Memphord Estates Stormwater Basins Rehabilitation - Bidding Documents Summary

This is a complete set of bidding and contract documents issued by Monaghan Township, York County, Pennsylvania, for the rehabilitation of two existing stormwater basins. The scope of work includes clearing brush and felling trees along the fence line, repairing existing fencing, replacing outlet structures, installing inlet snouts with bioskirts (36-inch and 15-inch), installing a gravel access road, and site restoration including topsoil and seeding with compost filter sock placement. Bids were due electronically via PennBid by 1:00 p.m. on February 4, 2026, with public opening and reading immediately thereafter at the Monaghan Township Municipal Building, 202 South York Road, Dillsburg, Pennsylvania 17019. A pre-bid conference was held on June 18, 2024, at the same location. The contract includes ten line items with lump sum and unit price components, including tree and vegetation clearing, two outlet structures, gravel access road, three stormwater inlet structures, 60 linear feet of SLCPP, inlet snouts, 20 square yards of topsoil, 30 pounds of seeding, and 102 linear feet of compost filter sock. Work must be substantially completed within 150 calendar days and fully completed within 180 calendar days from the Notice to Proceed.

Bid security equal to 10 percent of the maximum bid price is required in the form of a certified check, bank money order, or bid bond. The contract price is based on a lump sum base bid with potential alternates to be considered only after award. All work is tax-exempt as the project is owned by Monaghan Township. Contractors must comply with prevailing wage requirements under Davis-Bacon wage determinations for Pennsylvania's heavy and highway construction projects, with rates effective January 2, 2026. Performance and payment bonds are required, each equal to the full contract price. The owner will maintain property insurance on the work at full replacement cost. Liquidated damages of $200 per day apply for delays beyond the substantial completion date, and interest accrues at 0 percent per annum on unpaid amounts. Retainage of 10 percent applies to progress payments until 50 percent completion, after which no additional retainage is withheld if work progress remains satisfactory. The contractor must provide comprehensive general liability insurance with limits of $1,000,000 per occurrence and $2,000,000 excess umbrella coverage, with Monaghan Township and KPI Technology listed as additional insureds.

View the file

Other files

File Type Posted
2-Bid Submission Package.pdf PDF
3-Div 02.pdf PDF
4-Div 01.pdf PDF
1-DRAWINGS Memphord Estates Basins.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00100-1

DIVISION 00 – BIDDING AND CONTRACT REQUIREMENTS

SECTION 00100 – INSTRUCTIONS TO BIDDERS

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General

Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued and where the bidding procedures are to be administered.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents in the number and for the deposit sum, if any, stated in the advertisement or invitation to bid may be obtained from the Issuing Office.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, each Bidder shall submit on the form furnished for that purpose, a statement and written evidence such as financial data, previous experience, present commitments, and such other data as may be called for below.

3.02 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED DATA, AND

SITE

4.01 Subsurface and Physical Conditions

A. The Supplementary Conditions identify:

1. Those reports known to Owner of explorations and tests of subsurface conditions at or contiguous to the Site.

00100-2

B. Copies of reports and drawings referenced in Paragraph 4.01.A will be made available by Owner to any Bidder on request. Those reports and drawings are not part of the Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to rely as provided in Paragraph 4.02 of the General Conditions has been identified and established in Paragraph 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

4.02 Underground Facilities

A. Information and data shown or indicated in the Bidding Documents with respect to existing Underground Facilities at or contiguous to the Site is based upon information and data furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

4.03 Provisions concerning responsibilities for the adequacy of data furnished to prospective

Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph

4.06 of the General Conditions.

4.04 On request, Owner will provide Bidder access to the Site during regular business hours to conduct such examinations, investigations, explorations, tests, and studies as Bidder deems necessary for submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies. Bidder shall comply with all applicable Laws and Regulations relative to excavation and utility locates.

4.05 Reference is made to Article 7 of the Supplementary Conditions for the identification of the general nature of other work that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) that relates to the Work contemplated by these Bidding Documents. On request, Owner will provide to each Bidder for examination access to or copies of contract documents (other than portions thereof related to price) for such other work.

