMUNICATIONS
CONTROL PANEL
CONTROL
COPPER
DIGITAL PANEL METER
EMPTY CONDUIT
EXHAUST FAN
ELECTRICALLY OPERATED
EXISTING REMOVE
EXISTING REMOVE REPLACE
FLIGHT TEST VEHICLE
GROUND
GROUND BUS
GROUND FAULT CIRCUIT INTERRUPTER
HORSEPOWER
HERTZ
INTERRUPTING CURRENT
KILO AMPERES
KILOVOLT-AMPERES
LONG TERM, SHORT TERM,
INSTANTANEOUS AND GROUND FAULT
PROTECTION RELAY
METER
MAXIMUM
MAIN CIRCUIT BREAKER
MINIMUM
MAIN LUGS ONLY
NORMALLY CLOSED
NOT IN CONTRACT
NEUTRAL BUS
NORMALLY OPEN
POLE
PHASE
POSITION
POWER
RECEPTACLE
RIGID GALVANIZED STEEL
TRANSFORMER
TRANSFORMER RECTIFIER UNIT
UNLESS NOTED OTHERWISE
VOLT
WIRE
WEATHER PROOF
WIRELESS ACCESS POINT
EXPLOSION PROOF
(ALL MAY NOT APPLY)
1. THE EXISTING SERVICE AGED CABLES THAT ARE BEING SLATED FOR RE-USE ARE RATED
FOR 15KV . THIS DETERMINATION HAS BEEN MADE BY VA.
2. ALL THE SERVICE AGED CABLES, SLATED FOR RE-USE, SHALL BE TESTED IN SITU USING
ONE OF THE FOLLOWING NON-DESTRUCTIVE TESTS:
a. ON-LINE PARTIAL DISCHARGE TESTING.
b. OFF-LINE PARTIAL DISCHARGE TESTING.
c. VERY LOW FREQUENCY (VLF) DISSIPATION FACTOR TESTING.
d. POWER FACTOR/DISSIPATION FACTOR TESTING.
3. ALL OR ANY PORTION OR PART OF THE SERVICE AGED CABLE THAT DOESN'T PASS ONE OF
THE ABOVE TESTS SHALL BE REPLACED IN KIND WITH PRIOR AND SPECIFIC WRITTEN
APPROVAL FROM THE COR AND CO THROUGH A FORMAL CONTRACT MODIFICATION. THE
NEW CABLE AND/OR SPLICE(S) SHALL COMPLY WITH THE SPECIFICATIONS.
4. THE CONTRACTOR SHALL COORDINATE ALL POWER OUTAGES WITH THE COR AT LEAST
TWO WEEKS IN ADVANCE. POWER OUTAGES SHALL BE RESTRICTED TO THE HOURS THAT
ARE NOT NORMAL BUSINESS HOURS. SEE NOTE #8 BELOW.
5. ONLY ONE OF THE THREE (3) 208Y/120V SWITCHBOARDS, #1, #2 AND #3, SHALL BE
REPLACED. AT A TIME, SO THAT BUILDING 1-WEST'S OPERATIONS AREN'T ADVERSELY
AFFECTED. ALSO, REFER TO NOTE #8 BELOW.
6. THE CONTRACTOR SHALL PROVIDE A SEQUENCE OF WORK SHOWING ALL PHASING, AS
NECESSARY, ALONG WITH THEIR BID, FOR THE COR'S AND ENGINEER'S APPROVAL.
7. ALL POWER OUTAGES SHALL BE COORDINATED TO MINIMIZE TO AN ABSOLUTE MINIMUM
HOW LONG AREAS OF THE FACILITY WILL BE WITHOUT NORMAL POWER. SEE NOTE #8
BELOW. ALSO, REFER TO NOTE #8 BELOW
8. WHERE ANY SCHEDULED POWER OUTAGE RESULTS IN A LOSS OF SERVICE FOR LONGER
THAN FOUR (4) HOURS, THE CONTRACTOR SHALL PROVIDE TEMPORARY POWER TO
SERVICE THE FACILITY SUCH THAT TOTAL POWER OUTAGE AT THE FACILITY SHALL NOT
EXCEED FOUR (4) HOURS.
IMPORTANT NOTES:
1. SCOPE OF WORK: ELECTRICAL DEMOLITION WORK SHALL INCLUDE DISCONNECTION OF
ELECTRICAL EQUIPMENT, WIRING, CONDUIT, BOXES, ETC. IN THE AREA OF NEW AND/OR
RENOVATION CONSTRUCTION.
2. SITE SURVEY: ELECTRICAL CONTRACTOR SHALL VISIT THE SITE PRIOR TO SUBMISSION
OF THEIR BID TO EXAMINE THE EXISTING CONDITIONS AND THE EXTENT OF THE
DEMOLITION WORK.
3. SITE UTILITIES: ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR LOCATING ALL EXISTING
UTILITIES. ELECTRICAL CONTRACTOR IS RESPONSIBLE FOR REQUESTING EXISTING
AVAILABLE AS-BUILT DRAWINGS FROM THE OWNER. ELECTRICAL CONTRACTOR IS FULLY
RESPONSIBLE FOR REPAIRING ALL DAMAGED UTILITIES RESULTING FROM
CONSTRUCTION RELATED ACTIVITIES.
4. COORDINATION WITH OTHER TRADES: EXAMINE ALL DRAWINGS BY OTHER TRADES TO BE
FAMILIAR WITH DEMOLITION REQUIREMENTS BY OTHER TRADES. PROVIDE ALL
INCIDENTAL ELECTRICAL DEMOLITION OF AND/OR RELOCATION OF ELECTRICAL SYSTEMS
TO FACILITATE THE DEMOLITION WORK FROM OTHER TRADES WHETHER OR NOT
INDICATED ON THE DRAWINGS.
5. COORDINATION: COORDINATE THE DEMOLITION WITH THE NEW WORK FOR THE EXTENT
OF DEMOLITION WORK.
6. RACEWAYS: REMOVE ALL UNUSED EXPOSED CONDUIT, WIRE, RACEWAY, JUNCTION
BOXES, HANGERS, AND CLAMPS BACK TO THE SOURCE. WHERE CONDUITS ARE
CONCEALED IN WALL CAVITIES, CUT AND REMOVE THE CONDUITS ABOVE EXISTING WALL
LEADING INTO AN ACCESSIBLE CEILING OR TRUSS SPACE. REMOVE SURFACE MOUNTED
ELECTRICAL DEVICES, BOXES, AND RELATED CONDUITS.
