This is a pricing submittal form for the Utah Department of Transportation (UDOT) Fiber Optic and ATMS Construction Services RFP, establishing line-item unit prices across five geographic regions (Region 1, Region 2, Region 3, Region 4-East, and Region 4-West). The document contains approximately 999 line items covering traffic control services, conduit installation, trenching, rock saw operations, directional boring, fiber optic cabling, splicing and testing, labor categories, removal and restoration work, environmental controls, and ITS equipment installation. Services span routine maintenance and repair work to specialized construction tasks such as bridge-attached conduit systems and underground utility installations. The solicitation anticipates multiple contract awards with a contract term extending through March 31, 2028, with no renewal options.
Contractors submit pricing on a line-item basis and are compensated according to actual quantities of work performed. The pricing structure differentiates costs by region, unit of measure (lump sum, per foot, per day, per hour, per each, etc.), and work scope complexity. Certain items are designated as project-specific work requiring bids following contractor shortlist selection, while others are priced as actual cost items. State-furnished materials and equipment are separately itemized, with installation costs distinguished from materials. The form indicates that some items carry "N/A" pricing designations, indicating they will be competitively bid or negotiated following initial contractor selection. This multi-region, line-item pricing structure allows UDOT to efficiently procure diverse construction services across the state while maintaining cost control and enabling comparative evaluation across geographic areas and service categories.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 9-09. Submittal Form- Certifications- Yes No.docx | DOCX document | |
| 11-06. Submittal Form- Vendor Setup Form.pdf | ||
| 7-04. Delineator Std Specification.pdf | ||
| 3-07. Submittal Form- Business Confidentiality- Yes No.doc | DOC document | |
| 6-03. Items Listing MP Revision.docx | DOCX document | |
| 4-11. Map- Regional Map- UDOT Fiber RFP Region 4 Split.pdf | ||
| 5-10. Sample Score Sheet.doc | DOC document | |
| 10-02. Scope of Work.doc | DOC document | |
| 2-08. Submittal Form- Attachment A- Standard Terms and Conditions- Yes No.docx | DOCX document | |
| 8-01. RFP General Information- IN LIEU OF.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing Per Region
Maintenance, Repair, and Installation of the ITS and Fiber Optic System
Region 1 Region 2 Region 3 Region 4- East Region 4- West
| NO | DESCRIPTION | UNIT | UNIT PRICE | ||||
| Traffic Control | |||||||
| 1 | Traffic Control for Work - Beyond the Shoulder - up to 1,000 feet | Lump | |||||
| 2 | Traffic Control for Work - Shoulder Operation - up to 1,000 feet | Lump | |||||
| 3 | Traffic Control for Work - Single Lane Closure - up to 1,000 feet | Lump | |||||
| 4 | Traffic Control for Work - Two Lane Closure - up to 1,000 feet | Lump | |||||
| 5 | Traffic Control in an Urban Intersection Under 50 MPH (TC-5) | Lump | |||||
| 6 | Traffic Control Temporary Pedestrian Access Reroute (TC-6) | Lump | |||||
| 7 | Traffic Control for Work - Project Specific (bid following contractor shortlist) | Project | N/A | N/A | N/A | N/A | N/A |
| 8 | Police Support | Invoice | N/A | N/A | N/A | N/A | N/A |
| 9 | Additional Advance Warning Arrow Panel | Dev/day | |||||
| 10 | Attenuator Truck | Hour | |||||
| 11 | Variable Message Sign (VMS) | Dev/day | |||||
| 12 | Rumble Strips | Day | |||||
| 13 | Flagging | Hr | |||||
| Conduit | |||||||
| 14 | 1 1/4 inch Conduit | Ft | |||||
| 15 | 2 inch Conduit | Ft | |||||
| 16 | 3 inch Conduit | Ft | |||||
| 17 | 1D Conduit | Ft | |||||
| 18 | 2D Conduit | Ft | |||||
| 19 | 4D Conduit | Ft | |||||
| 20 | 2 inch Galvanized Rigid Conduit | Ft | |||||
| 21 | 2 inch Liquidtight Flexible Conduit | Ft | |||||