4.06 Paragraph 6.13.C of the General Conditions indicates that if an Owner safety program exists, it will be noted in the Supplementary Conditions.

4.07 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and the other related data identified in the Bidding Documents;

00100-3

B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and

Site conditions that may affect cost, progress, and performance of the Work;

C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and

Regulations that may affect cost, progress, and performance of the Work;

D. carefully study all reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in Paragraph 4.02 of the Supplementary Conditions as containing reliable "technical data,"

E. consider the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work;

(2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying any specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs;

F. agree at the time of submitting its Bid that no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

G. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

H. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder; and

I. determine that the bidding Document are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work. The submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article 4, that without exception the Bid is premised upon performing and furnishing the Work required by the Bidding Documents and applying any specific means, methods, techniques, sequences, and procedures of construction that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has given Engineer written notice of all conflicts, errors, ambiguities, and discrepancies that Bidder has discovered in the Bidding Documents and the written resolutions thereof by Engineer are acceptable to Bidder, and that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work.

00100-4

ARTICLE 5 – PRE-BID CONFERENCE

5.01 A pre-Bid conference will be held at 10:00 a.m. local time on June 18, 2024 at 202

South York Road, Dillsburg, Pa 17019. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference. Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 6 – SITE AND OTHER AREAS

6.01 The Site is identified in the Bidding Documents. Easements for permanent structures or permanent changes in existing facilities are to be obtained and paid for by Owner unless otherwise provided in the Bidding Documents. All additional lands and access thereto required for temporary construction facilities, construction equipment, or storage of materials and equipment to be incorporated in the Work are to be obtained and paid for by Contractor.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer in writing. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda mailed or delivered to all parties recorded by Engineer as having received the Bidding Documents. Questions received less than ten days prior to the date for opening of Bids may not be answered.

Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed advisable by Owner or Engineer.

ARTICLE 8 – BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of

10 percent of Bidder’s maximum Bid price and in the form of a certified check, bank money order, or a Bid bond (on the form attached) issued by a surety meeting the requirements of Paragraphs 5.01 and 5.02 of the General Conditions.

00100-5

8.02 The Bid security of the Successful Bidder will be retained until such Bidder has executed the Contract Documents, furnished the required contract security and met the other conditions of the Notice of Award, whereupon the Bid security will be returned. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults. The Bid security of other Bidders whom Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of seven days after the Effective Date of the Agreement or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be returned.

8.03 Bid security of other Bidders whom Owner believes do not have a reasonable chance of receiving the award will be returned within seven days after the Bid opening.

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which Milestones are to be achieved and the Work is to be substantially completed and ready for final payment are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract, if awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration of possible substitute or “or-equal” items. Whenever it is specified or described in the Bidding Documents that a substitute or “or-equal” item of material or equipment may be furnished or used by Contractor if acceptable to Engineer, application for such acceptance will not be considered by Engineer until after the award of the contract.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS AND OTHERS

12.01 If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers, individuals, or entities to be submitted to Owner in advance of a specified date prior to the Effective Date of the Agreement, the apparent Successful Bidder, and any other Bidder so requested, shall within five days after Bid opening, submit to Owner a list of all such Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work for which such identification is required. Such list shall be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, individual, or entity if requested by Owner. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit a substitute, without an increase in the Bid.

00100-6

12.02 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors, Suppliers, individuals, or entities. Declining to make requested substitutions will not constitute grounds for forfeiture of the Bid security of any Bidder.

Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to revocation of such acceptance after the Effective Date of the Agreement as provided in Paragraph 6.06 of the General Conditions.

12.03 Contractor shall not be required to employ any Subcontractor, Supplier, individual, or entity against whom Contractor has reasonable objection.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents. Additional copies may be obtained from the Engineer.

13.02 All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each [section, Bid item, alternative, adjustment unit price item, and unit price item] listed therein. In the case of optional alternatives the words “No Bid,” “No Change,” or “Not Applicable” may be entered.

13.03 A Bid by a corporation shall be executed in the corporate name by the president or a vice-president or other corporate officer accompanied by evidence of authority to sign.

