This document is a Request for Information (RFI) issued by the Port Authority of New York and New Jersey for the RFQS – 6000001282 Master Agreements for General Construction Services on a Work Order Basis for the AirTrain Newark Replacement Project. The document contains four specific questions and answers related to the request for qualifications, dated January 27, 2023. The RFI addresses eligibility, contractual clarifications, safety record submissions, and the definition of affiliates for potential bidders.
The RFI clarifies that local non-MWBE (Minority and Women-owned Business Enterprise) contractors are eligible to apply. Bidders are instructed to submit 3 years of OSHA 300 logs as part of their safety record documentation, with the understanding that the Authority may request additional information after initial review. An affiliate is defined as a subsidiary group or a person connected to an organization, which is relevant for safety record and contractor past performance submissions. Potential contractors are directed to refer to Addendum #1 for further details on specific qualification statement requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQS – 6000001282 MASTER AGREEMENTS FOR GENERAL CONSTRUCTION SERVICES ON A WORK ORDER BASIS –
AIRTRAIN NEWARK REPLACEMENT PROJECT – REQUEST FOR INFORMATION
Date: January 27, 2023
RFI # RFQS
Document
Question/Request for Clarification Answer
001 1282 Are local non MWBE eligible to apply? Yes.
002 1282 As per the Contractor's Qualification Statement Form, latter part of page 1, the following is requested: “Indicate which part of the work indicated in Paragraphs II and II.A of the attached Request for Qualification Statements (“RFQS”) you plan on performing with your own forces and what work you plan on sub-contracting to another firm.”
Paragraph II does not identify any work we should indicate in the above section and there is no section identified as
II.A. Please clarify which work we are to specify in this section.
Please see Addendum #1.
As part of the submission for the Safety Record, we are required to provide the firm’s safety record of for the past three (3) years as well as for affiliates. Please clarify what information/documentation is to be included to satisfy this requirement.
Aside from EMR, submit 3 years of your firm’s OSHA 300 logs. The Authority may request additional information post submission review.
RFI # RFQS
Document
Question/Request for Clarification Answer
004 1282 Can you please provide the definition of affiliate as the
Safety Record and Contractor Past Performance are required for these as part of the submission?
Affiliate is a subsidiary group, or a person connected to an organization.