7. CONDUIT STATUS: FIELD VERIFY STATUS OF CONDUITS IN THE SPACE AND DETERMINE IF
CONDUITS ARE TO REMAIN OR BE REMOVED. WHERE APPLICABLE AND NOT
SPECIFICALLY INDICATED OTHERWISE, EXISTING IN-PLACE CONDUITS ABOVE CEILINGS
OR IN WALLS, JUNCTION BOXES, PULL BOXES, AND HANGERS ABOVE CEILINGS, TRUSS
SPACE, OR IN WALLS MAY BE RE-USED FOR NEW WIRING. COMPLY WITH CONDUIT FILL
REQUIREMENTS LISTED IN THE NEC.
8. ACTIVE CIRCUITS: EXISTING ACTIVE CIRCUITS IN WORK AREAS TO REMAIN. WHERE
REMOVAL OF CONDUIT AND WIRING AFFECTS THE OPERATION UPSTREAM AND/OR
DOWNSTREAM OF ELECTRICAL EQUIPMENT, WHICH IS NOT INDICATED TO BE REMOVED,
THE ELECTRICAL CONTRACTOR SHALL BE RESPONSIBLE TO MAINTAIN AND PROVIDE ALL
REQUIRED CONDUITS AND WIRING TO RESTORE THE UPSTREAM AND/OR DOWNSTREAM
CONNECTIONS OF ELECTRICAL EQUIPMENT TO ITS NORMAL OPERATION. ELECTRICAL
CONTRACTOR SHALL COORDINATE THIS WITH OWNER AND ASSOCIATED PARTIES.
9. FEEDERS: DISCONNECT AND REMOVE FEEDERS FROM THE ARCHITECTURAL AND
MECHANICAL EQUIPMENT TO BE REMOVED. COORDINATE WITH ARCHITECTURAL AND
MECHANICAL DRAWINGS AND CONTRACTORS FOR FULL SCOPE OF WORK. REMOVE ALL
DISCONNECTS, JUNCTION BOXES, AND CONTROL STATIONS.
10. LOW VOLTAGE CABLING: REMOVE UNUSED DATA/COMMUNICATION CONDUITS AND
CABLING COMING FROM TELEPHONE AND DATA CLOSETS. CONDUITS THAT ARE EXISTING
TO REMAIN SHALL BE TAGGED AS SUCH.COORDINATE WITH THE COR.
11. SUPPORT: RE-SUPPORT ITEMS WHERE WALLS AND SUPPORTS ARE SCHEDULED FOR
REMOVAL.
12. PROTECTION: PROTECT EXISTING ITEMS TO REMAIN FROM DAMAGE BY OTHER
DEMOLITION ACTIVITIES.
13. MATERIAL: MATERIAL INCLUDING, BUT NOT LIMITED TO, WIRING DEVICES, CONDUIT,
WIRING, JUNCTION BOXES, ETC. THAT IS REMOVED SHALL BECOME PROPERTY OF THE
ELECTRICAL CONTRACTOR, UNLESS OTHERWISE NOTED. THE ELECTRICAL CONTRACTOR
SHALL BE RESPONSIBLE FOR REMOVAL AND PROPER DISPOSAL OF THESE MATERIALS.
14. SALVAGED EQUIPMENT: ELECTRICAL EQUIPMENT INCLUDING, BUT NOT LIMITED TO,
PANELBOARD, TRANSFORMERS, LIGHT FIXTURES, DISCONNECT SWITCHES, CONTROL
PANELS, ETC. THAT IS REMOVED SHALL BE CLEANED AND RETURNED TO THE COR,
UNLESS THE COR ELECTS TO DISPOSE OF THIS EQUIPMENT.
DEMOLITION NOTES:
1. ALL ELECTRICAL WORK SHALL BE PERFORMED IN ACCORDANCE WITH THE NATIONAL ELECTRICAL CODE
2017 WITH STATE OF MICHIGAN AMENDMENTS (PART 8).
2. DRAWINGS ARE DIAGRAMMATICAL AND INDICATE DESIGN INTENT.
3. DO NOT SCALE DRAWINGS.
4. CONTRACTOR SHALL FIELD VERIFY EXISTING CONDITIONS AND ACTUAL DIMENSIONS PRIOR TO START OF
WORK.
5. THOROUGHLY COORDINATE ELECTRICAL WORK WITH OTHER TRADES TO AVOID PHYSICAL CONFLICTS AND
CONFLICTS WITH WORK SEQUENCE.
6. ALL WIRING SHALL BE #12 AWG UNLESS OTHERWISE NOTED, BRANCH CIRCUITS WITH LENGTH EXCEEDING
150FT SHALL BE #10 AWG MINIMUM.
7. ALL CONDUITS SHALL CONTAIN GROUND WIRE, SIZED PER NEC 2017, ART. 250.
8. ALL CONDUIT AND WIRING SHALL BE CONCEALED IN WALL OR CEILING CAVITY EXCEPT FOR EXISTING
BLOCK WALLS, AREAS WITH EXPOSED CEILING CONSTRUCTION. EXPOSED CONDUIT SHALL BE RGS UP TO
10 FT HEIGHT ABOVE FINISHED FLOOR, WHERE MOUNTED EXPOSED.
9. THE ELECTRICAL CONTRACTOR MAY, AT THEIR OPTION, REUSE A PORTION OR ALL OF EXISTING
MULTI-BRANCH CIRCUIT WIRING AND/OR CONDUIT(S) PROVIDED THEY MEET ALL THE REQUIREMENTS OF
THE NEW INSTALLATIONS (I.E., APPROPRIATE ROUTING, CONDUIT SIZE, CONDUIT TYPE, WIRE SIZE FOR
LENGTH WITH DERATING, TESTING ETC.).
10. BRANCH CIRCUIT WIRING SHALL BE DERATED PER NEC 310-15. DUE TO HARMONIC LOADING, THE NEUTRAL
CONDUCTOR SHALL BE CONSIDERED AS A CURRENT CARRYING CONDUCTOR FOR DERATING PURPOSES.
11. MAIN BRANCH CIRCUIT CONDUIT RUNS SHALL BE EMT. REFER TO SPECIFICATIONS FOR ADDITIONAL
RACEWAY RESTRICTIONS.
12. ALL EMPTY DUCTS AND CONDUITS SHALL BE DEBURRED, CLEANED, TAGGED AND PROVIDED WITH A NYLON
PULL STRING.
