5-FDOT Liquidated Damages FY25.pdf
PDF 158 KB Posted
- Solicitation number
- ITB No. 2026-001
- Issued by
- Palm Beach County, Florida
About this file
This document is an excerpt from the Florida Department of Transportation (FDOT) Fiscal Year 2025-26 contract specifications, specifically addressing liquidated damages and contractor responsibilities. The section details the procedures and financial penalties associated with a contractor's failure to complete contract work within the specified Contract Time, outlining a structured schedule of daily charges based on the original contract amount ranging from $904 per calendar day for contracts under $299,999 to $10,224 plus an additional $0.00005 per dollar over $40 million for larger contracts.
The document establishes the Department's rights in cases of contractor default, including charging all costs incurred due to the default, applying liquidated damages, and potentially completing the work themselves. The specifications also outline conditions for releasing the contractor's responsibility, which occurs when all work is completed and accepted by the Department. Additionally, the document provides for the recovery of damages suffered by third parties when the contractor fails to complete work within the Contract Time, unless the delay was caused by the Department's actions or omissions.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
manner. The Department will charge all costs that the Department incurs because of the Contractor’s default, including the costs of completing the work under the Contract, against the Contractor. If the Department incurs such costs in an amount that exceeds the sum that would have been payable under the Contract, then the Contractor and the surety shall be liable and shall pay the Department the amount of the excess.
If, after the ten day notice period and prior to any action by the Department to otherwise complete the work under the Contract, the Contractor establishes their intent to prosecute the work in accordance with the Department’s requirements, then the Department may allow the Contractor to resume the work, in which case the Department will deduct from any monies due or that may become due under the Contract, any costs to the Department incurred by the delay, or from any reason attributable to the delay.
8-10 Liquidated Damages for Failure to Complete the Work.
8-10.1 Highway Code Requirements Pertaining to Liquidated Damages:
Section 337.18, paragraph (2) of the Florida Statutes, requires that the Department adopt regulations for the determination of default and provides that the Contractor pay liquidated damages to the Department for any failure of the Contractor to complete the Contract work within the Contract Time. These Code requirements govern, and are herewith made a part of the Contract.
8-10.2 Amount of Liquidated Damages: Applicable liquidated damages are the amounts established in the following schedule:
Original Contract Amount Daily Charge Per Calendar Day
$299,999 and under ........................................................$904 $300,000 but less than $2,000,000..............................$1,685 $2,000,000 but less than $5,000,000...........................$2,667 $5,000,000 but less than $10,000,000.........................$3,813 $10,000,000 but less than $20,000,000.......................$5,021 $20,000,000 but less than $40,000,000.......................$7,442 $40,000,000 and over ............... $10,224 plus 0.00005 of any amount over $40 million (Round to nearest whole dollar)
The Engineer may approve adjustments to the liquidated damages amounts in accordance with the Construction Project Administration Manual (CPAM) provided all contract work is complete.
8-10.3 Determination of Number of Days of Default: For all contracts, regardless of whether the Contract Time is stipulated in calendar days or working days, the Engineer will count default days in calendar days.
8-10.4 Conditions under which Liquidated Damages are Imposed: If the Contractor or, in case of their default, the surety fails to complete the work within the time stipulated in the Contract, or within such extra time that the Department may have granted then the Contractor or, in case of their default, the surety shall pay to the Department, not as a penalty, but as liquidated damages, the amount so due as determined by the Code requirements, as provided in 8-10.2.
8-10.5 Right of Collection: The Department has the right to apply, as payment on such liquidated damages, any money the Department owes the Contractor.
100 FY 2025-26Return to Table of Contents
8-10.6 Allowing Contractor to Finish Work: The Department does not waive its right to liquidated damages due under the Contract by allowing the Contractor to continue and to finish the work, or any part of it, after the expiration of the Contract Time.
8-10.7 Completion of Work by Department: In the case of a default of the Contract and the completion of the work by the Department, the Contractor and their surety are liable for the liquidated damages under the Contract, but the Department will not charge liquidated damages for any delay in the final completion of the Department’s performance of the work due to any unreasonable action or delay on the part of the Department.
8-11 Release of Contractor’s Responsibility.
The Department considers the Contract complete when the Contractor has completed all work and the Department has accepted the work. The Department will then release the Contractor from further obligation except as set forth in their bond, and except as provided in 5- 13.
8-12 Recovery of Damages Suffered by Third Parties.
In addition to the damages provided for in 8-10.2 and pursuant to Section 337.18 of the Florida Statutes, when the Contractor fails to complete the work within the Contract Time the Department may recover from the Contractor amounts that the Department pays for damages suffered by third parties unless the failure to timely complete the work was caused by the Department’s act or omission.
101 FY 2025-26Return to Table of Contents
File details come from the government source that posted it. Updated .