5--5- Unit Price Schedule- PAR132405 Hunter Park Trail Connection.docx

DOCX document 33 KB Posted

Attached to
SLCo PAR132405 Hunter Park Trail Connection - CONST
Solicitation number
SLCo PAR132405 Hunter Park Trail Connection - CONST
Issued by
Utah

About this file

This is a Unit Price Schedule document for Salt Lake County's Hunter Park Trail Connection construction project (PAR132405) in Utah. The project involves construction of a new concrete trail with site preparation, grading, and installation of hardscape elements, along with irrigation system adjustments and landscape restoration. The unit price schedule requires contractors to submit installed unit costs for 35 line items covering construction fencing, site clearing, asphalt and concrete removal, concrete sidewalks and curbs, stairs, asphalt paving, irrigation system components including various PVC and HDPE pipes, sprinkler heads, and planting materials including trees, groundcover, sod, and structural soil. The project includes a Base Bid and three Bid Alternates, with all disturbed areas requiring patching and repair. The schedule is to be submitted through the Online Solicitation System (OSS) and is dated April 2026.

The unit price schedule requires contractors to provide inclusive pricing for labor, materials, and overhead costs for each line item, valid for both additions and deletions during construction. Bid prices must be entered in dollars and cents for all 35 items, with an additional line for Other Items at the contractor's discretion. The schedule does not specify quantities, response deadlines, site visit requirements, or award dates within this document alone, as it functions as the pricing template to be completed by bidding contractors rather than the solicitation notice containing those administrative details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 2 – Document 2.0 Unit Price Schedule

County requires Contractor to submit the following installed unit costs, which include Contractor overhead and profit. Should the need arise to add or delete items during construction, the unit cost must be valid for either adding or deleting. This unit price schedule must be attached in the Online Solicitation System (OSS).

Item No.

Unit

Description of Item

Unit Bid Price Dollars Cents

1.
Linear Foot
Construction Fencing
2.
Square Foot
Clear and Grub
3.
Each
Inlet Protection
4.
Cubic Yard
Imported General Fill
5.
Cubic Yard
Excavated Cut Used as Fill On-Site
6.
Linear Foot
Saw Cut of Asphalt
7.
Linear Foot
Saw Cut of Concrete Sidewalk
8.
Linear Foot
Saw Cut of Concrete Curb and Gutter
9.
Square Foot
Removal and Haul Off of Asphalt Pavement Along Parking Lot
10.
Square Foot
Removal and Haul Off of Concrete Sidewalk
11.
Linear Foot
Removal and Haul Off of Concrete to Mow Curb

Site Improvements

12.
Square Foot
6” thick concrete sidewalk and base material, including all materials & labor incidental
13.
Linear Foot
Stairs with a handrail with base material, including all materials and labor incidental
14.
Square Foot
3” Asphalt complete with base material, including all materials and labor incidental
15.
Linear Foot
24” Spill Concrete Curb and Gutter and base material complete, including all materials & labor incidental
16.
Linear Foot
12” Concrete Mow Curb complete with base material, including all materials & labor incidental
17.
Linear Foot
12” Curb wall around plant bed
18.
Square Foot
ADA concrete ramp with handrail with base materials, including all materials and labor incidental

Irrigation System

19.
Each
6” Pop-Up with Spray Nozzle (per detail) including all materials and labor incidental
20.
Linear Foot
Two Wire Path with Conduit (per detail and specs) including all materials and labor incidental
21.
Each
Cable Fuse Device in 10” Round Valve Box (per specs) including all materials and labor incidental
22.
Linear Foot
1” PVC Schedule 40 Irrigation Pipe and Fittings (per detail and specs) including all materials and labor incidental
23.
Linear Foot
1-1/2” PVC Schedule 40 Irrigation Pipe and Fittings (per detail and specs) including all materials and labor incidental
24.
Linear Foot
2” HDPE PE4710 DR11 Pipe and Fittings (per detail and schedule) including all materials and labor incidental
25.
Linear Foot
3” HDPE PE4710 DR11 Pipe and Fittings (per detail and schedule) including all materials and labor incidental
26.
Linear Foot
4” HDPE PE4710 DR11 Pipe and Fittings (per detail and schedule) including all materials and labor incidental
27.
Linear Foot
6” HDPE PE4710 DR11 Pipe and Fittings (per detail and schedule) including all materials and labor incidental
28.
Linear Foot
Tracer Tape (per specs) including all materials and labor incidental

Planting and Landscape

29.
Each
Tree – 2” Caliper Deciduous and Staking – provide, plant, and establish
30.
Each
Groundcover – 4” pot – provide, plant, and establish
31.
Square Foot
New Sod for Turf Patch & Repair along all Irrigation Trenches and Disturbed Areas – provide, plant, and establish
32.
Square Foot
Fine Grading and Soil Prep
33.
Cubic Yard
Provide and Placement of Utelite Structural Soil, all materials and labor incidental
34.
Cubic Yard
Planting Soil Mix per specs, provide and installed

35.

Other Items (at contractor’s discretion)

Project _____________________________________

Name of Company Bidding __________________________________________________

April 2026