13. MOUNTING HEIGHTS OF ELECTRICAL DEVICES ARE TO CENTER OF DEVICE UNLESS OTHERWISE NOTED.
14. IN GENERAL, ELECTRICAL EQUIPMENT, WHICH ARE INDICATED ON THE PLAN MAY NOT BE SCALED, EXCEPT
WHERE DIMENSIONED OR ADDITIONAL LAYOUT CRITERIA IS INDICATED AT CRITICAL LOCATIONS.
15. WHEREVER 'PROVIDE' IS USED IN THE DRAWINGS AND SPECIFICATIONS, IT SHALL MEAN 'PROVIDE AND
INSTALL'.
16. ALL EMERGENCY WIRING SHALL BE IN SEPARATE CONDUIT FROM NON-EMERGENCY WIRING.
17. REFER TO THE ONE LINE DIAGRAMS FOR CONDUIT AND WIRE SIZES.
18. EXISTING ONE LINE DIAGRAMS WERE CREATED FROM AVAILABLE DRAWINGS AND INFORMATION.
ELECTRICAL CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CONDITIONS AND LOCATIONS PRIOR TO
START OF WORK.
19. ALL 120 VOLT BRANCH CIRCUITS SHALL BE PROVIDED WITH SEPARATE FULL SIZE NEUTRAL CONDUCTORS.
20. PROVIDE PULL BOXES AS REQUIRED TO INTERCEPT FEEDER AND BRANCH CIRCUITS AND EXTEND TO NEW
PANEL LOCATION. REFER TO SPECIFICATIONS FOR APPROVED SPLICING METHODS. LOCATE PULL BOXES IN
ACCESSIBLE LOCATIONS.
21. COORDINATE SEQUENCING AND TEMPORARY REQUIREMENTS TO MAINTAIN LIGHTING SYSTEM OPERATION
DURING CONSTRUCTION.
22. THE ELECTRICAL TRADES SHALL PROVIDE FIELD INVESTIGATION TO VISUALLY AND ELECTRICALLY TRACE
BRANCH CIRCUITS, WHICH ARE TO BE REMOVED. IF BRANCH CIRCUITS SERVE LIGHTING OR EQUIPMENT
OUTSIDE OF THE PROJECT SCOPE, THE EXISTING BRANCH CIRCUIT WIRING SHALL BE MAINTAINED TO
SERVE THESE LOADS.
23. FEEDER SIZES ARE BASED ON NEC 2017 ARTICLES 310.15, 310.60, 250.122, AND 110.14. CONDUIT SIZES
SELECTED ARE BASED ON RIGID METAL CONDUIT (UNLESS NOTED OTHERWISE) AND 40% CONDUIT FILL.
CONDUIT SIZE SHALL BE ADJUSTED AS REQUIRED FOR OTHER TYPES OF CONDUIT. UNLESS NOTED
OTHERWISE, THE CONDUCTOR SIZE IS BASED ON AN AMBIENT TEMPERATURE OF 60°C AND 600V
INSULATED COPPER CABLE APPLIED AT 60°C FOR TERMINATIONS RATED 100 AMPS AND LESS AND 75°C FOR
TERMINATIONS RATED MORE THAN 100 AMPS. CONDUCTOR SIZE IS A MINIMUM AND DOES NOT TAKE INTO
ACCOUNT VOLTAGE DROP OR DERATING. CONDUCTOR SIZE SHALL BE ADJUSTED AS REQUIRED PER NEC.
24. THE CONTRACTOR SHALL COMPLY WITH THE VA, LOCAL AND STATE RULES AND REGULATIONS WHILE
ACCESSING AND WORKING IN CONFINED SPACES, SUCH AS MANHOLES AND CABLE VAULTS.
THE CONTRACTOR IS FREE TO PROPOSE THEIR OWN SEQUENCE OF WORK SO AS TO KEEP THE
NUMBER AND DURATION OF POWER SHUTDOWNS TO THE LEAST NECESSARY.
THE PROPOSED SEQUENCE OF WORK BELOW ENVISIONS KEEPING THE EXISTING 13.2 KV, 4.8 KV
AND 208Y/120V POWER SYTSEMS OPERATIONAL, AS LONG AS IS PRACTICAL, WHILE INSTALLING
THE NEW 13.2 KV AND 208Y/120V SYSTEMS.
FEEDERS A#104 AND A#106 ORIGINATE IN THE MV SWITCHGEAR IN THE BASEMENT OF BUILDING
32 (ENERGY CENTER).
BUILDING 1-WEST
1. PHASE A:
A. PROVIDE THE 15 KV PRIMARY INCOMING AND TIE SWITCHGEAR (MVS-MAIN).
B. PROVIDE THE 15 KV FEEDER SWITCHGEAR (MVS-SWGR) ALONG WITH THE ASSOCIATED
UNDERGROUND DUCTS AND 15 KV CABLES.
C. TRANSFER BUILDINGS 1-WEST, #22, #28 AND THE LINAC BUILDING ON TO FEEDER /
SWITCH #A104.
D. LOCK OUT TAG OUT FEEDER #A106 IN THE MV SWITCHGEAR IN BUILDING 32 (ENERGY
CENTER). DISCONNECT THE 15 KV CABLES FROM FEEDER / SWITCH #A106 AND
RE-ROUTE, WITH ADDITIONAL CABLES, AS REQUIRED, TO MVS-MAIN. NEW CABLES
SHALL MATCH EXISTING. NEW CABLES SHALL BE CONNECTED TO THE EXISTING USING
DEADBREAK ELBOWS.
E. SHUTDOWN REQUIRED. DISCONNECT THE 208Y/120V SWITCHBOARD “SWBD-2” FROM
UNIT SUBSTATION #2 AND FEED IT FROM A SPARE 800A BREAKER IN 208Y/120V
SWITCHBOARD “SWBD-1”. USE DIESEL LOCOMOTIVE CABLE (DLO) RATED
FOR 600V, 90 DEG C, 4-1/C, 777.7 KCMIL AND 1-1/C 777.7 KCMIL GROUND.
F. SHUTDOWN REQUIRED. DISCONNECT THE 208Y/120V SWITCHBOARD “SWBD-3” FROM
UNIT SUBSTATION #3 AND FEED IT FROM A SPARE 800A BREAKER IN 208Y/120V
SWITCHBOARD “SWBD-1”. USE DIESEL LOCOMOTIVE CABLE (DLO) RATED
FOR 600V, 90 DEG C, 4-1/C, 777.7 KCMIL AND 1-1/C 777.7 KCMIL GROUND.
