The document is a design phase milestone schedule for the SCCPSS (Savannah-Chatham County Public School System) 2219 Gamble Road Project, spanning from February to December 2025. The project is divided into five distinct phases: Phase IA (Master Plan), Phase IB (Restoration & Office Building), Phase II (Gas Station), Phase III (Site Development/Parking Lot), Phase IV (Maintenance Building Renovation), and Phase V (Storage Building). The schedule outlines detailed design progression milestones, including Schematic Design (SD), Design Development (DD), and Construction Documents (CD) stages for each phase, with specific tasks such as progress set submissions, owner meetings, architectural backgrounds, consultant drawings, BIM clash detection, and final document sets.
The timeline indicates a comprehensive, multi-phase development project with a structured approach to design and documentation. Each phase includes multiple checkpoints and deliverables, with activities tracked across weeks in 2025. The project appears to involve significant design coordination, with repeated cycles of progress sets, owner feedback, consultant document preparation, and technical reviews. The schedule suggests a methodical approach to project development, with careful tracking of design milestones and interdependent tasks across different project components.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
MP Progress Set Sent to Owner 5
Meeting with Owner for Feedback 11
Receive Shamrock+ Model 18
Progress Set 1 (50%) 31
Progress Set 2 (75%) 11
100% PD Set 25
Notice to Procede Issued 21
100% Survey + Geotech 6
Kick-off Design 2
SD Progress Set Sent to Owner 13
Meeting with Owner for Feedback 13
Architecture Backgrounds 23
Final Consultants Set 30
100% SD (30% Set) 31
Arch. Backgrounds 31
Consultants Prog. Dwgs. 7
BIM Clash Detection 7
Architect's Comments 12
Final Consultants Set 14
100% DD (60% Set) 15
Arch. Backgrounds 15 19
Consultants Prog. Dwgs. 27
BIM Clash Detection 27
Architect's Comments 1
Final Consultants Set 11
100% Final CD Set 12
Kick-off Design 25
SD Progress Set Sent to Owner 28
Meeting with Owner for Feedback 29
Architecture Backgrounds 3
Consultants Prog. Dwgs. / Info 11
Architect's Comments 18
Final Consultants Set 22
100% SD (30% Set) 23
Arch. Backgrounds 24
Consultants Prog. Dwgs. 29
BIM Clash Detection 29
Architect's Comments 1
Final Consultants Set 8
100% DD (60% Set) 9
Arch. Backgrounds 13
Consultants Prog. Dwgs. 22
BIM Clash Detection 22
Architect's Comments 30
Final Consultants Set 10
100% Final CD Set 11
Kick-off Design 16
SD Progress Set Sent to Owner 28
Meeting with Owner for Feedback 3
Architecture Backgrounds 21
Final Consultants Set 28
100% SD (30% Set) 29
Arch. Backgrounds 29
Consultants Prog. Dwgs. 9
BIM Clash Detection 10
Architect's Comments 17
Final Consultants Set 25
100% DD (60% Set) 26
Arch. Backgrounds 30
Consultants Prog. Dwgs. 1
BIM Clash Detection 10
Architect's Comments 16
Final Consultants Set 23
100% Final CD Set 24
Kick-off Design 22
SD Progress Set Sent to Owner 1
Meeting with Owner for Feedback 3
Architecture Backgrounds 6
Consultants Prog. Dwgs. / Info 17
Architect's Comments 21
Final Consultants Set 23
100% SD (30% Set) 24
Arch. Backgrounds 24
Consultants Prog. Dwgs. 30
BIM Clash Detection 31
Architect's Comments 4
Final Consultants Set 20
100% DD (60% Set) 21
Arch. Backgrounds 21
Consultants Prog. Dwgs. 4
BIM Clash Detection 5
Architect's Comments 9
Final Consultants Set 18
100% Final CD Set 19
Kick-off Design 22
SD Progress Set Sent to Owner 1
Meeting with Owner for Feedback 3
Architecture Backgrounds 6
Consultants Prog. Dwgs. / Info 17
Architect's Comments 21
Final Consultants Set 23
100% SD (30% Set) 24
Arch. Backgrounds 24
Consultants Prog. Dwgs. 30
BIM Clash Detection 31
Architect's Comments 4
Final Consultants Set 20
100% DD (60% Set) 21
Arch. Backgrounds 21
Consultants Prog. Dwgs. 4
BIM Clash Detection 5
Architect's Comments 9
Final Consultants Set 18
100% Final CD Set 19
Phase IA
November December
GMC
Phase I
Master
Plan
October
NTP
Kick-off Meeting
Master Plan
Survey +
Geotech
April May June July August
Phase IV
Maint.
Building
Reno
Phase V
Storage
Building
SD
DD
CD
DD
CD
SD
Phase III
Site Dev. /
Parking
Lot
SD
Phase IB
Rest. &
Office
Building
DD
CD
SD
DD
CD
CD
SD
DD
Phase II
Gas
Station
SeptemberFebruary March
SCCPSS 2219 Gamble Road Project
Design
Phase Milestones