5 SOW 573A4-18-601 (REV).docx
DOCX document 32 KB Posted
- Attached to
- Expand Electrical Distribution Federal contract opportunity
- Solicitation number
- 36C24823R0102
About this file
This statement of work outlines requirements for an electrical distribution expansion project at the Lake City VA Medical Center in Lake City, Florida. The contractor shall demolish existing structures, prepare the site, and furnish all labor, materials, and work to expand electrical distribution per project drawings and specifications. Key tasks include upgrading the substation, generator, and electrical system to divide branches into normal, life safety, critical, and equipment categories. The contractor must complete all work within 365 calendar days of receiving notice to proceed and coordinate all construction to minimize disruptions to hospital operations. The contractor is responsible for safety compliance, maintaining access and security, submitting required documentation like schedules, meeting minutes and as-built drawings, and using union labor.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 3 CATEX Form_573A4-18-601.pdf | ||
| S02 AMEND 36C24823R0102 0002 RFI.pdf | ||
| PRICE SCHEDULE.docx | DOCX document | |
| RFI QUESTIONS and GOVERNMENT RESPONSES.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Expand Electrical Distribution Project: 573A4-18-601 Form 2237: 573-23-1-3286-0001 LAKE CITY VA Medical Center Part I – General A. Scope of Work (SOW)
1. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for Project 573A4-18-601 Expand Electrical Distribution as required by drawings and specifications.
2. This document does not relieve the construction contractor of his/her professional responsibility to conduct and produce a correct, complete and fully coordinated work.
3. The following documents are part of the contract documents:
3.1. Specification Section 01 00 00 General Requirements
3.2. Photos of Manhole and Manhole Contents
3.3. Asbestos-containing materials (ACM) and lead containing paint (LCP) Report
3.4. VA NEPA Categorical Exclusion Determination
3.5. Bid Deducts:
1. ALTERNATE NO.1: Eliminate the Critical #1 ATS (C1ATS).
2. Alternate No. 2: Eliminate the Critical #2 ATS (C2ATS).
3. Alternate No. 3: Eliminate the Equipment ATS (EATS).
4. Alternate No. 4: Eliminate all work associated with refeeding the fire pump, including conduit, wire, MI cable, etc.
5. Alternate No. 5: Eliminate the normal feed to the three ATS (EATS, C1ATS, and C2ATS), including conduit, wire, and terminations.
6. Alternate No. 6: Eliminate the emergency feed to the three ATS (EATS, C1ATS, and C2ATS), including conduit, wire, and terminations.
7. Alternate No. 7: Eliminate the six circuit breakers feeding the three ATS. Assume 4x400 amp, molded case breakers, and 2x800amp molded case breakers.
8. Alternate No. 8: Keep the two exhaust fans and associated wiring on the generator building roof.
9. Alternate No. 9: Do not reroof the generator building.
10. Alternate No. 10: Keep the two exhaust fans and associated wiring on the substation building roof.
11. Alternate No. 11: Do not reroof the substation building.
12. Alternate No. 12: Eliminate fitting out the fourth-floor vertical electrical closet.
13. Alternate No. 13: Eliminate fitting out the third-floor vertical electrical closet.
14. Alternate No. 14: Do not install the conduit from the generator equipment room to the fire pump.
15. Alternate No. 15: Eliminate installing the empty conduit to the fire pump. The approximate distance is 100’.
16. Alternate No. 16: Eliminate gutting and reworking the basement vertical closet.
17. Alternate No. 17: Eliminate removing the ceilings in all the vertical closets.
B. General Project Description
1. Work includes but is not limited to, all labor, material, equipment and supervision to expand electrical distribution, at the Lake City VA Medical Center in Lake City, FL. – VA Project Number 573A4-18-601.
2. The existing electrical feeder cable is beyond its useable lifespan. Additionally, the facility has replaced 3 feeder circuits that have failed. All cables that were replaced were installed in the same timeframe as the feeder cable in question. The facility also does not meet the NFPA requirements for separation of Life Safety, Critical and equipment branches
3. The project intent is to upgrade the electrical system at the Lake City VA Medical Center, Lake City, Florida. The upgrade will include a new substation (which includes the MV switches, transformer, Main circuit breaker, bus duct, and 208-volt switchgear with new equipment) a new generator, new EES equipment (all rated 480/277-volts), and it will divide the electrical system into five electrical branches: Normal, Life Safety, Critical-1, Critical-2, and Equipment branches.
4. Construction work includes, but is not limited to, demolition, site preparation, architectural finishes, mechanical and electrical work.
5. All work shall be performed per the project’s design drawings and specifications and the RFI’s responses as art of the bidding process.
6. Contractor shall timely discuss with VA means and methods of construction that may impact the facility inside/outside VA premises.