The corporate seal shall be affixed and attested by the secretary or an assistant secretary. The corporate address and state of incorporation shall be shown.

13.04 A Bid by a partnership shall be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership shall be shown.

13.05 A Bid by a limited liability company shall be executed in the name of the firm by a member and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm shall be shown.

13.06 A Bid by an individual shall show the Bidder’s name and official address.

13.07 A Bid by a joint venture shall be executed by each joint venturer in the manner indicated on the Bid Form. The official address of the joint venture shall be shown.

13.08 All names shall be printed in ink below the signatures.

13.09 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

00100-7

13.10 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.11 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the state where the Project is located, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID; COMPARISON OF BIDS

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis for the base Bid and may include a separate price for each alternate described in the Bidding Documents as provided for in the Bid Proposal Form. The price for each alternate will be the amount added to or deleted from the base Bid if Owner were to select any of the alternates, which will only be considered after award of the contract. In the comparison of Bids, only the base Bid items will be considered for award of the contract.

ARTICLE 15 – SUBMITTAL OF BID

15.01 With each copy of the Bidding Documents, a Bidder is furnished one separate unbound copy of the Bid Form, and the Bid Bond Form. The unbound copy of the Bid Form is to be completed and submitted with the Bid security and the following documents:

A. Statement of Bidder Qualifications B. Non-Collusion Affidavit of Prime Bidder C. Certification of Non-Discrimination D. Safety Guidelines and Requirements

15.02 A Bid shall be submitted no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title, the designated contract portion of the Project for which the Bid is submitted, the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid shall be addressed to:

Monaghan Township

202 South York Road

Dillsburg, PA 17019

00100-8

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be modified or withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids.

16.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the Advertisement or Invitation to

Bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner further reserves the right to reject the Bid of any Bidder whom it finds, after reasonable inquiry and evaluation, to not be responsible. Owner may also reject the Bid of any Bidder if Owner believes that it would not be in the best interest of the Project to make an award to that Bidder. Owner also reserves the right to waive all informalities not involving price, time, or changes in the Work and to negotiate contract terms with the Successful Bidder.

19.02 More than one Bid for the same Work from an individual or entity under the same or different names will not be considered. Reasonable grounds for believing that any Bidder has an interest in more than one Bid for the Work may be cause for disqualification of that Bidder and the rejection of all Bids in which that Bidder has an interest.

19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices and other data, as may be requested in the Bid Form or prior to the Notice of Award.

00100-9

19.04 In evaluating Bidders, Owner will consider the qualifications of Bidders and may consider the qualifications and experience of Subcontractors, Suppliers, and other individuals or entities proposed for those portions of the Work for which the identity of Subcontractors, Suppliers, and other individuals or entities must be submitted as provided in the Supplementary Conditions.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders, proposed Subcontractors, Suppliers, individuals, or entities proposed for those portions of the Work in accordance with the Contract Documents.

19.06 If the Contract is to be awarded, Owner will award the Contract to the Bidder whose Bid is in the best interests of the Project and will be based on the base Bid price.

ARTICLE 20 – CONTRACT SECURITY AND INSURANCE

20.01 Article 5 of the General Conditions, as may be modified by the Supplementary

Conditions, sets forth Owner’s requirements as to performance and payment bonds and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it shall be accompanied by such bonds.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the required number of unsigned counterparts of the Agreement along with the other Contract Documents which are identified in the Agreement as attached thereto. Within 15 days thereafter, Successful Bidder shall sign and deliver the required number of counterparts of the Agreement and attached documents to Owner. Within ten days thereafter, Owner shall deliver one fully signed counterpart to Successful Bidder with a complete set of the Drawings with appropriate identification.

ARTICLE 22 – SALES AND USE TAXES

22.01 Owner is exempt from Pennsylvania state sales and use taxes on materials and equipment to be incorporated in the Work. Said taxes shall not be included in the Bid.

Refer to Paragraph 6.10 of the Supplementary Conditions for additional information.