| 22 | 4 inch Galvanized Rigid Conduit | Ft | |||||
| 23 | 4 inch Liquidtight Flexible Conduit | Ft | |||||
| 24 | 6 inch Galvanized Rigid Conduit | Ft | |||||
| 25 | 6 inch Liquidtight Flexible Conduit | Ft | |||||
| 26 | Individual 12.7/10mm Microduct | Ft | |||||
| 27 | Individual 16/13mm Microduct | Ft | |||||
| 28 | Three 12.7/10mm Microducts with one No. 14 Locate Wire | Ft | |||||
| 29 | 18/14mm Microduct Bundle | Ft | |||||
| 30 | No. 14 Locate Wire placed in New or Existing Conduit | Ft | |||||
| 31 | Detectable Pull Tape placed in Existing Conduit | Ft | |||||
| State Furnished Conduit | |||||||
| 32 | Install State Furnished Conduit (up to eight conduits, 3 inch diameter or less) | Ft | |||||
| 33 | Install State Furnished Conduit (more than eight conduits, 3 inch diameter or less) | Ft | |||||
| 34 | Install One State Furnished Microduct in Existing Conduit | Ft | |||||
| 35 | Install Three State Furnished Microducts in Existing Conduit | Ft | |||||
| Installation | |||||||
| 36 | Install State Furnished Conduit ( up to eight conduits, 3 inch diameter or less) Trench and Rock Saw adder for additional conduit placement up to a 4D, 16-1.25” conduits (or similar product bundle size) | Ft | |||||
| 37 | Trenching 3 feet Deep - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 38 | Trenching 3 feet Deep - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 39 | Trenching 3 feet Deep - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 40 | Trenching 3 feet Deep - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 41 | Trenching 5 feet Deep - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 42 | Trenching 5 feet Deep - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 43 | Trenching 5 feet Deep - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 44 | Trenching 5 feet Deep - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 45 | Trenching 4 feet Deep - In Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 46 | Trenching 4 feet Deep - In Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 47 | Trenching 4 feet Deep - In Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 48 | Trenching 4 feet Deep - In Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 49 | Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 50 | Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 51 | Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 52 | Rock Saw 26 inches Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 53 | Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 54 | Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 55 | Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 56 | Rock Saw 3 feet Deep and 5 inches Minimum Width - In/Outside of Pavement with Concrete Backfill - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 57 | Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 58 | Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 59 | Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 60 | Rock Saw 4 feet Deep and 5 inches Minimum Width - In Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 61 | Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 62 | Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 63 | Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 64 | Rock Saw 3 feet Deep and 5 inches Minimum Width - Outside Pavement - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 65 | Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - Up to 500 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 66 | Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - 500 Feet to 2,000 Feet, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 67 | Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavement - 2,000 Feet to 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 68 | Rock Saw 5 feet Deep and 5 inches Minimum Width - Outside Pavment - over 5 miles, up to 1D, 4-1.25” conduits (or similar product bundle size) | Ft | |||||
