5-Contractor Schedule and Phasing Plan Requirements - York City Hall.pdf
PDF 67 KB Posted
- Solicitation number
- Not on record
- Issued by
- York County, Pennsylvania
About this file
This document is a Schedule and Phasing Plan Requirements file for the City of York, Pennsylvania's York City Hall Interiors Renovation project (Project No. 26103). The project encompasses interior renovation work divided into three separate prime contracts: Architectural, Electrical, and Plumbing. Sealed bids are due online via PennBid between 2:00 PM on July 29th and 2:00 PM on August 21st, with public opening and posting occurring immediately thereafter. A non-mandatory pre-bid meeting is scheduled for August 3rd at 10:00 AM at York City Hall, located at 101 South George Street, York, PA 17401. The anticipated construction duration is approximately 120 calendar days, with the specific completion timeline to be determined through the contractor's submitted construction schedule and phasing plan. Construction documents were prepared by Murphy & Dittenhafer Architects and are available at no cost through PennBid.
Each bidder must submit a certified check, cashier's check, or bid bond equal to 10 percent of the total bid amount, payable to the City of York. Contractors are required to submit a detailed proposed construction schedule and phasing plan with their bid for owner review and evaluation. The City of York is an Equal Opportunity Employer and reserves the right to reject any or all bids, reject portions thereof, or waive any informalities or irregularities in the bidding process. All required labor, materials, equipment, and incidentals necessary for completion of the York City Hall Interiors Renovation must be included in the bid proposals, which shall be submitted electronically through PennBid along with all required forms, bid security, and other documents specified in the bidding documents.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
York City Hall Interior Renovations 101 S George St, York, PA 17401 M&D Project 26103
Bid Phasing Requirements and Construction Parameters
York City Hall Interiors Renovation
101 S. George St, York PA 17401
General Requirements
The following requirements establish the Owner's minimum expectations for construction sequencing and phasing. The Contractor shall review all Contract
Documents, including the drawings, general notes, detail notes, schedules, and all other information contained within the bid documents, and shall submit a complete construction timeline and phasing plan with their bid. The submitted schedule and phasing plan shall represent the Contractor's intended approach to completing the Work and shall identify the anticipated sequence of operations, duration of each phase, trade coordination, and the Contractor's plan for maintaining the Owner's operations throughout construction. The submitted construction timeline and phasing plan shall be subject to Owner review, and any requested revisions shall be incorporated by the successful Contractor prior to commencement of the Work. Unless otherwise approved by the Owner, all work identified as requiring off-hours shall be performed outside of the
Owner's normal hours of operation, Monday through Friday, 7:00 AM to 5:00 PM.
Construction Phasing Requirements
The Contractor shall coordinate all construction activities to minimize disruption to the
Owner's ongoing operations. Window treatment installation, painting, carpet replacement, and installation of the acrylic glazing system at the reception counter shall be performed during off-hours unless otherwise approved by the Owner. The Contractor shall protect existing finishes, furnishings, equipment, and occupied spaces during all construction activities and shall return each work area to a safe, clean, and operational condition upon completion of each phase of work.
Restroom renovations shall be phased to maintain continuous restroom availability for building occupants. A maximum of one (1) set of restrooms shall be taken out of service at any given time. The Plumbing Contractor and Electrical Contractor shall coordinate with the Architectural General Contractor regarding their required work activities and shall provide anticipated durations necessary to complete each restroom renovation phase. The Architectural General Contractor shall coordinate all subcontractors and trade sequencing to allow each trade to mobilize, complete its work, and maintain the approved construction schedule. The General Contractor shall be responsible for coordinating all trade activities, inspections, restoration, and completion requirements prior to reopening each restroom area for Owner use.
Schedule and Coordination Requirements
York City Hall Interior Renovations 101 S George St, York, PA 17401 M&D Project 26103
The General Contractor shall maintain and manage the approved construction schedule throughout the duration of the project and shall coordinate all subcontractors to ensure the Work progresses in accordance with the approved phasing plan. Any proposed revisions to the construction schedule or phasing plan that may affect the Owner's operations shall be submitted to the Owner for review and approval prior to implementation. The Contractor shall provide timely notice of anticipated schedule impacts, delays, or changes affecting project sequencing.
Furniture Relocation Coordination
The Contractor shall coordinate with the Owner regarding the removal and relocation of furniture and other movable items within areas affected by construction. The Owner is willing to assist with the relocation of furniture, as needed, to facilitate completion of the
Work; however, the Contractor shall coordinate all furniture relocation activities, identify areas requiring access, and provide adequate advance notice to the Owner to minimize disruption to normal operations.