ARTICLE 23 – PREVAILING WAGES AND EMPLOYMENT VERIFICATION

23.01 Attention of the Bidders is particularly called to the requirements concerning the payment of not less than prevailing wage and salary rates specified in the Supplementary Conditions and the conditions of employment with respect to certain categories and classifications of employees.

23.02 Successful bidder, along with all subcontractors to be utilized, will be required to provide

DGS verification form to the OWNER in accordance with The Public Works Employment Verification Act (Act 127 of 2012) as a condition prior to award of contract.

00300-1

ADVERTISEMENT FOR BIDS

OWNER: Monaghan Township Separate sealed bids for:

“Memphord Estates Stormwater Basins Rehabilitation” will be received electronically via the PennBid Program by Monaghan Township until 1:00 P.M., prevailing time, February 4, 2026. Bids will then be opened and publicly read aloud immediately thereafter at the

Monaghan Township Municipal Building 202 S. York Road Dillsburg, PA 17019

All project documents and details are available at no cost on PennBid (www.pennbid.net).

No bid will be considered unless it is accompanied by a certified check or Bid Bond in an amount equal to at least ten percent (10%) of the total bid. The Bid Security shall be made payable to Monaghan Township.

The Owner reserves the right, at its option, to reject any or all bids, to waive any informalities, irregularities, defects, errors or omissions in any or all Bid Proposals, as the Owner may deem to be in its best interest.

BY ORDER OF MONAGHAN TOWNSHIP

YORK COUNTY, PENNSYLVANIA

http://www.pennbid.net/

00330-1

SECTION 00330 – BID PROPOSAL

ARTICLE 1 – BID RECIPIENT

This Bid is submitted to:

Monaghan Township 202 South York Road Dillsburg, PA 17019

1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2 – BIDDER’S ACKNOWLEDGEMENTS

2.01 Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

ARTICLE 3 – BIDDER’S REPRESENTATIONS

3.01 In submitting this Bid, Bidder represents that:

A. Bidder has examined and carefully studied the Bidding Documents, other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged:

Addendum No. Addendum Date

B. Bidder has visited the Site and become familiar with and is satisfied as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

C. Bidder is familiar with and is satisfied as to all Laws and Regulations that may affect cost, progress, and performance of the Work.

00330-2

D. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities) that have been identified in SC-4.02 as containing reliable "technical data," and (2) reports and drawings of Hazardous Environmental Conditions, if any, at the Site that have been identified in SC-4.06 as containing reliable "technical data."

E. Bidder has considered the information known to Bidder; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents; and (3) Bidder’s safety precautions and programs.

F. Based on the information and observations referred to in Paragraph 3.01.E above, Bidder does not consider that further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents.

G. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

H. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder.

I. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted.

ARTICLE 4 – BIDDER’S CERTIFICATION

4.01 Bidder certifies that:

A. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation;

B. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid;

C. Bidder has not solicited or induced any individual or entity to refrain from bidding; and

00330-3

D. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 4.01.D:

1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process;

2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition;

3. “collusive practice” means a scheme or arrangement between two or more

Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels; and

4. “coercive practice” means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

E. Bidder is equal opportunity employer and does not discriminate based on age, race, nationality, religion, or disability. Bidder also ensures that any subcontractors shall also be equal opportunity employers.

ARTICLE 5 – BASIS OF BID

5.01 Unit Prices are to be computed in accordance with Paragraph 11.03.B of the General

Conditions.

5.02 Bidder acknowledges that estimated quantities are not guaranteed, and are solely for the purpose of comparison of Bids, and final payment for all unit price Bid items will be based on actual quantities, determined as provided in the Contract Documents.

5.03 Bidder will complete the Work in accordance with the Contract Documents for the following unit price(s) and total cost:

00330-4

BASE BID: MEMPHORD ESTATES STORMWATER BASINS REHABILITATION

ITEM

NO.