| 69 | Directional Bore - 4 inch Diameter Product Bundle - 0 Feet to 2,000 Feet | Ft | |||||
| 70 | Directional Bore - 4 inch Diameter Product Bundle - 2,000 Feet to 4,000 Feet | Ft | |||||
| 71 | Directional Bore - 4 inch Diameter Product Bundle - 4,000 Feet to 10,000 Feet | Ft | |||||
| 72 | Directional Bore - 4 inch Diameter Product Bundle - 10,000+ Feet | Ft | |||||
| 73 | Directional Bore - 8 inch Diameter Product Bundle - 0 Feet to 2,000 Feet | Ft | |||||
| 74 | Directional Bore - 8 inch Diameter Product Bundle - 2,000 Feet to 4,000 Feet | Ft | |||||
| 75 | Directional Bore - 8 inch Diameter Product Bundle - 4,000 Feet to 10,000 Feet | Ft | |||||
| 76 | Directional Bore - 8 inch Diameter Product Bundle - 10,000+ Feet | Ft | |||||
| 77 | Directional Bore - 12 inch Diameter Product Bundle - 0 Feet to 2,000 Feet | Ft | |||||
| 78 | Directional Bore - 12 inch Diameter Product Bundle - 2,000 Feet to 4,000 Feet | Ft | |||||
| 79 | Directional Bore - 12 inch Diameter Product Bundle - 4,000 Feet to 10,000 Feet | Ft | |||||
| 80 | Directional Bore - 12 inch Diameter Product Bundle - 10,000+ Feet | Ft | |||||
| 81 | 24 inch Wide Conduit Hanger Assembly between Bridge Girders | Ea | |||||
| 82 | 24 inch Wide Conduit Hanger Assembly under Bridge Deck Overhang | Ea | |||||
| 83 | Bridge Attached Conduit System - Project Specific (bid following contractor shortlist) | Project | N/A | N/A | N/A | N/A | N/A |
| 84 | 30' Wood Pole with Riser Standoffs | Ea | |||||
| 85 | 30' Wood Pole without Riser Standoffs and Ground Anchor | Ea | |||||
| 86 | 3/8" Aerial Strand with Aerial Microduct MD7 Attached to Existing Pole(s) | Ft | |||||
| 87 | Conduit Entry into Existing Building | Lump | |||||
| Proofing & Conduit Repair | |||||||
| 88 | Spot Repair 1 1/4 inch Conduit less than 100 feet | 10ft increment | |||||
| 89 | Spot Repair 2 inch Conduit less than 100 feet | 10ft increment | |||||
| 90 | Spot Repair 3 inch Conduit less than 100 feet | 10ft increment | |||||
| 91 | Spot Repair MD7 16/13 Microduct less than 100 feet | 10ft increment | |||||
| 92 | Spot Repair MD7 18/14 Microduct less than 100 feet | 10ft increment | |||||
| 93 | Spot Repair Individual Microduct (12.7/10 or 16/13) less than 100 feet | 10ft increment | |||||
| 94 | Spot Repair 1D Conduit less than 100 feet | 10ft increment | |||||
| 95 | Spot Repair 2D Conduit less than 100 feet | 10ft increment | |||||
| 96 | Spot Repair 4D Conduit less than 100 feet | 10ft increment | |||||
| 97 | Proofing Existing Conduit with State approved Mandrel | Ft | |||||
| 98 | Proof Existing Microduct | Ft | |||||
| Junction Boxes | |||||||
| 99 | Type I - Polymer Concrete Junction Box (24" Deep) | Ea | |||||
| 100 | Type II - Polymer Concrete Junction Box (24" Deep) | Ea | |||||
| 101 | Type III - Polymer Concrete Junction Box (24" Deep) | Ea | |||||
| 102 | Type II - Polymer Concrete Junction Box (36" Deep) | Ea | |||||
| 103 | Type III - Polymer Concrete Junction Box (36" Deep) | Ea | |||||
| 104 | Type II - High Density Polyethylene (HDPE) Junction Box (36" Deep) | Ea | |||||
| 105 | Type III - High Density Polyethylene (HDPE) Junction Box (36" Deep) | Ea | |||||
| 106 | Type II - Hybrid Junction Box (PC Body with HDPE lids) (36" Deep) | Ea | |||||
| 107 | Type III - Hybrid Junction Box (PC Body with HDPE lids) (36" Deep) | Ea | |||||
| 108 | Replace Type I - Polymer Concrete Junction Box Lid | Ea | |||||
| 109 | Replace Type II - Polymer Concrete Junction Box Lid | Ea | |||||
| 110 | Replace Type III - Polymer Concrete Junction Box Lid | Ea | |||||
| 111 | Replace Type II - HDPE Junction Box Lid | Ea | |||||
| 112 | Replace Type III - HDPE Junction Box Lid | Ea | |||||
| 113 | Concrete Collar for Type I - Junction Box | Ea | |||||
| 114 | Concrete Collar for Type II - Junction Box | Ea | |||||
| 115 | Concrete Collar for Type III - Junction Box | Ea | |||||
| 116 | Concrete Floor in Type I - Junction Box | Ea | |||||
| 117 | Concrete Floor in Type II - Junction Box | Ea | |||||
| 118 | Concrete Floor in Type III - Junction Box | Ea | |||||
