APPENDIX B: PAST PERFORMANCE QUESTIONNAIRE (PPQ)
The Contractor shall complete the company specific information on this form, contact their clients, forward this form to their clients and request that their clients complete it (verify/concur and score) and send it via email to Sarah.Connor@gsa.gov with the Subject “47PK0222Q0008 - PPQ for ENTER CONTRACTOR’S NAME” by the required quote due date and time.
Past Performance Information:
Contractor Name: _______________________________________________________
Contract Title/Number: ___________________________________________________
Prime Contractor: Yes________ No__________
Building Information Building Type: __________________________________________________________
Square Footage: _______________________ Total Floors: ______________________
Building Address: _______________________________________________________
City/State/Country: ______________________________________________________
Year(s) Service Provided: From _____________________ To ____________________
Brief description of requirement:
The Performance measures are as follows:
1. QUALITY:
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
3. CUSTOMER SATISFACTION:
4. MANAGEMENT EFFECTIVENESS:
5. GENERAL:
The adjectival rating categories are provided below for your guidance.
| EXCELLENT: |
| Contractor demonstrates initiative to enhance/exceed contractual requirements/objectives and overall Contractor-Government relationship is exceptional. |
| VERY GOOD: |
| There are no quality-of-service problems and/or nonconformance does not impact achievement of contract goals. |
| SATISFACTORY: |
| Nonconformance is minor and have little impact on achievement of contract goals; minor Government intervention is needed to resolve issues |
| MARGINAL: |
| Nonconformance is impacting achievement of contract goals; substantial Government intervention is needed to resolve issues. |
| UNSATISFACTORY: |
| Nonconformance is compromising the achievement of contract goals, despite substantive intervention by Government personnel. |
TECHNICAL EFFECTIVENESS/TIMELINESS OF PERFORMANCE
This area of the questionnaire deals with contract compliance, requirements, to include appropriateness of personnel and technical excellence and the Contractor’s ability to meet milestones and delivery schedules.
LEGEND:
E = Excellent VG = Very Good S = Satisfactory M = Marginal U = Unsatisfactory N/A = Not applicable
1. QUALITY:
E
VG
S
M
U
N/A
a) Quality of technical data/report preparation efforts
b) Ability to meet quality standards specified for technical performance
c) Timeliness/effectiveness of contract problem resolution without extensive customer guidance
d) Adequacy/effectiveness of quality control program and adherence to contract quality assurance requirements (without adverse effect on performance)
Please provide comments to substantiate the assigned rating. At a minimum, provide comments to substantiate any rating that is checked Exceptional (E), Very Good (VG), Marginal (M), Unsatisfactory (U) or Not Applicable (N).
E = Excellent VG = Very Good S = Satisfactory M = Marginal U = Unsatisfactory N/A = Not applicable
2. SCHEDULE/TIMELINESS OF PERFORMANCE:
E
VG
S
M
U
a) Compliance with contract delivery/completion schedules including any significant intermediate milestones. (If liquidated damages were assessed or the schedule was not met, please address below)
b) Rate the Contractor's use of available resources to accomplish tasks identified in the contract
Please provide comments to substantiate the assigned rating. At a minimum, provide comments to substantiate any rating that is checked Exceptional (E), Very Good (VG), Marginal (M), Unsatisfactory (U) or Not Applicable (N).
MANAGEMENT EFFECTIVENESS
This area deals with the Contractor’s overall communications with the government, effectiveness and reliability of key personnel, ability to recruit and maintain qualified personnel, ability to manage multiple and diverse projects from planning through execution, accurate estimate and control cost, overall performance in planning, scheduling and monitoring, management initiatives and prompt notification of problems.
E = Excellent VG = Very Good S = Satisfactory M = Marginal U = Unsatisfactory N/A = Not applicable
3. CUSTOMER SATISFACTION:
VG
S
M
U
a) Quality of technical data/report preparation efforts
a) To what extent were the end users satisfied with the project?
b) Contractor was reasonable and cooperative in dealing with your staff (including the ability to successfully resolve disagreements/disputes; responsiveness to administrative reports, businesslike and communication)
c) To what extent was the contractor cooperative, businesslike, and concerned with the interests of the customer?
Please provide comments to substantiate the assigned rating. At a minimum, provide comments to substantiate any rating that is checked Exceptional (E), Very Good (VG), Marginal (M), Unsatisfactory (U) or Not Applicable (N).
E = Excellent VG = Very Good S = Satisfactory M = Marginal U = Unsatisfactory N/A = Not applicable
4. MANAGEMENT:
VG
S
M
U
a) Effectiveness of on-site management, including management of subcontractors, suppliers, materials, and/or labor force?
b) Ability to hire, apply, and retain a qualified workforce to this effort
c) Government Property Control
d) Knowledge/expertise demonstrated by contractor personnel
e) Utilization of Small Business concerns
f) Ability to simultaneously manage multiple projects with multiple disciplines
g) Ability to assimilate and incorporate changes in requirements and/or priority, including planning, execution and response to Government changes
h) Effectiveness of overall management (including ability to effectively lead, manage and control the program)
I) Effectively transition personnel and operations when taking over from the incumbent contractor?
Please provide comments to substantiate the assigned rating. At a minimum, provide comments to substantiate any rating that is checked Exceptional (E), Very Good (VG), Marginal (M), Unsatisfactory (U) or Not Applicable (N).
E = Excellent VG = Very Good S = Satisfactory M = Marginal U = Unsatisfactory N/A = Not applicable
5. GENERAL:
VG
S
M
U
a) Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
b) Compliance with contractual terms/ provisions (explain if specific issues)
c) Would you hire or work with this firm again? (If no, please explain below)
d) In summary, provide an overall rating for the work performed by this contractor
Please provide comments to substantiate the assigned rating. At a minimum, provide comments to substantiate any rating that is checked Exceptional (E), Very Good (VG), Marginal (M), Unsatisfactory (U) or Not Applicable (N).
PAST PERFORMANCE QUESTIONNAIRE REFERENCE INFORMATION
Information Provided By:
1. Name:
2. Position Title/Grade:
3. Organization:
4. Mailing Address:
5. Telephone/Fax Numbers:
6. Length of Involvement in Contract:
7. Questionnaire Completion Date:
8. Remarks on outstanding performance: (Continue on separate sheet if necessary)
9. Remarks on unsatisfactory performance: (Continue on separate sheet if necessary)
- 139 -