DESCRIPTION

UNIT

ESTIMATED

QUANTITY

UNIT

PRICE

TOTAL

COST

1 Tree and Vegetation Clearing LS 1

2 Outlet Structures EA 2

3 Gravel Access Road LS 1

4 Stormwater Inlet Structures EA 3

5 SLCPP LF 60

6 SNOUT w/ Bioskirt 36” EA 1

7 SNOUT w/ Bioskirt 15” EA 2

8 Topsoil SY 20

9 Seeding LB 30

10 Compost Filter Sock LF 102

TOTAL CONSTRUCTION BASE BID:

(IN WORDS)

(IN FIGURES)

ARTICLE 6 – TIME OF COMPLETION

6.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 14.07 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

6.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 7 – ATTACHMENTS TO THIS BID

7.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security in the form of certified check, money order or Bid bond on the form attached;

00330-5

B. Statement of Bidder’s Qualifications

C. Non-Collusion Affidavit of Prime Bidder

D. Certification of Non-Discrimination

E. Safety Guidelines and Requirements (O.S.H.A.)

ARTICLE 8 – DEFINED TERMS

8.01 The terms used in this Bid with initial capital letters have the meanings stated in the

Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

00330-6

ARTICLE 9 – BID SUBMITTAL

9.01 This Bid is submitted by:

If Bidder is:

An Individual

Name (typed or printed):

By:

(Individual’s signature)

Doing business as:

A Partnership

Partnership Name:

By:

(Signature of general partner -- attach evidence of authority to sign)

Name (typed or printed):

A Corporation

Corporation Name: (SEAL)

State of Incorporation:

Type (General Business, Professional, Service, Limited Liability):_______

By:

(Signature -- attach evidence of authority to sign)

Name (typed or printed):

Title:

(CORPORATE SEAL)

Attest

Bidder's Business Address

Phone No. _______________________________ Fax No.

E-mail ___________________________________

SUBMITTED on , 20____.

00410-1

SECTION 00410 – BID BOND

Any singular reference to Bidder, Surety, Owner or other party shall be considered plural where applicable.

BIDDER (Name and Address):

SURETY (Name and Address of Principal Place of Business):

OWNER (Name and Address):

202 South York Road Dillsburg, PA 17019

BID

Bid Due Date: July 2, 2024 Description:

Fisher Run Road Culvert Replacement

BOND

Bond Number:

Date (Not earlier than Bid due date):

Penal sum

(Words) (Figures)

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth below, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

BIDDER SURETY

(Seal) (Seal)

Bidder’s Name and Corporate Seal Surety’s Name and Corporate Seal

By: By:

Signature Signature (Attach Power of Attorney)

Print Name Print Name

Title Title

Attest: Attest:

Signature Signature

00410-2

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond. Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond shall be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder shall occur upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation shall be null and void if:

3.1 Owner accepts Bidder’s Bid and Bidder delivers within the time required by the

Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2 All Bids are rejected by Owner, or

3.3 Owner fails to issue a Notice of Award to Bidder within the time specified in the

Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions shall not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.

6. No suit or action shall be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety and in no case later than one year after Bid due date.

7. Any suit or action under this Bond shall be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder shall be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Registered or Certified Mail, return receipt requested, postage pre-paid, and shall be deemed to be effective upon receipt by the party concerned.

00410-3

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond shall be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute shall govern and the remainder of this Bond that is not in conflict therewith shall continue in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

00451-1

SECTION 00451 – STATEMENT OF BIDDER'S QUALIFICATIONS

All questions must be answered and the data given must be clear and comprehensive. This statement must be notarized. If necessary, questions may be answered on separate attached sheets. The bidder may submit any additional information he desires.

1. Name of bidder: ___________________________________________________________

2. Permanent main office address:

3. When organized: __________________________________________________________

4. If a corporation, where incorporated: ___________________________________________

5. How many years have you been engaged in the contracting business under your present firm or trade name? ________

6. Contracts on hand (schedule these, showing amount of each contract and the appropriate anticipated dates of completion):

7. General character of work performed by your company:

8. Have you ever failed to complete any work awarded to you? If so, where and why?

9. Have you ever defaulted on a contract? If so, where and why?

10. List the more important projects recently completed by your company, stating the approximate cost for each and the month and year completed:

11. List your major equipment available for this contract:

12. Experience in construction work similar in importance to this project:

00451-2

13. Background and experience of the principal members of your organization, including the officers:

14. Credit available: $__________________

15. Give Bank references: ______________________________________________________

16. Provide a detailed financial statement and furnish any other information that you may deem appropriate:

17. Provide a list of company references on attached sheet.

18. The undersigned hereby authorizes and requests any persons, firm, or corporation to furnish any information requested by the OWNER in verification of the recitals comprising this STATEMENT OF BIDDER'S QUALIFICATIONS.