| 119 | Type I Junction Box Precast Collar | Ea | |||||
| 120 | Type II Junction Box Precast Collar | Ea | |||||
| 121 | Type III Junction Box Precast Collar | Ea | |||||
| 122 | Remove Type I Junction Box | Ea | |||||
| 123 | Remove Type II Junction Box | Ea | |||||
| 124 | Remove Type III Junction Box | Ea | |||||
| 125 | Remove Junction Box Larger than Type III | Ea | |||||
| 126 | Grout or Epoxy Patching | Ea | |||||
| 127 | General Maintenance of Junction Box | Ea | |||||
| 128 | Pre-Cast Utility Vault (4'x4'x51") | Ea | |||||
| 129 | Pre-Cast Utility Vault (4'x6'-6"x84") | Ea | |||||
| 130 | Furnish and Install Locate Ball or Disk in Existing Junction Box | Ea | |||||
| 131 | Furnish and Install Maintenance Marker | Ea | |||||
| State Furnished Junction Boxes | |||||||
| 132 | Install State Furnished Type II Junction Box | Ea | |||||
| 133 | Install State Furnished Type III Junction Box | Ea | |||||
| Communication Cabling | |||||||
| 134 | Single Mode Non Armored Fiber Optic Drop Cable - 6 Strand - with Six Port Fiber Distribution Unit - 200 Feet (includes 200 feet of cable length) | Ea | |||||
| 135 | Single Mode Non Armored Fiber Optic Drop Cable - 6 Strand (additional cable length beyond 200 feet) | Ft | |||||
| 136 | Single Mode Non Armored Fiber Optic Drop Cable - 12 Strand - with Twelve Port Fiber Distribution Unit - 200 Feet (includes 200 feet of cable length) | Ea | |||||
| 137 | Single Mode Non Armored Fiber Optic Drop Cable - 12 Strand (additional cable length beyond 200 feet) | Ft | |||||
| 138 | Single Mode (Armored or Non Armored) Fiber Optic Cable - 12 Strand Count | Ft | |||||
| 139 | Single Mode (Armored or Non Armored) Fiber Optic Cable - 24 Strand Count | Ft | |||||
| 140 | Single Mode (Armored or Non Armored) Fiber Optic Cable - 72 Strand Count | Ft | |||||
| 141 | Single Mode (Armored or Non Armored) Fiber Optic Cable - 144 Strand Count | Ft | |||||
| 142 | Single Mode (Armored or Non Armored) Fiber Optic Cable - 288 Strand Count | Ft | |||||
| 143 | Single Mode Micro Fiber Optic Cable - 72 Strand | Ft | |||||
| 144 | Single Mode Micro Fiber Optic Cable - 144 Strand | Ft | |||||
| 145 | Single Mode Micro Fiber Optic Cable - 288 Strand | Ft | |||||
| 146 | Fiber Optic Cable Removal | Ft | |||||
| 147 | Cat 5e Cable | Ft | |||||
| State Furnished Communication Cabling | |||||||
| 148 | Install State Furnished Single Mode Micro Fiber Optic Cable | Ft | |||||
| 149 | Install State Furnished SMF Cable | Ft | |||||
| Splicing and Testing | |||||||
| 150 | Remove and Replace Fiber Optic Splice Enclosure | Ea | |||||
| 151 | Install Splice Enclosure | Ea | |||||
| 152 | Open and Close Existing Splice Case | Ea | |||||
| 153 | 1-6 Fusion Splices at one location | Ea Splice | |||||
| 154 | 7-12 Fusion Splices at one location | Ea Splice | |||||
| 155 | 13-48 Fusion Splices at one location | Ea Splice | |||||
| 156 | 49-96 Fusion Splices at one location | Ea Splice | |||||
| 157 | 97-144 Fusion Splices at one location | Ea Splice | |||||
| 158 | 144-288 Fusion Splices at one location | Ea Splice | |||||
| 159 | Install 72 CT Patch Panel in Building | Ea | |||||
| 160 | Install 144 CT Patch Panel in Building | Ea | |||||
| 161 | Install 288 CT Patch Panel in Building | Ea | |||||
| 162 | Terminate Patch Panel | Ea Strand | |||||
| 163 | Terminate ST Connector / Anerobic | Ea | |||||
| 164 | Bare End Fiber Optic Test | Ea Strand | |||||
| 165 | Fiber Optic Light Source/Power Meter Test and OTDR Trace | Ea | |||||
| Labor | |||||||
| 166 | Labor - Technician | Hr | |||||
| 167 | Labor Emergency Rate - Technician | Hr | |||||
| 168 | Labor- Journeyman Electrician | Hr | |||||
| 169 | Labor - Electrician Technician | Hr | |||||
| 170 | Locating of UDOT infrastructure | Hr | |||||
| 171 | Locating of UDOT infrastructure | Day | |||||
| Removal and Restoration | |||||||
| 172 | Subsurface Utility Exploration - Vacuum Excavation - Pot Holes | Ea | |||||