G. DISCONNECT UNIT SUBSTATIONS #2 AND #3 FROM THE 4.8 KV SOURCE AND REMOVE
FROM THE BUILDING.
2. PHASE B:
A. PROVIDE A MOBILE 500 KW, 208Y/120V DIESEL GENERATOR ALONG WITH AN ATS AND
THE NECESSARY CABLES AND CONTROL WIRING TO PROVIDE EMERGENCY POWER TO
THE BUILDING. THE GENERATOR SHALL BE CONNECTED TO ONE OF THE SPARE 1600A
BREAKERS IN THE UNIT SUBSTATION. THE MAIN BREAKERS, IN THE SUBSTATION SHALL
BE OPEN WHEN THE GENERATOR IS RUNNING.
B. PROVIDE THE RIGHT 15 KV AIR TERMINAL CHAMBER (ATC), ASSOCIATED 1000 KVA, 13.2
KV - 208Y/120V TRANSFORMER AND THE 208Y/120V SECONDARY DISTRIBUTION
SWITCHBOARD. CONNECT TO THE ASSOCIATED FEEDER IN MVS-SWGR.
C. SHUTDOWN REQUIRED. DISCONNECT SWBD-3 ON BOTH THE LINE SIDE AND THE LOAD
SIDE AND REMOVE FROM THE BUILDING. RETAIN LOAD SIDE FEEDERS FOR RE-USE.
D. PROVIDE SWITCHBOARDS #3-A AND #3-B. CONNECT THE LINE SIDE, OF EACH
SWITCHBOARD, TO THEIR FEEDERS IN THE UNIT SUBSTATION. CONNECT THE EXISTING
LOAD SIDE FEEDERS TO THE BREAKERS IN THE SWITCHBOARDS.
E. SHUTDOWN REQUIRED. DISCONNECT SWBD-2 ON BOTH THE LINE SIDE AND THE LOAD
SIDE AND REMOVE FROM THE BUILDING. RETAIN LOAD SIDE FEEDERS FOR RE-USE.
F. PROVIDE SWITCHBOARDS #2-A AND #2-B. CONNECT THE LINE SIDE, OF EACH
SWITCHBOARD, TO THEIR FEEDERS IN THE UNIT SUBSTATION. CONNECT THE EXISTING
LOAD SIDE FEEDERS TO THE BREAKERS IN THE SWITCHBOARDS.
G. SHUTDOWN REQUIRED. DISCONNECT SWBD-1 ON BOTH THE LINE SIDE AND THE LOAD
SIDE AND REMOVE FROM THE BUILDING. RETAIN LOAD SIDE FEEDERS FOR RE-USE.
H. PROVIDE SWITCHBOARDS #1-A AND #1-B. CONNECT THE LINE SIDE, OF EACH
SWITCHBOARD, TO THEIR FEEDERS IN THE UNIT SUBSTATION. CONNECT THE EXISTING
LOAD SIDE FEEDERS TO THE BREAKERS IN THE SWITCHBOARDS.
3. PHASE C:
A. DISCONNECT UNIT SUBSTATION #1 FROM THE 4.8 KV SOURCE AND REMOVE FROM THE
BUILDING.
B. PROVIDE THE LEFT 15 KV AIR TERMINAL CHAMBER (ATC) AND ASSOCIATED 1000 KVA,
13.2 KV - 208Y/120V TRANSFORMER. CONNECT TO THE ASSOCIATED FEEDER IN
MVS-SWGR.
C. PLACE BUILDINGS 1-WEST, #28 AND THE LINAC BUILDING ON THE NEW MVS-SWGR
SWITCH.
D. LOCK OUT TAG OUT FEEDER #A104 IN THE SWITCHGEAR IN BUILDING 32 (ENERGY
CENTER). DISCONNECT THE 15 KV CABLES FROM FEEDER / SWITCH #A104 AND
RE-ROUTE, WITH ADDITIONAL CABLES, AS REQUIRED, TO MVS-MAIN. NEW CABLES
SHALL MATCH EXISTING. CONNECT THE NEW CABLES, TO THE EXISTING, USING
DEADBREAK ELBOWS.
E. SHUTDOWN REQUIRED. REPLACE TRANSFORMER AT BUILDING #22 AND CONNECT
CABLES TO MVS-SWGR.
4. PHASE D:
A. PROVIDE THE GENERATOR TRANSFORMER (T-GEN) WITH ASSOCIATED CONDUITS AND
CABLES.
B. DISCONNECT THE GENERATOR DISTRIBUTION SWITCHGEAR ON BOTH THE LINE SIDE
AND THE LOAD SIDES AND REMOVE. RETAIN CABLES FOR RE-USE
C. PULL BACK THE MV CABLE FROM THE GENERATOR DISTRIBUTION SWITCHGEAR AND
TERMINATE AT THE 4800V TERMINALS OF THE GENERATOR TRANSFORMER (T-GEN).
D. PROVIDE 15KV CABLE, IN CONDUIT, BETWEEN T-GEN AND THE 15 KV SWITCHGEAR,
MVS-GEN.
E. PROVIDE THE 15 KV SWITCHGEAR, MVS-GEN, IN THE SAME LOCATION AS THE
GENERATOR DISTRIBUTION SWITCHGEAR AND RECONNECT TO BOTH THE ATS.
F. CONNECT THE LOAD SIDE OF BOTH THE ATS TO THE MV SWITCHGEAR, MVS-SWGR.
BUILDING 22
1. SHUTDOWN REQUIRED. DISCONNECT THE EXISTING PAD-MOUNTED TRANSFORMER
AND REMOVE. RETAIN THE ASSOCIATED MV AND 600V CABLES FOR RE-USE.
2. PROVIDE THE PAD-MOUNTED TRANSFORMER.
3. CONNECT THE EXISTING MV AND 600V CABLES TO THE PAD-MOUNTED TRANSFORMER.
BUILDING 28
1. PROVIDE THE 15 KV SWITCHGEAR AND PAD-MOUNTED TRANSFORMER.
2. PROVIDE THE ASSOCIATED UNDERGROUND DUCTS, FROM THE EXISTING MANHOLE TO
THE 15 KV SWITCHGEAR AND THE 15 KV CABLES.
3. PROVIDE THE 600V CABLES, IN CONDUIT, FROM THE PAD-MOUNTED TRANSFORMER
SECONDARY TO THE 480V SECTION IN THE ELECTRICAL ROOM.