C. Definitions
1. Contracting Officer (CO): The services to be performed under this contract are subject to the general supervision, direction, control and approval of the CO.
2. VA Project Manager (PM): The Contracting Officer’s Technical Representative (COR) responsible for administering contracts under the immediate direction of the CO and the PM/COR at the construction site. When more than one PM/COR is assigned to a construction project one is designated as being in-charge and is called the “Senior PM/COR”. The PM/COR is responsible for protecting the Government’s interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of changed work, approval of all submittals, samples, shop drawings, etc.
3. Contractor: This term, as used herein, refers to the Contractor under this contract.
4. A/E: This term, as used herein, refers to the Architect-Engineer firm that is part of the design team (Government Consultant).
D. Tentative Schedule
1. Period of Performance – The contractor shall complete the work required under this Scope of Work within three hundred sixty-five (365) calendar days from receipt of “Notice to Proceed” (NTP). Working hours will vary depending on the tasks being accomplished. Work affecting hospital’s operations must be done after 5 p.m. in the afternoon and with timely advance coordination through VA’s Project Manager/COR.
Part II – Responsibilities
1. The RFP documents are intended to define existing conditions, certain required items and design parameters to be included in the project. It is the Contractor’s responsibility to complete the documents and construction in a manner consistent with the intent of the RFP documents within the required time period (contract length).
2. Prior to any mobilization and construction, the contractor shall request and have approved an Infection Control Construction Permit, a Construction Safety Certification, and an Interim Life Safety Measures Certification from the VA Medical Center. Also, project schedule and construction phases must be approved by VA Chief Engineering. Contractor shall provide all necessary environmental documents and related EQB approved permits for construction.
3. Contractor shall completely prepare site, prior to the installation of the equipment, and furnish all labor, equipment and materials necessary to perform work for this specific project as required by this statement of work and the project specifications and drawings.
4. All projects associated construction and temporary work shall conform to the latest VA specifications, VA Standards, energy conservation methods, EPA, OSHA, ADA, NFPA, NEC, ASHRAE, LIFE SAFETY CODE, IBC, local, Federal and industry requirements and regulations.
5. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire job.
6. The Contractor shall comply with all applicable federal, state and local requirements for protecting the safety of the contractor’s employees, building occupants and the environment. In particular, all applicable standards of the Occupational Safety and Health Administration (OSHA) shall be followed when working in accordance with this project. No process or materials shall be employed in such a manner that they will introduce additional hazards into occupied space.
7. Contractor shall have comprehensive knowledge, experience, expertise, equipment and personnel to complete this work.
8. Contractor shall keep the VA Project Manager informed at all times of the status and progress of the project.
9. Detailed Schedule and Narrative: The Contractor shall provide a detailed phasing schedule and written narrative, indicating specific dates for each step of the construction process in concurrence with the progress schedule.
10. Contract Progress Schedule: The progress schedule will be provided in a time-scaled bar graph format for each project phase. The horizontal axis will be scaled for a time beginning with the Notice to Proceed and concluding with contract completion. The vertical axis will show the milestones and a detailed breakdown of the construction tasks. All schedule items will show a start date and a completion date.
11. Breakdown the construction period in at least eight construction tasks as required, (e.g.: site preparation, demolition, equipment procurement, equipment/materials delivery, equipment installation, architectural finishes, tests, and final inspection, etc.)
12. The Contractor shall develop a well-organized, practicable and complete written narrative construction phasing for the proposed project in order that the normal hospital operations will not be interrupted except by previous and timely coordination with VA staff through the Project Manager.
13. The Contractor shall specify how much allowance has been made for adverse weather in the schedule.
14. The Contractor shall specify the days of the week and the hours of construction operations during each phase of the work.
15. The Contractor shall prepare written minutes of each meeting with the Government concerning contractual, design and construction matters. Copies of the minutes shall be furnished to the Contracting Officer and within seven calendar days of the meetings. The Contractor shall prepare written records of phone conversations addressing major project issues and furnish a copy to the Contracting Officer within five calendar days of contract.
16. The Contractor shall develop a complete set of as-built drawings at the end of the construction work and submit it for VA review and approval.
17. Any related supporting system, apparatus, material or work not mentioned, or any incidental accessories necessary to make the work complete in all respects and ready for operation even if not particularly specified, shall be furnished, delivered and installed by the Contractor without additional cost to the Government.
18. Construction General Sections' applicable requirements: the Contractor shall comply with the applicable construction project requirements (e.g. submission of final as-built drawings, shop drawings, tests, safety requirements, new material and equipment provision and installation requirements, Buy American Act, payment and performance bonds requirements; insurance requirements; progress payments and schedules, work inspection and supervision, daily logs requirements, material and workmanship, guaranty, cleaning up, accident prevention, and other requirements) included in the specifications.
