5-10. Sample Score Sheet.doc
DOC document 84 KB Posted
- Solicitation number
- UDOT260084MP-1 - Re solicitation
- Issued by
- Utah
About this file
This is a Proposal Evaluation Score Sheet for the Utah Department of Transportation (UDOT) Fiber Optic and ATMS Construction Services Request for Proposals. The document outlines a three-stage evaluation process for contractors seeking to provide fiber optic maintenance, repair, and installation services. UDOT anticipates awarding multiple contracts under this solicitation, which will remain open for the state to accept additional contractor submissions at any time. The contract term extends through March 31, 2028, with no renewal options available. Contractors will be compensated on a line-item basis according to quantities of work performed, and all work must comply with Utah Department of Transportation standards and specifications.
The evaluation process consists of mandatory minimum requirements, technical proposal scoring, and cost proposal evaluation. Stage 1 requires contractors to pass three mandatory criteria: national certification in fiber optic installation, state certification in fiber optic installation, and certification in both Work Zone Safety and SWIP training. Contractors failing any mandatory requirement are eliminated from further consideration. Stage 2 allocates 60 points for technical evaluation across three criteria: demonstrated experience in fiber optic installation (40 points with 8x weight), staffing and equipment resources (10 points with 2x weight), and internal policies, safety standards, and quality control procedures (10 points with 2x weight). Stage 3 allocates 40 points based on cost proposals, with the lowest cost bidder receiving maximum cost points and other bidders receiving points calculated through a ratio formula comparing their cost to the lowest proposed cost. Proposals exceeding double the lowest cost receive no cost points. The total evaluation yields a maximum of 100 points possible.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 9-09. Submittal Form- Certifications- Yes No.docx | DOCX document | |
| 11-06. Submittal Form- Vendor Setup Form.pdf | ||
| 7-04. Delineator Std Specification.pdf | ||
| 3-07. Submittal Form- Business Confidentiality- Yes No.doc | DOC document | |
| 6-03. Items Listing MP Revision.docx | DOCX document | |
| 4-11. Map- Regional Map- UDOT Fiber RFP Region 4 Split.pdf | ||
| 10-02. Scope of Work.doc | DOC document | |
| 1-05. Submittal Form- Pricing- All Regions.xlsx | XLSX spreadsheet | |
| 2-08. Submittal Form- Attachment A- Standard Terms and Conditions- Yes No.docx | DOCX document | |
| 8-01. RFP General Information- IN LIEU OF.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
Fiber Optic Maintenance, Repair, and Installation Proposal Evaluation Score Sheet
Firm Name:
Evaluator:
Date:
Stage 1: Determination of Responsiveness (Pass/Fail):
| Mandatory Minimum Requirements |
| Pass |
| Fail |
| Notes |
1. Contractor must be Nationally Certified in Fiber Optic Installation.
2. Contractor must be State Certified in Fiber Optic Installation.
3. Contractor must be certified in BOTH Work Zone Safety and SWIP training
Responses that fail in any of the above will not proceed on to the Technical Evaluation Stage.
Stage 2: Detailed Technical Evaluation (Scored):
Technical Evaluation
| EVALUATION CRITERIA |
| Points Possible |
| Score |
(1 - 5)
| Weight |
| Points |
1. Experience
| · Demonstrated Experience in Fiber Optic Installation |
| 40 points |
X 8
2. Resources
| · Staffing and equipment resources to address project work under this contract in a timely manner. |
| 10 points |
X 2
3. Policies
| · Internal policies, safety standards and plan, and quality control procedures to minimize mistakes, ensure a safe work environment, and ensure high quality construction. |
| 10 points |
X 2
Total Technical Evaluation Points (60 points possible)
Stage 3: Cost Proposal Evaluation (Scored):
Cost Evaluation
| Evaluation Criteria |
| Points Possible |
| Points |
| · Total Project Cost (predetermined sample project) |
| 40 points |
| *Inserted by UDOT Procurement |
Total Cost Evaluation Points (40 points possible)
TOTAL EVALUATION POINTS (100 POINTS POSSIBLE)
Evaluation of Cost Proposals: The offeror with the lowest total cost will receive the maximum available Cost points. All other offerors will receive points as determined by the ratio* of their cost to the lowest offered cost. Final cost scores will be calculated based on the following:
*Ratio Calculation: Points assigned to each offeror’s Cost Proposal will be based on the Lowest Proposed Cost. The offeror with the Lowest Proposed Cost will receive 100% of the cost points. All other offerors will receive a portion of the total cost points based on what percentage higher their proposed cost is than the Lowest Proposed Cost. An Offeror whose proposed cost is more than double (200%) the Lowest Proposed Cost will receive no points. The formula to compute the points is: Cost Points x (2- (Proposed Cost/ Lowest Proposed Cost)).
SOLICITATION CRITERIA SCORE SUMMARY
| Final Selection Criteria |
| Max. Score Available |
| Stage 1: Mandatory Minimum Requirement |
| Pass/Fail |
| Stage 2: Technical Proposal |
| 60 |
| Stage 3: Cost Proposal |
| 40 |
| Total Solicitation Points Possible |
| 100 |
Scoring:
(a) Five points (Excellent): The proposal addresses and exceeds all of the requirements or criteria described in the RFP.
(b) Four points (Good): The proposal addresses all of the requirements or criteria described in the RFP and, in some respects, exceeds them.
(c) Three points (Satisfactory): The proposal addresses all of the requirements or criteria described in the RFP in a minimum satisfactory manner.
(d) Two points (Unsatisfactory): The proposal addresses the requirements or criteria described in the RFP in an unsatisfactory manner; or
(e) One point (Poor): The proposal inadequately addresses the requirements or criteria described in the RFP or cannot be assessed due to incomplete information; or
(f) Zero (Fail): The proposal fails to address the requirements or criteria described in the RFP or cannot be assessed due to missing information.
Score Sheet