4. PROVIDE A MOBILE 500 KW, 480Y/277V DIESEL GENERATOR ALONG WITH THE
NECESSARY CABLES AND CONTROL WIRING TO PROVIDE TEMPORARY POWER TO THE
BUILDING.
5. SHUTDOWN REQUIRED. DISCONNECT THE EXISTING MV SWITCHGEAR AND DRY-TYPE
TRANSFORMER AND REMOVE FROM THE BUILDING. PROVIDE THE 480V SECTION AND
CONNECT IT TO THE EXISTING 480V SWITCHBOARD. TERMINATE 600V CABLES.
6.
LINAC BUILDING
1. SHUTDOWN REQUIRED. DISCONNECT THE EXISTING PAD-MOUNTED TRANSFORMER
AND REMOVE ALONG WITH THE ASSOCIATED MV CABLE FROM THE MANHOLE. RETAIN
600V CABLES FOR RE-USE.
2. PROVIDE A MOBILE 500 KW, 480Y/277V DIESEL GENERATOR ALONG WITH THE
NECESSARY CABLES AND CONTROL WIRING TO PROVIDE TEMPORARY POWER TO THE
BUILDING.
3. PROVIDE THE 15 KV SWITCHGEAR AND PAD-MOUNTED TRANSFORMER.
4. PROVIDE THE ASSOCIATED UNDERGROUND DUCTS, FROM THE EXISTING MANHOLE TO
THE 15 KV SWITCHGEAR AND THE 15 KV CABLES.
5. CONNECT THE 600V CABLES TO THE PAD-MOUNTED TRANSFORMER.
PROPOSED SEQUENCE OF WORK
11/18/19
100% CONSTRUCTION
DOCUMENTS SUBMISSION
BLDG. 22
BLDG. 1-W
BLDG. 28
AMBULANCE
ENTRANCE
LINAC
ED101
ELECTRICAL COMPOSITE SITE
PLAN - DEMOLITION
M.
SABAPATHY
I. ORTIZ
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
T-22
T-LINAC
T-28
(E) 480Y/277V
SWITCH BOARD
LINEWEIGHT LEGEND:
NEW ITEMS.
ITEMS TO BE REMOVED OR
RELOCATED.
EXISTING ITEMS TO REMAIN.
GENERAL NOTES:
1. THE DRAWINGS AND SPECIFICATIONS ARE FOR DESIGN INTENT.
ALTHOUGH INTENDED TO CONVEY INFORMATION AS ACCURATELY
AS POSSIBLE, THE DRAWING IS BASED MOSTLY ON EXISTING
AS-BUILT DRAWINGS AND SOME FIELD VERIFICATIONS.
CONTRACTOR SHALL VERIFY FIELD CONDITIONS BEFORE
COMMENCING WORK AND NOTIFY ENGINEER/ARCHITECT
CONCERNING MAJOR DISCREPANCIES.
2. REFER TO SHEET EE001 FOR ELECTRICAL SYMBOLS LIST.
3. REFER TO SHEET EE002 FOR GENERAL AND DEMOLITION NOTES
AND ABBREVIATIONS.
4. DISCONNECT POWER TO THE EXISTING ELECTRICAL EQUIPMENT
TO BE REMOVED. COORDINATE WITH CIVIL DRAWINGS AND
CONTRACTORS FOR THE FULL SCOPE OF DEMOLITION WORK.
5. (E) INDICATES EXISTING TO REMAIN.
6. ELECTRICAL CONTRACTOR SHALL CONFIRM BRANCH CIRCUIT
WIRING TO REMAIN DURING DEMOLITION WORK. ROUTE AND
EXTEND EXISTING CIRCUITS TO REMAIN TO NEW ELECTRICAL
EQUIPMENT.
7. FIELD VERIFY SIZES, LOCATIONS, ELEVATIONS, AND DETAILS OF
ALL EXISTING CONSTRUCTION AND CONDITIONS THAT AFFECT
THE WORK BEFORE PROCEEDING WITH THIS WORK.
8. PROVIDE SHORING, SHEETING, UNDERPINNING, AND ALL OTHER
MEANS REQUIRED TO PROTECT AND MAINTAIN THE SAFETY,
INTEGRITY, AND STABILITY OF ALL EXISTING AND NEW
CONSTRUCTION THAT MAY BE AFFECTED BY WORK.
9. VERIFY AND IDENTIFY ANY MISCELLANEOUS CONDUIT OR
EQUIPMENT NOT INDICATED ON THE DRAWINGS PRIOR TO
DEMOLITION.
10. SITE CLEAN-UP IS REQUIRED ON A DAILY BASIS.
11. WHERE FEASIBLE, EXISTING EQUIPMENT SHALL BE REMOVED
ONLY AFTER THE NEW EQUIPMENT HAS BEEN INSTALLED, TESTED
AND COMMISSIONED. REFER TO THE PROPOSED SEQUENCE OF
WORK ON SHEET EE002.
12. REFER TO THE ONE LINE DIAGRAM ON SHEET ED601.
ED401
MH-P2
MH-P6
MH-P102
MH-P4
MV SWITCH
KEY NOTES:
1. TRANSFORMER SHALL BE REPLACED. EXISTING PRIMARY AND
SECONDARY CABLES SHALL BE RETAINED FOR RE-USE.
2. TRANSFORMER SHALL BE REPLACED. EXISTING SECONDARY
CABLES SHALL BE RETAINED FOR RE-USE. REMOVE PRIMARY
CABLES BACK TO THE MANHOLE, MH-P2.
3. MV SWITCH AND TRANSFORMER SHALL BE REPLACED. REMOVE
PRIMARY CABLES BACK TO THE MANHOLE, MH-P4. THE 480Y/277V
SWITCHBOARD SHALL BE RETAINED FOR RE-USE.