19. Pedestrian and Vehicular Maintenance of Traffic: The construction of the proposed project shall allow for full operation of the existing hospital at all times and maintaining the operations of all existing utility services and fire exits. In addition, it shall maintain free and unobstructed access to facility emergency vehicles and for fire, police, and other emergency response forces in accordance with NFPA 241. The phasing plan presented on the contract drawings indicate, primarily throughout written and graphical instructions, the general sequencing and staging for each phase of the site and project development construction. Contractor is to submit a phasing plan for VA final approval. Minimum amount of phases shall be five. The Contractor shall provide an equivalent continuous secured perimeter while work is performed to prevent intrusion to the federal premises. Contractor shall also provide a security guard at all times consistent with VACHS security regulations and shall coordinate logistics with VACHS Police Service through project’s COR. Facility security is currently provided under a private contractor.
20. Prior to the initial Pre-Construction Meeting, Contractor shall submit a list key personnel (Project Manager, on-the-job Superintendent, Quality Control Manager, etc.) to be involved in this project and supply brief statement of qualifications/biographical data including name of individual, company position, years with the company, work and educational background, experience applicable to this Project, tasks to be assigned to that individual on this Project, percentage of workweek to be committed to this Project, and authority of that individual to act on behalf of the Contractor. All key personnel shall submit evidence of their OSHA 30 hour construction safety training. VA expects to have a Project Manager, Quality Control Manager, and Superintendent on-site fully devoted for this project. The Project Manager shall be committed a minimum of 30% of work per week on this project and be present on site the same percentage. Both, the Quality Control Manager and Superintendent, shall be committed a minimum of 100% of work per week on this project and be present on site the same percentage.
21. No later than 10 calendar days after receipt of award and prior to commencing construction work, Contractor shall submit a Quality Control Plan proposed to implement the requirements for inspection of construction. Design and construction will be permitted to begin only after the VA COR acceptance of the CQC Plan.
Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record, consultants, architect/engineers (AE), fabricators, suppliers, and purchasing agents:
a. A description of the quality control organization, including a chart showing lines of authority and acknowledgment that the CQC staff will implement all aspects of the work specified.
b. The name, qualifications (in resume format), duties, responsibilities, and authorities of each person assigned a CQC function.
c. Procedures for scheduling, reviewing, certifying, and managing submittals, including those of subcontractors, designers of record, consultants, architect- engineers (A/E), offsite fabricators, and suppliers.
d. Control, verification, and acceptance testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test.
e. Procedures for tracking preparatory, initial, and follow-up control phases and control, verification, and acceptance tests including documentation.
f. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
g. Reporting procedures, including proposed reporting formats.
h. A list of the definable features of design and construction work. A definable feature of work is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment. Although each section of the specifications may generally be considered as a definable feature of work, there are frequently more than one definable feature under a particular section.
22. All vendor/contract personnel must report to the Police Service and identify themselves upon entering the VACHS facility. They shall all abide by Police Service rules and personal identification verification (PIV) regulations and to carry the identification card throughout the entire period while providing the service.
23. This acquisition will not require services that involve connection of one or more contractor-owned IT devices such as a laptop computer or remote connection from a contractor system to a VA internal trusted, therefore the C&A requirements do not apply, and a Security Accreditation Package is not required.
Part III – Post Award Requirements A. Construction Period Submittals
1. The contractor shall distribute one (1) electronic set of the submittal in pdf format attention to VA CO with copy to VA PM/COR via e-mail. All materials and equipment submittals must be submitted and approved by record A/E, VA PM/COR and CO prior to start of construction. All submittals shall be as per the specifications.
2. Other submittals – Contractor shall submit test results, certificates, manufacturer’s instructions, manufacturer’s field reports, etc. as required by the VA RFP specifications to PM/COR and CO in pdf format via e-mail correspondence.
3. Project record drawings – Contractor shall maintain a set of construction documents (field as-built drawings) to record actual construction changes during the entire construction process as required by the RFP specifications. The project record drawings will be available for review by the VA PM/COR at all times.
4. Shop drawings and submittals – A/E shall verify Contractor’s shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review materials for conformity with the RFP documents and specifications. The A/E shall recommend approval, disapproval or other suitable disposition to the VA PM/COR The VA PM/COR and CO will have final approval authority. The A/E shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the A/E shall request the Contractor to submit related components of a system before acting on a single component. The A/E may be required to hold joint reviews with the VA technical staff on complicated system submittals.
Project Close-Out
5. The contractor shall comply with the requirements in the “General Requirements”, Section 010000, for submission of final RFP as built drawings, manuals and other documents as noted. Required as built drawings and specifications shall be submitted in the same format required for the construction documents.
- - - End SOW- - -