Bid Tab Summary

This document is a bid tabulation form for Boulder County Parks and Open Space Department (BCPOS) in Colorado for the Wally Toevs Helical Pier & Deck Support Installation project. The project involves the design and installation of helical pier supports for the Walden Ponds fishing pier structure, which experienced a structural failure in July 2025 when support posts shifted forward, causing deck joists to separate from the ledger board and resulting in partial collapse into the pond. The fishing pier has remained closed to the public since the incident. BCPOS is seeking a qualified helical pier specialty contractor to provide design submittal and complete installation services. The project scope takes priority given the public safety concerns and current closure status, with construction to commence as soon as finalized plans are available.

The bid tabulation form presents the comparative pricing and technical evaluation of submitted proposals from qualified contractors for the helical pier support system. The document serves as the official record of all bids received, allowing BCPOS to evaluate and compare contractor qualifications, proposed methodologies, and pricing structures to select the most qualified and cost-effective contractor to proceed with the redesigned and reconstructed fishing pier project that must also comply with current Americans with Disabilities Act requirements.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID TAB SECTION

Item Number Item Description Cost

1. Site prep and layout $____________

• Layout of helical pier and drilled footing locations.

•Installation of safety fence around the construction site perimeter.

• Set up Concrete Washout Area and Vehicle tracking control area.

2. Helical Piers $____________ Cost for the manufacturing and installation of all 28 helical piers and associated hardware needed to connect a 4x4 support post.

3. Drainage/Grading $____________ Cost of any necessary grading requirements to meet Project specifications.

4. Drilled Pier footings $____________

• Locating and drilling all 25 concrete footings.

• Removal of all excess dirt/soil, from drilling.

• Assembly and installation of footing rebar cages.

• Ordering and pouring concrete piers with cast-in-place 4x4 post anchors.

BID TOTAL $____________