4. EXISTING 1500KW/1875KVA GENERATOR AND SWITCHGEAR
LOCATED IN THE GENERATOR ROOM
IMPORTANT NOTE:
REFER TO PROPOSED SEQUENCE OF
WORK ON SHEET EE002
N
0 105
MV SWITCH
11/18/19
100% CONSTRUCTION
DOCUMENTS SUBMISSION
AutoCAD SHX Text 1W
AutoCAD SHX Text 1E
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text T2
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text
SEE DETAIL FOR TUNNEL FACILITIES
AutoCAD SHX Text
TC
AutoCAD SHX Text
FO
AutoCAD SHX Text
TC
AutoCAD SHX Text
FO
AutoCAD SHX Text 4"G
AutoCAD SHX Text 4"G
AutoCAD SHX Text 4"G
AutoCAD SHX Text
1 1/2"OXY
AutoCAD SHX Text
1 1/2"OXY
AutoCAD SHX Text
2"OXY
AutoCAD SHX Text
4"FUEL
AutoCAD SHX Text
2"FUEL
AutoCAD SHX Text
2"FUEL
AutoCAD SHX Text
1/2"OXY
AutoCAD SHX Text
QLD
AutoCAD SHX Text T
AutoCAD SHX Text
SYMBOLS
AutoCAD SHX Text
SYMBOLS
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text
WALK
AutoCAD SHX Text
WALK
AutoCAD SHX Text
WALK
AutoCAD SHX Text
WALK
AutoCAD SHX Text 6"
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text H
AutoCAD SHX Text H
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P&S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text 3"G
AutoCAD SHX Text G
AutoCAD SHX Text G
AutoCAD SHX Text 6"G-100#
AutoCAD SHX Text 6"
AutoCAD SHX Text
1"STM
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text
CONC.
AutoCAD SHX Text 1 1/2"G
AutoCAD SHX Text 2"G
AutoCAD SHX Text
CB-22
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text
NTS
AutoCAD SHX Text
%%USITE KEY MAP
ENTRANCE
ED401
ELECTRICAL ENLARGED PLAN
BUILDING 1 - WEST
M.
SABAPATHY
I. ORTIZ
(E) MV UNIT SUBSTATION
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
GENERAL NOTES:
1. THE DRAWINGS AND SPECIFICATIONS ARE FOR DESIGN INTENT.
ALTHOUGH INTENDED TO CONVEY INFORMATION AS ACCURATELY
AS POSSIBLE, THE DRAWING IS BASED MOSTLY ON EXISTING
AS-BUILT DRAWINGS AND SOME FIELD VERIFICATIONS.
CONTRACTOR SHALL VERIFY FIELD CONDITIONS BEFORE
COMMENCING WORK AND NOTIFY ENGINEER/ARCHITECT
CONCERNING MAJOR DISCREPANCIES.
2. REFER TO SHEET EE001 FOR ELECTRICAL SYMBOLS LIST.
3. REFER TO SHEET EE002 FOR GENERAL AND DEMOLITION NOTES
AND ABBREVIATIONS.
4. DISCONNECT POWER TO THE EXISTING ELECTRICAL EQUIPMENT
TO BE REMOVED. COORDINATE WITH CIVIL DRAWINGS AND
CONTRACTORS FOR THE FULL SCOPE OF DEMOLITION WORK.
5. (E) INDICATES EXISTING TO REMAIN.
6. ELECTRICAL CONTRACTOR SHALL CONFIRM BRANCH CIRCUIT
WIRING TO REMAIN DURING DEMOLITION WORK. ROUTE AND
EXTEND EXISTING CIRCUITS TO REMAIN TO NEW ELECTRICAL
EQUIPMENT.
7. FIELD VERIFY SIZES, LOCATIONS, ELEVATIONS, AND DETAILS OF
ALL EXISTING CONSTRUCTION AND CONDITIONS THAT AFFECT
THE WORK BEFORE PROCEEDING WITH THIS WORK.
8. PROVIDE SHORING, SHEETING, UNDERPINNING, AND ALL OTHER
MEANS REQUIRED TO PROTECT AND MAINTAIN THE SAFETY,
INTEGRITY, AND STABILITY OF ALL EXISTING AND NEW
CONSTRUCTION THAT MAY BE AFFECTED BY WORK.
9. VERIFY AND IDENTIFY ANY MISCELLANEOUS CONDUIT OR
EQUIPMENT NOT INDICATED ON THE DRAWINGS PRIOR TO
DEMOLITION.
10. SITE CLEAN-UP IS REQUIRED ON A DAILY BASIS.
11. WHERE FEASIBLE, EXISTING EQUIPMENT SHALL BE REMOVED
ONLY AFTER THE NEW EQUIPMENT HAS BEEN INSTALLED, TESTED
AND COMMISSIONED. REFER TO THE PROPOSED SEQUENCE OF
WORK ON SHEET EE002.
12. REFER TO THE ONE LINE DIAGRAM ON SHEET ED601.
UNIT SUBSTATION-1
UNIT SUBSTATION-3
UNIT SUBSTATION-2
SWBD-1
SWBD-3
SWBD-2
(E) ATS
(E) ATS-3
(E) ATS-5-6
(E) ATS-5-5
(E) ATS
(E) BLDG 26
EMER LTG
ATS
(E) (E)
(E) CC-B2
FLAGPOLE TO
BE RELOCATED
(BY OTHERS)
LINEWEIGHT LEGEND:
NEW ITEMS.
ITEMS TO BE REMOVED OR
RELOCATED.
EXISTING ITEMS TO REMAIN.
SITE LTS.
WEST (E) LP-A (E) PP-A
EXH. FAN #1
EXH. FAN #2
EXH. FAN #3
(E) ASCO
LIGHTING
CONTACTOR
SWBD (E) PUMP
CONTROLLER
(E) AMBULANCE
GARAGE X-FMR
(E) AUTOMATIC TRANSFER
SWITCHES
GENERATOR DISTRIBUTION
SWITCHGEAR
MH-P7
KEY NOTES:
1. REMOVE ASSOCIATED MV CABLE BACK TO THE POWER SOURCE.
2. EXISTING LOW VOLTAGE (LV) FEEDER CABLE SHALL BE RETAINED
FOR RE-USE.