| 173 | Subsurface Utility Exploration - Mechanical Excavation - Pot Holes | Ea | |||||
| 174 | Trench Backfill in Pavement | Cu Ft | |||||
| 175 | Remove and Replace HMA Surface, up to 4,000 square feet | Sq Ft | |||||
| 176 | Place HMA Surface/ Roto mill - Project specific (bid following contractor shortlist) | Project | N/A | N/A | N/A | N/A | N/A |
| 177 | Asphalt Repair (HMA) | Actual Cost | N/A | N/A | N/A | N/A | N/A |
| 178 | Sand | Tons | |||||
| 179 | Free Draining Granular Backfill Borrow | Tons | |||||
| 180 | Untreated Base Course | Tons | |||||
| 181 | Geotextile ( Separation or Stabilization) | Sq Yd | |||||
| 182 | Flowable Fill | Cu Yd | |||||
| 183 | Concrete Curb (any type) - Less than 50 feet | Ft | |||||
| 184 | Concrete Curb (any type) - Greater than 50 feet | Ft | |||||
| 185 | Concrete Flatwork | Sq Ft | |||||
| 186 | Furnish/Install Chain Link Fencing | Actual Cost | N/A | N/A | N/A | N/A | N/A |
| 187 | Striping/Pavement Markings | Actual Cost | N/A | N/A | N/A | N/A | N/A |
| 188 | Remove and Replace Sidewalk | Sq Ft | |||||
| 189 | Remove and Replace Stamped Decorative Surface | Sq Ft | |||||
| 190 | Remove and Replace Curb and Gutter | Ft | |||||
| 191 | Install and Remove Temporary Cold Patch | Sq Ft | |||||
| 192 | Pavement Marking Paint - 4 inch White or Yellow | Ft | |||||
| 193 | Pavement Marking Tape - 4 inch White or Yellow | Ft | |||||
| 194 | Remove and Replace Landscaping | Sq Ft | |||||
| 195 | Remove and Re-Install Existing Delineator Post | Ea | |||||
| 196 | Remove Existing Delineator Post | Ea | |||||
| 197 | Delineator Post - Steel | Ea | |||||
| 198 | Delineator Post - Flexible Plastic | Ea | |||||
| Environmental Controls | |||||||
| 199 | Temporary Erosion and Sediment Control - Check Dam | Ft | |||||
| 200 | Temporary Erosion and Sediment Control - Silt Fence Slope Barrier | Ft | |||||
| 201 | Temporary Erosion and Sediment Control - Slope Drain | Ft | |||||
| 202 | Temporary Erosion and Sediment Control - Drop Inlet Barrier | Ft | |||||
| 203 | Temporary Erosion and Sediment Control - Sediment Trap | Cu Ft | |||||
| 204 | Temporary Erosion and Sediment Control - Curb inlet Barrier | Ft | |||||
| 205 | Temporary Erosion and Sediment Control - Temporary Berm | Ea | |||||
| 206 | Temporary Erosion and Sediment Control - 9 inch Fiber Roll | Ft | |||||
| 207 | Broadcast Seed | 1000 Sq Ft | |||||
| 208 | Drill Seed | 1000 Sq Ft | |||||
| 209 | Environmental Control Supervisor (ECS) | Week | |||||
| Contractor Furnished ITS Equipment Installation | |||||||
| 210 | ITS Cabinet Foundation | Ea | |||||
| 211 | CCTV Pole Foundation | Ea | |||||
| 212 | Highway Luminare Pole Foundation | Ea | |||||
| 213 | Underground Service Pedestal - New Installation w/ Base | Ea | |||||
| 214 | H-Frame (Complete) | Ea | |||||
| 215 | Electrical Disconnect on Existing H-Frame | Ea | |||||
| 216 | Transformer on Existing H-Frame | Ea | |||||
| 217 | Install Solar Panel Assembly | Ea | |||||
| 218 | Install Solar Batter Assembly | Ea | |||||
| 219 | RHH-USE2-RHW2, AWG 2-6 (copper) | Ft | |||||
| 220 | RHH-USE2-RHW2, AWG 8-12 (copper) | Ft | |||||
| 221 | RHH-USE2-RHW2, AWG 14 (copper) | Ft | |||||
| 222 | Bare Copper Ground Wire, No. 6 | Ft | |||||
| 223 | Ground Rod 3/4" x 10' | Ft | |||||
| State Furnished ITS Equipment Installation | |||||||
| 224 | 334 ATMS Cabinet | Ea | |||||
| 225 | Pole Mount 336 ITS Cabinet | Ea | |||||
| 226 | CCTV Pole - 45 feet | Ea | |||||
| 227 | CCTV Pole - 60 - 80 feet | Ea | |||||
| 228 | Highway Luminare Pole | Ea | |||||
| 229 | CCTV Assembly | Ea | |||||
| 230 | Non-Intrusive Detector Assembly | Ea | |||||
| 231 | IP Radio Assembly | Ea | |||||
| 232 | Solar Panel Assembly | Ea | |||||
| 233 | Solar Battery Assembly | Ea | |||||
| Incidental Materials | |||||||
| 997 | Pick up and delivery of UDOT materials ( small loads, pick up truck ) | Mile | |||||
| 998 | Pick up and dellivery of UDOT materials ( Large loads, semi truck ) | Mile | |||||
| 999 | Incidental Items | Invoice | N/A | N/A | N/A | N/A | N/A |