Dated at _______________ this _______ day of ______________ 20__.

(Name of Bidder)

By: ________________________________

Title: ______________________________

STATE / COMMONWEALTH OF: __________________________

COUNTY OF: ________________________

_________________________________________________, being duly sworn deposes and says that he/she is ________________________________________ of

(Title)

(name of organization) and that the answers to the foregoing questions and all statements therein contained are true and correct.

Subscribed and sworn to before me this _____________day of __________________, 20___.

Notary Public

My Commission Expires: ______________, 20__.

00451-3

REFERENCES

1. Company Name: ________________________________________________ Company Address: ________________________________________________ Telephone No.: ________________________________________________ Contact Person: ________________________________________________

2. Company Name: ________________________________________________ Company Address: ________________________________________________ Telephone No.: ________________________________________________ Contact Person: ________________________________________________

3. Company Name: ________________________________________________ Company Address: ________________________________________________ Telephone No.: ________________________________________________ Contact Person: ________________________________________________

END OF SECTION

00452-1

SECTION 00452 – NON-COLLUSION AFFIDAVIT OF PRIME BIDDER

State/Commonwealth of ______________________County of ___________________

_______________________________________________, being first duly sworn, deposes and says that:

(1) He is ___________________________________________________________________ (Owner, partner, officer, representative or agent) of ________________________________________________, the Bidder that has submitted the attached Bid;

(2) He is fully informed respecting the preparation and contents of the attached Bid and of all pertinent circumstances respecting such Bid;

(3) Such Bid is genuine and is not a collusive or sham Bid;

(4) Neither the said Bidder nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted or to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or to fix any overhead, profit or cost element for the Bid prices or the Bid price of any Bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the Owner or any Person interested in the proposed Contract; and

(5) The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant.

(Signed)_________________________

(Title)___________________________

Subscribed and sworn to before me this __________day of _____________, 20__.

Notary Public

My commission expires __________________________

00454-1

SECTION 00454 – CERTIFICATION OF NON-DISCRIMINATION _CFA

The Contractor shall not:

1. in any manner discriminate in the hiring of any employee(s) for the performance of the activities required under this agreement or any subgrant agreement, contract, or subcontract, by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of

2. the Pennsylvania Human Relations Act (“PHRA”) and applicable federal laws, against any citizen of this Commonwealth who is qualified and available to perform the work to which the employment relates.

3. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, against or intimidate any of its employees.

4. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, in the provision of services under this agreement or any subgrant agreement, contract, or subcontract.

5. in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of PHRA and applicable federal laws, against any subgrantee, contractor, subcontractor, or supplier who is qualified to perform the work to which this agreement relates.

6. in any manner discriminate against employees by reason of participation in or decision to refrain from participating in labor activities protected under the Public Employee Relations Act, Pennsylvania Labor Relations Act, or National Labor Relations Act, as applicable, and to the extent determined by entities charged with the Acts’ enforcement and shall comply with any provision of law establishing organizations as employees’ exclusive representatives.

Dated__________________, 20__ _________________________ (Name of Contractor)

Official Address By ____________________________

(Title)

00453-1

SECTION 00453 – CERTIFICATION OF NON-DISCRIMINATION

1. CONTRACTOR shall not discriminate against any employee, applicant for employment independent contractor, or any other person because of race, color, religious creed, ancestry, national origin, age, or sex. CONTRACTOR shall take affirmative action to ensure that applicants are employed, and that employees or agents are treated, during employment, without regard to their race, color, religious creed, ancestry, national origin, age or sex. Such affirmative action shall include, but is not limited to, the following: Employment, upgrading, demotion or transfer;

recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training. CONTRACTOR shall post in conspicuous places, available to all employees, agents, applicants for employment, and other persons a notice to be provided by the contracting agency setting forth the provisions of the non-discrimination clause.