2 2
IMPORTANT NOTE:
REFER TO PROPOSED SEQUENCE OF
WORK ON SHEET EE002
MV
FUSE
FDR
# A106
FDR
# A104
1500 KVA
TRANSFORMER
CABLE
# 14
CABLE
# 4
ISOLATION BANK 'A' ISOLATION BANK 'A'
SECONDARY
SELECTOR SWITCHES
ISOLATION BANK 'B'
SECONDARY
SELECTOR SWITCHES
CABLE
# 15
CABLE
# 3
1000 KVA
TRANSFORMER
MV
FUSE
FDR
# A104
FDR
# A106
ISOLATION BANK 'B'
BAY A BAY B I/C
ISOLATION BANK 'A' ISOLATION BANK 'B'
(E) PULL BOX
N
0 105
11/18/19
100% CONSTRUCTION
DOCUMENTS SUBMISSION
AutoCAD SHX Text B3-15
AutoCAD SHX Text B3-16
AutoCAD SHX Text P
AutoCAD SHX Text D
AutoCAD SHX Text
NTS
AutoCAD SHX Text
%%USITE KEY MAP
100E
125E
200E
125E
125E
500KVA
30KVA
LINEAR
ACCELERATOR
500KVA
750KVA
NURSING
HOME
BUILDING #28
480Y/277V
3Ø, 4w
SWITCHBOARD
MANHOLE MH-P3
MANHOLE MH-P4
MANHOLE MH-P2
MANHOLE P6
MANHOLE MH-P5
BUILDING #22
DISTRIBUTION
CENTER #2
SOUTH
METER
HOUSE
125E
250E
EXISTING 3-1/C - 350Kcmil, EPR, 15KV, SHIELDED
133% INSULATION
133% INSULATION
EXISTING
3-1/C - 350KCMIL,
EPR, 15KV,
SHIELDED
EXISTING
3-1/C - 350KCMIL,
EPR, 15KV,
SHIELDED
133% INSULATION
WIRE LEGEND:
3 - 1/C - 15KV, 133% SHIELDED INSULATION, 350Kcmil EPR &
1 - #350Kcmil XHHW GRD IN 5" PVC DUCTBANK
3 - 1/C - 15KV, 133% SHIELDED INSULATION, 500Kcmil EPR &
1 - #500Kcmil XHHW GRD IN 5" PVC DUCTBANK
600A
3P
600A
3P
300E
300E
600A
3P
600A
3P
BUILDING 1-W
ISOLATION BANK "A"
1200A/
300A
SITE GENERATOR
1500KW/1875KVA, 4800V, 3P, 4W
600A
3P
600A
3P
125E
BUILDING 1-W
ISOLATION BANK "B"
1500KVA
WITH FAN COOLING
13,200-4800V, 3PH, 3W
250E
600A
3P
600A
3P
600A
3P
600A
3P
1000KVA
WITH FAN COOLING
13,200-4800V, 3 , 3W
600A
3P
600A
3P
250E
ISOLATION BANK B
MOTORIZED OPERATED
AUTOMATIC TRANSFER SWITCH
ISOLATION BANK A
MOTORIZED OPERATED
AUTOMATIC TRANSFER SWITCH
K
K
K
ISOLATION BANK B
SECONDARY SELECTOR
SWITCHES
ISOLATION BANK A
SECONDARY SELECTOR
SWITCHES
ISOLATION BANK A
PRIMARY SELECTOR
SWITCHES
ISOLATION BANK B
PRIMARY SELECTOR
SWITCHES
KEY INTERLOCK
SO ONLY ONE
SWITCH CAN BE
CLOSED AT A TIME
TYPICAL
PRIMARY FEEDER #A-106
13200V, 3PH, 3W FROM MANHOLE, PS102
PRIMARY FEEDER #A-104
13200V, 3PH, 3W FROM MANHOLE, PS102
750KVA
4800-208/120V
3PH, 4W
750KVA
4800-208/120V
3 , 4W
750KVA
4800-208/120V
3PH, 4W
GENERATOR DISTRIBUTION
SWITCHGEAR
COPPER
BUS LINK
COPPER
BUS LINK
CABLE #4
CABLE #3
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
LINEWEIGHT LEGEND:
NEW ITEMS.
ITEMS TO BE REMOVED OR
RELOCATED.
EXISTING ITEMS TO REMAIN.
ED601
ELECTRICAL ONE LINE
DIAGRAM - DEMOLITION
M. SABAPATHY I. ORTIZ07/31/19
GENERAL NOTES:
1. REFER TO SHEET EE001 FOR ELECTRICAL SYMBOLS LIST.
2. REFER TO SHEET EE002 FOR GENERAL AND DEMOLITION NOTES,
ABBREVIATIONS AND PROPOSED SEQUENCE OF WORK.
125E
95% CONSTRUCTION
DOCUMENTS
PULL BOX IN CABLE
VAULT BELOW
SUBSTATION ROOM
PULL BOX IN
BUILDING 1-W
CRAWL SPACE
T-22
CABLE #15
CABLE #3
CABLE #4
CABLE #14
CABLE #15
CABLE #15
CABLE #15
CABLE #14
CABLE #14
CABLE #14
CABLE #14
CABLE #15
CABLE #14
MV SWITCH
T-28
B
B
B
B
B
B
B
B
B
A
MV SWITCH
ABOVE GROUND
PULL BOX
UNIT SUBSTATION 3
UNIT SUBSTATION 2
UNIT SUBSTATION 1
208Y/120V
SWITCHBOARD #3
SWBD - 3
208Y/120V
SWITCHBOARD #2
SWBD - 2
208Y/120V
SWITCHBOARD #1
SWBD - 1
ABOVE GROUND
PULL BOX
DEAD BREAK
JUNCTION (TYPICAL)
T - LINCA
AutoCAD SHX Text
AutoCAD SHX Text G
AutoCAD SHX Text K
AutoCAD SHX Text K
AutoCAD SHX Text K
AutoCAD SHX Text K
AutoCAD SHX Text K
AutoCAD SHX Text 80E
AutoCAD SHX Text 80E
BLDG. 22
BLDG. 1-W
BLDG. 28
AMBULANCE
ENTRANCE
LINAC
ES101
ELECTRICAL COMPOSITE SITE
PLAN
M.
SABAPATHY
I. ORTIZ
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
LINEWEIGHT LEGEND:
NEW POWER
CONTROL
EXISTING POWER
ES403
ES404
ES402
ES401
GENERAL NOTES:
1. THE DRAWINGS AND SPECIFICATIONS ARE FOR DESIGN INTENT.
ALTHOUGH INTENDED TO CONVEY INFORMATION AS ACCURATELY
AS POSSIBLE, THE DRAWING IS BASED MOSTLY ON EXISTING
AS-BUILT DRAWINGS AND SOME FIELD VERIFICATIONS.
CONTRACTOR SHALL VERIFY FIELD CONDITIONS BEFORE
COMMENCING WORK AND NOTIFY ENGINEER/ARCHITECT
CONCERNING MAJOR DISCREPANCIES.
2. REFER TO SHEET EE001 FOR ELECTRICAL SYMBOLS LIST.
3. REFER TO SHEET EE002 FOR GENERAL AND DEMOLITION NOTES
AND ABBREVIATIONS.
4. DISCONNECT POWER TO THE EXISTING ELECTRICAL EQUIPMENT
TO BE REMOVED. COORDINATE WITH CIVIL DRAWINGS AND
CONTRACTORS FOR THE FULL SCOPE OF DEMOLITION WORK.
5. (E) INDICATES EXISTING TO REMAIN.
6. ELECTRICAL CONTRACTOR SHALL CONFIRM BRANCH CIRCUIT
WIRING TO REMAIN DURING DEMOLITION WORK. ROUTE AND
EXTEND EXISTING CIRCUITS TO REMAIN TO NEW ELECTRICAL
EQUIPMENT.
7. FIELD VERIFY SIZES, LOCATIONS, ELEVATIONS, AND DETAILS OF
ALL EXISTING CONSTRUCTION AND CONDITIONS THAT AFFECT
THE WORK BEFORE PROCEEDING WITH THIS WORK.
8. PROVIDE SHORING, SHEETING, UNDERPINNING, AND ALL OTHER
MEANS REQUIRED TO PROTECT AND MAINTAIN THE SAFETY,
INTEGRITY, AND STABILITY OF ALL EXISTING AND NEW
CONSTRUCTION THAT MAY BE AFFECTED BY WORK.
9. VERIFY AND IDENTIFY ANY MISCELLANEOUS CONDUIT OR
EQUIPMENT NOT INDICATED ON THE DRAWINGS PRIOR TO
DEMOLITION.
10. SITE CLEAN-UP IS REQUIRED ON A DAILY BASIS.
11. WHERE FEASIBLE, EXISTING EQUIPMENT SHALL BE REMOVED
ONLY AFTER THE NEW EQUIPMENT HAS BEEN INSTALLED, TESTED
AND COMMISSIONED. REFER TO THE PROPOSED SEQUENCE OF
WORK ON SHEET EE002.
12. REFER TO THE ONE LINE DIAGRAMS ON SHEETS EP601, EP602,
EP603 AND EP604.
13. REFER TO THE CIVIL DRAWINGS FOR THE CONCRETE PAD
DETAILS.
IMPORTANT NOTE:
REFER TO PROPOSED SEQUENCE OF
WORK ON SHEET EE002
N
0 105
MH-PS102
MH-P6
11/18/19
100% CONSTRUCTION
DOCUMENTS SUBMISSION
AutoCAD SHX Text 1W
AutoCAD SHX Text 1E
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text T2
AutoCAD SHX Text
SEE DETAIL FOR TUNNEL FACILITIES
AutoCAD SHX Text
TC
AutoCAD SHX Text
FO
AutoCAD SHX Text
TC
AutoCAD SHX Text
FO
AutoCAD SHX Text 4"G
AutoCAD SHX Text 4"G
AutoCAD SHX Text 4"G
AutoCAD SHX Text
1 1/2"OXY
AutoCAD SHX Text
1 1/2"OXY
AutoCAD SHX Text
2"OXY
AutoCAD SHX Text
4"FUEL
AutoCAD SHX Text
2"FUEL
AutoCAD SHX Text
2"FUEL
AutoCAD SHX Text
1/2"OXY
AutoCAD SHX Text
QLD
AutoCAD SHX Text T
AutoCAD SHX Text
SYMBOLS
AutoCAD SHX Text
SYMBOLS
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text 6"
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text H
AutoCAD SHX Text H
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P&S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text P
AutoCAD SHX Text
1"STM
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text S
AutoCAD SHX Text P
AutoCAD SHX Text
CB-22
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text E
AutoCAD SHX Text
NTS
AutoCAD SHX Text
%%USITE KEY MAP
AMBULANCE
ENTRANCE
ES401
ELECTRICAL ENLARGED PLAN
BUILDING 1 - WEST
M.
SABAPATHY
I. ORTIZ
UNIT SUBSTATION- SS1W
13.2KV - 208Y/120V
15 KV
SWITCHGEAR #1
15 KV PRIM.
FEEDER AND TIE
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN, INC.
1221 N. PENNSYLVAINA STREET
INDIANAPOLIS, IN 46204
317.800.6388
STACEY PAUL
ELECTRICAL ENGINEER:
GHAFARI ASSOCIATES
17101 MICHIGAN AVE.
DEARBORN, MI 48126
UPGRADE ELECTRICAL
SWITCHGEAR & DISTRIBUTION
ANN ARBOR VAMC
506-18-102
N/A Project Director
Revisions: Date:
SUITE 200
PROJECT NUMBER: 187371
313.441.3000
JEFF PEDERSEN
SWITCHBOARD #3-A
(E) FLAGPOLE
TEST
WELL
SWITCHBOARD #3-B SWITCHBOARD #2-A SWITCHBOARD #2-B
SWITCHBOARD #1-A SWITCHBOARD #1-B
T-GEN
TEST WELL
LINEWEIGHT LEGEND:
NEW POWER
CONTROL
EXISTING POWER
15KV
MVS-GEN
ATS EQUIPMENT
BY OTHERS
FRONT
FRONT
FRONT
FRONT
FRONT
SITE LTS.
WEST
(E) LP-A (E) PP-A
EXH. FAN #1
EXH. FAN #2
EXH. FAN #3
(E) ASCO
LIGHTING
CONTACTOR
SWBD (E) PUMP
CONTROLLER
(E) AMBULANCE
GARAGE X-FMR
(E) PANEL
(E) PANEL
CC-B2
(E) POWER
LOGIC PANEL
FRONT
FRONT
3'-0" MINIMUM
INSTALL IN PHASE A
INSTALL IN PHASE B
TO EXISTING GROUND
BUS IN THE CABLE VAULT
TO EXISTING GROUND
BUS IN THE CABLE VAULT
KEY NOTES:
1. BOLT WITH LUGS, TO EXISTING BUS BAR (TYPICAL TO PRIMARY AND
SECONDARY SIDES OF TRANSFORMERS)
2. BOLLARDS ( SEE CIVIL DRAWINGS ).
3. OPENINGS IN THE FLOOR SLAB SHALL BE COVERED WITH STEEL PLATES OF
ADEQUATE STRENGTH AND SIZE.
4. INSTALL A 4" SQUARE, 2 1/8 " DEEP OUTLET BOX WITH A SINGLE GANG
ADJUSTABLE MUD RING AND 1" CONDUIT, STUBBED 6" INTO THE CEILING
SPACE. ELECTRICAL CONTRACTOR SHALL INSTALL (4) DATA OUTLETS, FACE
PLATE AND…
This is the start of the file's text. The full file is on GovTribe.