2. CONTRACTOR shall, in advertisement or requests for employment placed by it or on its behalf, state that all qualified applicants will receive consideration for employment without regard to race, color religious creed, ancestry, national origin, age or sex.

3. CONTRACTOR shall send each labor union or worker’s representative with which it has a collective bargaining agreement or other contract or understanding, a notice advising said labor union or workers’ representative of its commitment to this non-discrimination clause. Similar notice shall be sent to every other source of recruitment regularly utilized by the CONTRACTOR.

4. It shall be no defense to a finding of non-compliance with the Contract Compliance

Regulation Commission or this non-discrimination clause that the CONTRACTOR had delegated some of its employment practices to any union, training program, or other source or recruitment which prevents it from meeting its obligations. However, if the evidence indicates that the CONTRACTOR was not on notice of the third-party discrimination or made a good faith effort to correct it, such factor shall be considered in mitigation in determining appropriate sanctions.

5. Where the practice of a union or any training program or other source of recruitment will result in the exclusion of minority group persons, so that the CONTRACTOR will be unable to meet its obligations under the Contract Compliance Regulations issued by the Pennsylvania Human Relations Commission or this non-discrimination clause, CONTRACTOR shall then employ and fill vacancies through other non-discriminatory employment procedures.

6. CONTRACTOR shall comply with the Contract Compliance Regulations of the

Pennsylvania Human Relations Commission, 16 PA Code Chapter 49 and with all state and federal laws prohibiting discrimination in hiring or employment opportunities. In the event of the Contractor’s noncompliance with the non-discrimination clause of this CONTRACT, or with any such laws, this CONTRACT may, after hearing and adjudication, be terminated or suspended, in whole or in

00453-2 part, and the CONTRACTOR may be declared temporarily ineligible for further contracts and other such sanctions may be imposed and remedies invoked as provided by the Contract Compliance Regulations.

7. CONTRACTOR shall furnish all necessary employment documents and records to, and permit access to its books, records, and accounts by the contracting agency, the Office of Administration, Bureau of Affirmative Action, and the Human Relations Commission for purposes of investigation to ascertain compliance with the provisions of the Contract Compliance Regulations, pursuant to 49.35 of the regulations cited above (relating to information concerning compliance by contractors). If CONTRACTOR does not possess documents or records reflecting the necessary information requested, it shall furnish such information on reporting forms supplied by the contracting agency, the Bureau of Affirmative Action or the

COMMISSION.

8. CONTRACTOR shall actively recruit minority subcontractor or subcontractors with substantial minority representation among their employees.

9. CONTRACTOR shall include the provisions of the non-discrimination clause in every subcontract, so that such provisions will be binding upon each subcontractor.

10. The terms used in this non-discrimination clause shall have the same meaning as in the Contract Compliance Regulations issued by the Pennsylvania Human relations Commission, 16 PA Code Chapter 49.

11. CONTRACTOR obligations under this clause are limited to the Contractor’s facilities within Pennsylvania, or, where the contract is for the purchase of goods manufactured outside of Pennsylvania, the facilities at which such goods are actually produced.

Note: The penalty for making false statements in offers is prescribed in 18 U.S.C. Section 1001.

Dated__________________, 20__ _________________________ (Name of Bidder)

Official Address By ____________________________ (Including Zip Code):

(Title)

00454-1

SECTION 00454 – SAFETY GUIDELINES AND REQUIREMENTS

1. The CONTRACTOR will be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the WORK. He will take all necessary precautions for the safety of, and will provide the necessary protection to prevent damage, injury or loss to all employees on the WORK and other persons who may be affected thereby, all the WORK and all materials or equipment to be incorporated therein, whether in storage on or off the site, and other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction.

2. The CONTRACTOR will erect and maintain, as required by the conditions and progress of the WORK, all necessary safeguards for safety and protection.